Citation : 2021 Latest Caselaw 1729 j&K
Judgement Date : 23 December, 2021
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
ATJAMMU
CJ Court
Reserved on 05.08.2021
Pronounced on: 23.12.2021
Case: OWP No. 1634 of 2016
Sh. Sheikh Reyaz Hamid & Others ..... Petitioner(s)
Through :- Sh. R.K.S.Thakur, Advocate
v/s
State of J&K and Others .....Respondent(s)
Through :- Sh. S.S.Nanda, Sr. AAG for respondent
Nos. 1 to 5
Sh. Vipan Gandotra, Advocate for
respondent No. 6
CORAM:
HON'BLE THE CHIEF JUSTICE
HON'BLE MR. JUSTICE PUNEET GUPTA, JUDGE
JUDGMENT
PANKAJ MITHAL, CJ:
01. Heard Sh. R.K.S.Thakur, learned counsel for the petitioners and
Sh. S.S.Nanda, learned Senior Additional Advocate General for
respondent Nos. 1 to 5 and Sh. Vipan Gandotra, learned counsel for the
respondent No. 6.
02. The petitioners are 38 in numbers. All of them are aggrieved by
the acquisition of their land measuring about 49 kanals and 17 marlas
situate in village Devgole Tehsil Banihal District Ramban which has
been notified for acquisition for the four lanning of the National
Highway.
03. The petitioners have thus invoked the extra-ordinary writ
jurisdiction of this Court seeking for quashing of the following:-
(i) Notification dated 2nd June 2008 issued under Section 4(1) of the J&K Land Acquisition Act Samvat 1990 (hereinafter referred to as 'the Act');
(ii) Notification dated 21st December 2009 issued Section 6 of the Act;
(iii) Public Notice dated 9th January 2010 issued under Sections 9 and 9-A of the Act;
(iv) Tentative award dated 24th February 2010;
(v) Notification dated 17th October 2011 issued under
Section 17 of the Act ; and
(vi) The final award dated 5th November 2016 passed
under Section 11 of the Act.
04. The basic ground on which the above prayers have been made is
that the entire proceedings of acquisition are bad in law and have lapsed
by virtue