Citation : 2023 Latest Caselaw 2180 j&K
Judgement Date : 6 October, 2023
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
Reserved on: 29.09.2023
Pronounced on: 06.10.2023
AA No.3/2022
Jammu Development Authority through its
Vice-Chairperson, Vikas Bhawan, Rail Head Complex,
Jammu.
...Appellant(s)
Through:- Mr. Adarsh Sharma, Advocate
Versus
Saral Sugam Sewa Society, D-5, 348, Sangam Vihar,
New Delhi, 62 through its State Secretary, J&K, 47-A, 2nd Extension,
Gandhi Nagar, Jammu.
... Respondent
Through:- Ms. Shivani Jalali, Advocate
Coram: HON'BLE MR. JUSTICE SANJEEV KUMAR, JUDGE
HON'BLE MR. JUSTICE PUNEET GUPTA, JUDGE
JUDGMENT
Sanjeev Kumar-J
1. This appeal under Section 37 of the J&K Arbitration and
Conciliation Act, 1997 ["the Act"] arises from the judgment
dated 03.11.2021 passed by a Single Bench of this Court in an
application filed under Section 34 of the Act titled Jammu
Development Authority v. Saral Sugam Sewa Society, whereby the application of the appellant-authority for setting aside an
award of the sole arbitrator has been dismissed.
2. Before we advert to the grounds of challenge urged by the
learned counsel appearing for the appellant-authority, we deem it
appropriate to state few material facts germane to the disposal of
this appeal.
3. The appellant entered into an agreement/Memorandum of
Understanding (MOU) with the respondent-society on
15.12.2008 to undertake the work of operation, management and
maintenance of 28 public toilets on pay and use basis for a period
of five years. The contract was to commence w.e.f. 22.12.2008
and was to remain valid till 21.12.2013. It is important to note
that prior to the appellant-authority entering into MOU with the
respondent-society, the appellant-authority had an arrangement
on similar lines with M/s Sulabh International Social Service
Organization [M/s Sulabh International"] in terms of MOU
executed on 14.02.2006 for maintenance and operation of public
toilets on 22 sites. The aforesaid arrangement was later on
terminated by the appellant vide order No.SE/JDA/2471-75
dated 16.12.2008.
4. Feeling aggrieved, M/s Sulabh International filed two writ
petitions before the learned Single Bench; one challenging the
MOU entered by the appellant with the respondent-society; and
the other challenging the order of the appellant dated 16.12.2008
terminating the arrangement with it. M/s Sulabh International
succeeded in obtaining interim relief in both the writ petitions.
As per the claim of the respondent-society, which is not refuted
by the appellant, possession of all twenty eight sites was handed
over to the respondent on 22.12.2008. The respondent further
claimed that after passing of the interim directions by the Court,
M/s Sulabh International assisted by the officers of the appellant-
authority took back the possession of twenty two sites
24.12.2008 and the respondent-society was left only with six
sites. On the contrary, case of the appellant is that the
respondent-society, which was handed over six sites, could not
operate and maintain the public toilets even on these sites.
5. Having regard to the respondent-society‟s failure to maintain
even six sites, the appellant-authority vide its communication
No.JDA/Litg./2010/ 440 dated 12.05.2010 called upon the
respondent to discuss the matter and for taking decision to make
an alternative arrangement for maintenance of public toilets at
litigation free six sites. On failure of the respondent-society to
attend the office of the appellant-authority, the respondent-
society was put on notice to show cause as to why the contract
allotted in its favour be not cancelled. Having found no response
from the respondent-society, appellant-authority, claimably
acting in larger public interest and public convenience, cancelled
the arrangement/MOU made with the respondent-society and
revived the arrangement already made with M/s Sulabh
International with additional conditions by withdrawing the order
of termination of M/s Sulabh International passed on 15.12.2008.
However, the respondent-society, feeling aggrieved of such
action of the appellant-authority, challenged its termination as
also the revival of MOU with M/s Sulabh International by filing
OWP No.1154/2010. The writ petition was opposed by the
appellant by filing its objections.
6. Be that as it may, while the writ petition was pending
consideration of the learned Single Judge, the appellant-authority
and the respondent-society arrived at an agreement that the
claims of the respondent-society arising out of the MOU dated
15.12.2008 may be adjudicated upon by Sh. Sunil Sethi, Senior
Advocate as sole arbitrator. Learned Single Judge took note of
the agreement arrived at between the parties and accordingly,
disposed of OWP No.1154/2010 referring the respondent-society
and the appellant-authority to arbitration. Pursuant to the notice
issued by the arbitrator, both the parties caused their appearance
before the learned Arbitrator. The respondent-society filed its
claims before the learned Arbitrator with the following reliefs:-
a) To revoke/revive the contract dated 15.12.2008 entered
into between the appellant-authority and the respondent-
society for operation and maintenance of as many as 28
toilet blocks situated across the entire Jammu city.
b) To allow the respondent-society to work on the sites,
which were allotted to them vide MOU dated 15.12.2008.
c) Any other relief, order or direction which the Arbitrator
deems fit and appropriate in the nature and circumstances
of the instant case.
7. The disputes which were highlighted by the respondent-society
in its claims were enlisted from (A) to (E) of para 9 under the
heading „List of Disputes'. The appellant-authority filed its
objections/written statement but did not raise any counter claim.
The evidence was led by the respondent-society in the shape of
an affidavit executed by one Sh. Gauri Shanker, Secretary of the
respondent-society. The appellant-authority also produced
evidence in rebuttal and placed on record affidavit of one
T.R.Sargotra, Superintending Engineer.
8. It seems that during the course of hearing learned counsel
appearing for the respondent-society produced certain
documents, which were taken on record by the learned arbitrator.
To substantiate the documents, the respondent-society produced
another affidavit by way of evidence executed by Sh. Gauri
Shanker, Secretary of the respondent-society. In this second
affidavit sworn in by Gouri Shanker on behalf of the respondent-
society fresh claims to the tune of Rs.47,64,925/- on various
heads, which included a claim of compensation for the damage
suffered by the respondent-society, were also put forth.
Appellant-authority objected to the filing of second affidavit and
filed its reply affidavit. The Vice-Chairperson, JDA in her
affidavit also refuted the fresh clams put forth by the respondent-
society.
9. Learned Arbitrator considered the entire matter and came to the
conclusion that the respondent-society had not been fairly treated
and the contract entered into with it by the appellant-authority
was wrongfully terminated. The arbitrator did not allow the
respondent-society to continue with the operations for balance
period of the contract for the reason that M/s Sulabh
International was not party to the arbitration and was executing
the contract qua all the 28 toilet blocks pursuant to the revival of
their contract and cancellation of the MOU with the respondent-
society. The arbitrator, however, agreed with the respondent-
society that on account of this action of the appellant-authority,
respondent-society had suffered loss. The claims put forth by the
respondent-society by way of evidence affidavit were accepted
with modification and the respondent-society was held entitled to
a sum of Rs.34,23,473/- along with interest @ 9% to be reckoned
w.e.f. 02.05.2012 till realization of the amount. Accordingly, the
Arbitrator passed its award on 02.01.2013.
10. The Jammu Development Authority did not accept the award of
the Arbitrator and filed a petition under Section 34 of the Act
before the learned Single Bench. The award of the arbitrator was
assailed by the appellant-authority on following grounds:-
i) That the award passed by the learned Arbitrator is in
conflict with the public policy of the State.
ii) The Arbitrator awarded compensation to the respondent-
society in respect of claims, which were neither pleaded
nor projected either in the writ petition or in the claims
filed before the Arbitrator.
iii) The award is bad in the eye of law for the simple reason
that the second affidavit filed by the respondent-society
was taken on record by the Arbitrator after the evidence
stood closed and the matter was being finally heard by the
Arbitrator.
iv) That the Arbitrator did not spell out reasons in support of
its conclusion that there was breach of contract committed
by the appellant-authority in cancelling the MOU entered
by it with the respondent-Society.
v) That no award for compensation in favour of the
respondent-society could have been passed without first
quashing the order of cancellation of MOU dated
15.12.2008 entered into between the appellant-authority
and the respondent-society and also without terminating
the arrangement made with M/s Sulabh International by
reviving its earlier contract.
11. It was urged that the respondent-society could not have been
granted such relief without M/s Sulabh International being party
in the arbitration and without providing an opportunity of being
heard. The arbitrator has noticed this aspect and expressed his
inability to put the respondent-society back in the execution of
the work without first declaring the arrangement made by the
appellant-authority with M/s Sulabh International bad in the eye
of law.
12. The petition was opposed by the respondent-society. The learned
Single Judge considered the entire matter and did not find any
merit in the petition filed by the appellant-authority. Learned
Single Judge after discussing the entire matter in light of the rival
contentions addressed before it, came to the conclusion that the
appellant-authority had failed to show any perversity or error of
fact or law apparent on the face of the record. Vide order and
judgment impugned in this appeal, the petition filed by the
appellant-authority under Section 34 of the Act was dismissed.
13. The appellant-authority is aggrieved and has called in question
the impugned judgment as also the award of the sole Arbitrator
Sh. Sunil Sethi, Senior Advocate on the ground, which it had
pleaded and urged before the learned Single Judge.
14. Heard learned counsel for the parties and perused the material on
record.
15. First, the facts which are not in dispute before us.
16. Indisputably, an agreement/MOU was entered into by the
appellant-authority with the respondent-society on 15.12.2008 to
undertake the work of operation, management and maintenance
of 28 public toilets for a period of five years commencing from
22.12.2008. At the time of execution of MOU dated 15.12.2008
with respondent-society the appellant-authority had an
arrangement with M/s Sulabh International in terms of MOU
executed between them on 14.02.2006. This was, however, in
respect of 22 sites. This arrangement was later on terminated by
the appellant-authority vide its order dated 15.12.2008. Feeling
aggrieved, M/s Sulabh International challenged the MOU dated
15.12.2008 entered between by the appellant-authority with
respondent-society as also the order of termination of its
arrangement dated 15.12.2008 by filing two writ petitions
bearing OWP Nos.1018/2008 and 1039/2008. In OWP
No.1018/2008, the order of termination of contract with M/s
Sulabh International passed by the appellant-authority dated
15.12.2008 was stayed. In OWP No.1039/2008, the appellant-
authority was directed not to withdraw the works allotted to M/s
Sulabh International for all sites without resorting to due course
of law and the rules governing the subject. These directions were
passed on 23.12.2008 and 24.12.2008 respectively.
17. Because of the interim directions passed in twin petitions filed by
M/s Sulabh International, 22 sites out of 28 sites allotted to the
respondent-society vide MOU dated 15.12.2008 could not be
operationalized by the respondent-society. The respondent-
society, it seems, took over the operation of 28 sites on
22.12.2008 but in view of the interim directions passed in the
writ petitions filed by M/s Sulabh International, M/s Sulabh
International took over the operation and maintenance of 22 sites
which were subject matter of MOU dated 14.02.2006 entered
into between the appellant-authority and the said society.
18. The petitions filed by M/s Sulabh International remained pending
for almost two years. M/s Sulabh International continued to
operate and maintain 22 sites whereas six litigation free sites
only were handed over to the respondent-society for operation
and maintenance. It has amply come on record that the
respondent-society had been showing its inability to pay the
agreed annual sum of Rs.51000/- per site on the ground that
these sites were less frequented by public and, therefore, not
generating enough revenue. The appellant-authority called upon
the respondent-society to come forward and discuss the matter.
However, this was not responded by the respondent-society. The
appellant-authority even put the respondent-society on show
cause notice as to why the arrangement made with it for carrying
out operation and maintenance of the six sites be not terminated.
19. Indisputably, no reply was given by the respondent-society to the
show cause notice. This paved the way for the appellant-
authority to cancel the contract. It is true that the contract/MOU
dated 15.12.2008 was terminated by the appellant-authority only
after M/s Sulabh International agreed to withdraw both the writ
petitions on account of some assurance extended by the
appellant-authority. It is pertinent to note that both the writ
petitions filed by M/s Sulabh International came to be dismissed
as withdrawn vide order dated 27.08.2010. .It has also come on
record that after withdrawal of the writ petitions and the vacation
of the interim directions, respondent-society approached the
appellant-authority for allotment of all the sites which were
subject matter of MOU dated 15.12.2008.
20. It is further seen that the appellant-authority with a view to come
out of the litigation launched against it by M/s Sulabh
International agreed with the later to revive the MOU entered
between the parties in the year 2006 with fresh conditions. It is in
these circumstances and probably having regard to the conduct
of the respondent-society, which had shown its inability to pay
the annual amount of Rs.51,000/- in respect of six litigation free
sites allotted to it, vide its communication/order dated
09.09.2010 terminated the MOU dated 15.12.2008 entered with
the respondent-society. This made the respondent-society to file
OWP No.1154/2010.
21. Indisputably, the entire thrust of OWP No.1154/2010, which was
filed, inter alia, against M/s Sulabh International also, was to
seek quashment of the order of termination bearing No.560-
61/General dated 09.09.2010 as well as order of the appellant-
authority bearing No.558-59/JDA/General dated 09.09.2010,
whereby the MOU entered between the appellant-authority and
M/s Sulabh International on 14.02.2006 had been revived after
withdrawing earlier order of termination dated 15.12.2008. In
essence, the respondent-society claimed restoration of status quo
ante after the dismissal of two writ petitions of M/s Sulabh
International as withdrawn.
22. The writ petition, as stated above, was objected to by the
appellant-authority. Interestingly, the appellant-authority and the
respondent-society without involving M/s Sulabh International,
third necessary party to the dispute, agreed before the Writ Court
for disposal of the writ petition referring the disputes raised by
the respondent-society to the arbitration of sole arbitrator,
namely, Sh. Sunil Sethi, senior advocate.
23. The appellant-authority and respondent-society appeared before
the arbitrator. The respondent-society reiterated its claim, as was
projected by it, in the writ petition. From a reading of the entire
claim petition, one would not find even a whisper with regard to
any claim for damages suffered by it except Clause (E) of para 9
under the heading "List of Disputes", which for facility of
reference is reproduced hereunder:-
"E) Is the petitioner organization is not entitled to any benefit in the form of damages from the JDA who has left the petitioner organization a non voluntary Organization high and dry and without any source of livelihood from the past three and a half years."
24. Apart from the aforesaid paragraph, one would not find even a
single word in respect of any damage suffered by the respondent-
society. There is no quantification of the damages nor any basis
laid down for such damages in the claim petition. And rightly so,
as the respondent-society was aware that they could not execute
the contract due to stay orders granted by the High Court.
25. Reading the disputes raised by the respondent-society in
paragraph No.9 and the prayer made before the Arbitrator
together, it would be beyond any cavil of doubt that the
respondent-society only claimed revival of its contract and
handing back the possession of 28 toilet blocks allotted to it vide
MOU dated 15.12.2008 and nothing more. It is to this extent, the
respondent-society led its evidence by placing on record an
affidavit sworn-in by one Gauri Shanker, the Secretary of the
respondent-society. The affidavit filed by the respondent-society,
by way of evidence, does not spell out any claim in respect of
damages suffered by it on account of any breach of contract.
Neither any specific claims are raised nor basis for such claims
indicated anywhere in the affidavit.
26. The sole grievance raised by the respondent-society before the
Writ Court as also before the learned Arbitrator was that after
withdrawal of the writ petitions filed by M/s Sulabh International
and vacation of the interim directions passed therein, the
respondent-society was entitled to the revival of its contract and
allotment of 28 sites which were subject matter of the MOU
dated 15.12.2008.
27. The appellant-authority filed its objections in rebuttal as also the
affidavit of Mr. S.R.Sargotra, Superintending Engineer by way
of evidence. As noted above, the appellant-authority did not raise
any counter claim. It is, thus, not in dispute that both the parties
submitted only one affidavit each by way of evidence to support
their claim and stand respectively.
28. To appreciate the argument of learned counsel for the appellant-
authority that the second affidavit filed by the respondent-society
was taken on record by the arbitrator after the evidence stood
closed and the matter was being finally heard, it would be
appropriate to take note of the certain orders passed by the
learned arbitrator. The orders, which are relevant for our
purposes, are reproduced hereunder:-
Order dated 26th August, 2012 read as follows:-
"Dated:-26-08-2012 Sh. Avinash Gupta Legal Asst from JDA Sh. Gauri Shanker from SOS Evidence affidavits have been filed by both the parties. Both the parties say that they don‟t desire to file any further documents/pleadings. The matter as such is kept for final arguments on the next date of hearing. The case to come up now 02.09.2012 at 10:00 am."
Order dated 2nd September, 2012
"Date:-02-09-2012 Mrs. Shivani Jalali Pandita Advocate for SSS Society. None for JDA.
The date was fixed today for final arguments. Mrs. Shivani Jalali Pandita has partly argued the matter and produced ten letters depicting the handing over of toilet blocks to her client. The same are taken on record. The matter will be heard further on 9th of September, 2012 at 1.30 pm. JDA is proceeded ex parte today because of its absence and there being no request for adjournment.
Matter to be taken up on 9th of September, 2012 at 1.30 pm."
On 9th September 2012, following order was passed by the arbitrator:-
"9-9-2012 Representatives of both parties present. Case fixed for further proceedings for 17/09/2012 at 6 pm. Ex-parte against JDA is set aside on oral request."
th Order dated 17 September, 2012:-
"17.9.2012
Mrs. Shivani Jalali Pandita
Sh. Avinash Gupta Matter fixed for 24-9-2012 at 5 pm for evidence of claimant."
Order passed on 24th September, 2012 reads thus:-
"Date:- 24-09-2012 Sh. Pankaj Sharma Legal Asst for JDA Sh. Gauri Shanker from SSS Society. Both the parties are present. The matter has been kept for further evidence on the next date of hearing which is fixed for 30.09.2012, as requested by both sides. Matter to be taken up on 30th of September, 2012 at 11.00 am."
On 30.09.2012, following order was passed:-
"30-9-2012 Mrs. Shivani Jalali Pandita for SSS Society Nemo for JDA Matter is kept for filing of additional evidence affidavit by SSS Society on 1-10-2012 at 7 pm."
Proceedings done on 1st October, 2012 read as follows:-
"Date:-01.10.2012 Mr. Pankaj Sharma Advocate for JDA Mrs. Shivani Jalali Pandita Advocate for SSS Society. Additional evidence affidavit has been filed by SSS Society today and statement is made b Mrs. Shivani Jalali Pandita
(Advocate) for the society that she does not want to file any further evidence.
JDA seeks one more opportunity to file evidence affidavit and same has been granted.
Let the matter to be taken up on 08.10.2012 at 7 pm."
On 8th October, 2012, following order came to be passed:-
"Date:-08-10-2012 Sh. Gauri Shanker from SSS Society Telephonic request has been made by Sh. Adarsh Sharma Advocate for JDA that he may be given some time to file reply affidavit to additional evidence affidavit filed by the claimant. Same is granted. Matter now to be taken on 11.10.2012 at 7.00pm by giving last opportunity to file reply affidavit to JDA."
On 11.10.2012, the order passed by the arbitrator is as follows:-
"11-10-2012 Sh. Pankaj Sharma Adv. for JDA Another opportunity for filing rreply affidavit is sought by JDA. Same is granted and the matter is fixed for 16-10-2012 at 7 p.m. for last and final opportunity to JDA to file reply affidavit.
Order announced."
Order dated 16th October, 2012 reads thus:-
"Date:- 16.10.2012 Mr. Vikas Pankaj Sharma Advocate for JDA Mr. Gauri Shanker for SSS Society. Reply evidence affidavit has been filed by JDA today and the copy has been provided to the other party. The matter now be taken up on 21.10.2012 at 8.30 am for final arguments. Let the matter to be taken up on 21.10.2012 at 8.30 am."
29. As is evident from the proceeding-sheets maintained by the
learned Arbitrator, the matter was fixed for final hearing on
02.09.2012. The arguments on behalf of the respondent-society
were addressed by Ms. Shivani Jalali on 02.09.2012. Since
arguments could not be concluded, the matter was posted for
further arguments on 9th September, 2012. It is pertinent to
mention here that during the course of arguments, learned
counsel appearing for the respondent-society placed before the
arbitrator in as many as 10 different documents without
providing copy thereof in advance to the other side. The
documents were taken on record by the learned Arbitrator vide
its order dated 02.09.2012. It seems that the respondent-society
of its own and without seeking permission or orders from the
Arbitrator filed additional affidavit on 01.10.2012. This affidavit
was also sworn-in by Gauri Shanker, Secretary of the
respondent-society and was second affidavit sworn-in by way of
evidence. It is through this evidence affidavit by the respondent-
society, some claims for damages for the first time came to be
raised.
30. It needs to be marked that respondent-society neither amended
the claim petition nor filed any supplementary claims with or
without permission of the learned Arbitrator. This move of the
respondent-society was seriously objected to by the appellant-
authority. In the reply affidavit filed by then Vice Chairperson,
Jammu Development Authority, the Arbitrator was urged to
reject the second affidavit in evidence filed on behalf of the
respondent-society. It was pleaded that by way of second
affidavit in evidence sworn-in by same person a new case cannot
be set up. It was specifically pleaded in reply affidavit by the
Vice Chairperson, JDA that the respondent-society had neither in
the writ petition nor in the claim petition filed before the
arbitrator claimed any damages and the same cannot be
permitted to be introduced by way of evidence. The claims of
respondent-society for damages projected in the second evidence
affidavit were also refuted on merits. It was specifically pleaded
on behalf of the appellant-authority that the toilet blocks 22 in
number were never operated and maintained by the respondent-
society and, therefore, no loss whatsoever was suffered by the
respondent-society. It was, thus, submitted that all the 28 toilet
blocks could not be handed over to the respondent-society
pursuant to the MOU dated 15.12.2008 because of the stay
granted by the High Court in the two writ petitions filed by M/s
Sulabh International. It was further submitted in the reply
affidavit that the respondent-society, which had been allotted six
litigation free toilet blocks could not operate and maintain even
the said blocks, constraining the appellant-authority to cancel the
contract with it.
31. The arbitrator, as is apparent from his award, did not carefully
read the reply affidavit and without there being any iota of
evidence concluded that the appellant-authority had not disputed
the claim of the respondent-society on merits. The learned
arbitrator did not even thought it fit to consider the objection
taken by the appellant-authority to the submission of second
affidavit in evidence of the same person i.e. Secretary of the
respondent-society and introduction of new case during the
course of evidence/hearing.
32. Learned arbitrator also did not advert to the objection of the
appellant-authority what when the matter was being heard finally
where was the necessity to allow the respondent-society to lead
further evidence and that too without there being any request
from the respondent-society and formal order from the arbitrator.
Learned arbitrator, we are aware, may not be bound by strict
rules of pleading and evidence but at the same time cannot throw
the basic norms of procedure to wind.
33. The manner in which the learned arbitrator has acted has not
only deprived the appellant -authority of its right to contest the
claims of the respondent-society but has caused serious
miscarriage of justice. The entire proceedings conducted by the
learned arbitrator suffer from perversity. The claim for damages
are not only required to be pleaded and indicated under different
heads but a sufficient foundation is also required to be laid in the
pleadings to substantiate such claims.
34. From a reading of the writ petition from where the reference to
the arbitrator has arisen and also the claim petition filed before
the arbitrator, it is abundantly clear that the respondent- society
never intended to raise any claim for damages against appellant
but only wanted revival of its contract and its continuation for
the remainder contract period. The respondent-society was aware
that it could not operate atleast 22 toilet blocks due to the interim
directions passed by the High Court in two writ petitions filed by
M/s Sulabh International. It, therefore, rested its claim only for
restoration of its contract on the ground that after dismissal of the
writ petitions and vacation of the interim directions, the
respondent-society was entitled to claim continuance of the
contract entered into with it by the appellant-authority vide MOU
dated 15.12.2008.
35. It seems that while arguing the matter, the respondent-society
was told that revival of its contract is not possible without first
cancelling the contract entered into by the appellant-authority
with M/s Sulabh International and such action was not possible
unless M/s Sulabh International was also a party to the
arbitration. Confronted with the aforesaid position, hurriedly and
without giving proper thought to the issue, another affidavit by
way of evidence was filed by the Secretary of the respondent-
society, who had earlier also filed an evidence affidavit in
support of the respondent-society‟s claim.
36. It is by virtue of second affidavit, which was unauthorizedly and
without permission of the arbitrator was filed during course of
the arguments, fresh claims for damages were raised. The Jammu
Development Authority specifically refuted the claims and
sought rejection of the second affidavit in evidence but for the
reasons best known to the arbitrator, serious objection raised by
the appellant authority was taken as admission of the fresh
claims projected by respondent-society by way of second
affidavit. This is how the learned arbitrator messed up the entire
proceedings and passed the award, which has not only travelled
beyond reference but also suffers from grave perversity, both
substantive and procedural.
37. Learned arbitrator could not have gone beyond the terms of
reference and awarded the sums not claimed in the claim petition
or supplemented by filing additional claims. There was
absolutely no opportunity granted to the appellant-authority to
object to the claims and their quantification and, therefore, in the
process, learned arbitrator also acted in violation of the principles
of natural justice and decided the claims of the respondent-
society without providing adequate opportunity to contest the
same to the appellant-authority.
38. Viewed from any angle, the award passed by the arbitrator
challenged before the learned Single Judge was bad in the eye of
law and liable to be set aside. Learned Single Judge did not
appreciate these aspects and landed in serious error in upholding
the award, which was not only against the public policy of the
State but was beyond the terms of reference and absolutely
perverse.
39. It is trite that an arbitral award can be annulled, if the arbitral
tribunal awards differently than the submission of the parties
(ultra or extra petita). When an arbitral tribunal passes an award
in disregard of some fundamental legal principles and thereby
renders such award incompatible with the essential and widely
recognized values on which Indian Judicial System edificed,
such arbitral award will violate public policy of State. No doubt,
a challenged award will only be set aside if it violates public
policy not merely in its reasoning but also in its result.
40. The meaning and import of "Public Policy of the State" is
elaborately discussed and explained in a recent judgment of the
Apex Court in Batliboi Environmental Engineers Limited v.
Hindustan Petroleum Corporation Limited and another, Civil
Appeal No.1968 of 2012 decided on 21.09.2023. Paragraph Nos.
38 to 43 are quite relevant and are set out below:-
"38. The expression „public policy‟ under Section 34 of the A&C Act is capable of both wide and narrow interpretation.
Taking a broader interpretation, this Court in ONGC Limited. v. Saw Pipes Limited., 26 held that the legislative intent was not to uphold an award if it is in contravention of
provisions of an enactment, since it would be contrary to the basic concept of justice. The concept of „public policy‟ connotes a matter which concerns public good and public interest. An award which is patently in violation of statutory provisions cannot be held to be in public interest. Thus, expanding on the scope and expanse of the jurisdiction of the court under Section 34 of the A&C Act, it was held that an award can be set aside if it is contrary to:
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality, or
(d) in addition, if it is patently illegal.
Nevertheless, the decision holds that mere error of fact or law in reaching the conclusion on the disputed question will not give jurisdiction to the court to interfere. However, this will depend on three aspects: (a) whether the reference was made in general terms for deciding the contractual dispute, in which case the award can be set aside if the award is based upon erroneous legal position; (b) this proposition will also hold good in case of a reasoned award, which on the face of it is erroneous on the legal proposition of law and/or its application; and (c) where a specific question of law is submitted to an arbitrator, erroneous decision on the point of law does not make the award bad, unless the court is satisfied that arbitrator had proceeded illegally. In the said case, the court set aside the award on the ground that the award had not taken into consideration the terms of the contract before arriving at the conclusion as to whether the party claiming the damages is entitled to the same. Reference was made to the provisions of Sections 73 and 74 of the Contract Act, which relate to liquidated damages, general damages and penalty stipulations. This view had held the field for a long time and was applied in subsequent judgments of this Court in Hindustan Zinc Ltd. v. Friends Coal Carbonisation, (2006) 4 SCC 445, Centrotrade Minerals and Metals Inc. v. Hindustan Copper Limited, (2006) 11
SCC 245, Delhi Development Authority v. R.S. Sharma and Co., (2008) 13 SCC 80, J.G. Engineers (P) Ltd. v. Union of India and Another, (2011) 5 SCC 758, and Union of India v. L.S.N. Murthy, (2012) 1 SCC 718.
39. In 2006, this Court in McDermott International Inc. despite following the ratio of Saw Pipes Limited, made succinct observations regarding the restrictive role of courts in the postaward interference. In addition to the three grounds introduced in Renusagar Power Co. Limited v. General Electric Co., 1994 Supp (1) SCC 644, as noticed above, an additional ground of „patent illegality‟ was introduced Saw Pipes Limited, for exercise of the court‟s jurisdiction in setting aside an arbitral award. This Court, in McDermott International Inc, held that patent illegality, must be such which goes to the root of the matter. The public policy violation should be so unfair and unreasonable as to shock the conscience of the court. Arbitrator where s/he acts contrary to or beyond the express law of contract or grants relief, such awards fall within the purview of Section 34 of the A&C Act. Further, what would constitute public policy is a matter dependent upon the nature of transaction and the statute. Pleadings of the party and material brought before the court would be relevant to enable the court to judge what is in public good or public interest, or what would otherwise be injurious to public good and interest at a relevant point. So, this must be distinguished from public policy of a particular government.
40. A similar view was expressed in Rashtriya Ispat Nigam Ltd. v. Dewan Chand Ram Saran, (2012) 5 SCC 306 with the clarification that where a term of the contract is capable of two interpretations and the view taken by the arbitrator is a plausible one, it cannot be said that the arbitrator travelled outside the jurisdiction or the view taken the arbitrator is against the terms of the contract. The court cannot interfere with the award and substitute its view with the award and interpretation accepted by the arbitrator, the reason being the
court does not sit in appeal over the findings and decision of the arbitrator, while deciding an application under Section 34 of the A&C Act. The arbitrator is legitimately entitled to take a view after considering the material before him/her and interpret the agreement. The judgment should be accepted as final and binding.
41. Subsequently, in ONGC Ltd. v. Western Geco International Ltd., (2014) 9 SCC 263 a three Judge Bench of this Court observed that the Court, in Saw Pipes Ltd., did not examine what would constitute „fundamental policy of Indian law‟. The expression „fundamental policy of Indian law‟ in the opinion of this Court includes all fundamental principles providing as basis for administration of justice and enforcement of law in this country. There were three distinct and fundamental juristic principles which form a part and parcel of „fundamental policy of Indian law‟. The first and the foremost principle is that in every determination by a court or an authority that affects rights of a citizen or leads to civil consequences, the court or authority must adopt a judicial approach. Fidelity to judicial approach entails that the court or authority should not act in an arbitrary, capricious or whimsical manner. The court or authority should act in a bona fide manner and deal with the subject in a fair, reasonable and objective manner. Decision should not be actuated by extraneous considerations. Secondly, the principles of natural justice should be followed. This would include the requirement that the arbitral tribunal must apply its mind to the attending facts and circumstances while taking the view one way or the other. Nonapplication of mind is a defect that is fatal to any adjudication. Application of mind is best done by recording reasons in support of the decision. As noticed above, Section 31(3)(a) of the A&C states that the arbitral award shall state the reasons on which it is based, unless the parties have agreed that no reasons are to be given. Sub-clauses (i) and (iii) to Section 34(2) also refer to different facets of natural justice. In a given case sub- clause to Section 34(2) and sub-clause (ii) to clause (b) to
Section 34(2) may equally apply. Lastly, is the need to ensure that the decision is not perverse or irrational that no reasonable person would have arrived at the same or be sustained in a court of law. Perversity or irrationality of a decision is tested on the touchstone of Wednesbury principle of reasonableness. At the same time, it was cautioned that this Court was not attempting an exhaustive enumeration of what would constitute „fundamental policy of Indian law‟, as a straightjacket definition is not possible. If on facts proved before them, the arbitrators fail to draw an inference which ought to have been drawn or if they have drawn an inference which on the face of it, is untenable resulting in injustice, the adjudication made by an arbitral tribunal that enjoys considerable latitude and play at the joints in making awards, may be challenged and set aside.
42. The decision of this Court in Associate Builders elaborately examined the question of public policy in the context of Section 34 of the A&C Act, specifically under the head „fundamental policy of Indian law‟. It was firstly held that the principle of judicial approach demands a decision to be fair, reasonable and objective. On the obverse side, anything arbitrary and whimsical would not satisfy the said requirement.
43. Referring to the third principle in Western Geco, it was explained that the decision would be irrational and perverse if (a) it is based on no evidence; (b) if the arbitral tribunal takes into account something irrelevant to the decision which it arrives at; or (c) ignores vital evidence in arriving at its decision. The standards prescribed in Excise and Taxation Officer-cum-Assessing Authority v. Gopi Nath & Sons, (1992 Supp (2) SCC 312 and Kuldeep Singh v.
Commissioner of Police, (1999) 2 SCC 10 should be applied and relied upon, as good working tests of perversity. In Gopi Nath & Sons it has been held that apart from the cases where a finding of fact is arrived at by ignoring or relevant materials or taking into consideration irrelevant material, the
finding is perverse and infirm in law when it outrageously defies logic as to suffer from vice of irrationality. Kuldeep Singh clarifies that a finding is perverse when it is based on no evidence or evidence which is thoroughly unreliable and no reasonable person would act upon it. If there is some evidence which can be acted and can be relied upon, however compendious it may be, the conclusion should not be treated as perverse. This Court in Associate Builders emphasised that the public policy test to an arbitral award does not give jurisdiction to the court to act as a court of appeal and consequently errors of fact cannot be corrected. Arbitral tribunal is the ultimate master of quality and quantity of evidence. An award based on little evidence or no evidence, which does not measure up in quality to a trained legal mind would not be held to be invalid on this score. Every arbitrator need not necessarily be a person trained in law as a Judge. At times, decisions are taken acting on equity and such decisions can be just and fair should not be overturned under Section 34 of the A&C Act on the ground that the arbitrator‟s approach was arbitrary or capricious. Referring to the third ground of public policy, justice or morality, it is observed that these are two different concepts. An award is against justice when it shocks the conscience of the court, as in an example where the claimant has restricted his claim but the arbitral tribunal has awarded a higher amount without any reasonable ground of justification. Morality would necessarily cover agreements that are illegal and also those which cannot be enforced given the prevailing mores of the day. Here again interference would be only if something shocks the court‟s conscience. Further, „patent illegality‟ refers to three sub-heads: (a) contravention of substantive law of India, which must be restricted and limited such that the illegality must go to the root of the matter and should not be of a trivial nature. Reference in this regard was made to clause (a) to Section 28(1) of the A&C Act, which states that the dispute submitted to arbitration under Part I shall be in accordance with the substantive law
for the time being in force. The second sub-head would be when the arbitrator gives no reasons in the award in contravention with Section 31(3) of the A&C Act. The third sub-head deals with contravention of Section 28(3) of the A&C Act which states that the arbitral tribunal shall decide all cases in accordance with the terms of the contract and shall take into account the usage of the trade applicable to the transaction. This last sub-head should be understood with a caveat that the arbitrator has the right to construe and interpret the terms of the contract in a reasonable manner. Such interpretation should not be a ground to set aside the award, as the construction of the terms of the contract is finally for the arbitrator to decide. The award can be only set aside under this sub-head if the arbitrator construes the award in a way that no fair-minded or reasonable person would do.
41. We do not wish to discuss the legal position more, as the
judgment aforementioned takes care of all aspect of challenge to
arbitral award by resort to Section 34 of the Act. Suffice for us to
say and hold that the arbitral award passed by the sole arbitrator
in the instant case was liable to be set aside on the grounds
enumerated in Section 34 of the Act, in particular, grounds
mentioned under Subsections 2(a) (iv) and 2(b(ii) thereof. Not
only the arbitrator has passed award not falling within the terms
of the submission to arbitration and in respect of matters beyond
the scope of the submission to arbitration but has also rendered
his award which is in conflict with public policy of State. The
Single Bench, with great respect, has failed to appreciate all
these aspects of the case.
42. For the reasons given above, we allow this appeal and set aside
the judgment impugned dated 03.11.2021. As a result, arbitral
award dated 02.01.2013 passed by the learned arbitrator is also
set aside. Parties are left to bear their own costs.
(Puneet Gupta) (Sanjeev Kumar)
Judge Judge
JAMMU
06.10.2023
Vinod,PS
Whether the order is speaking : Yes
Whether the order is reportable: Yes
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!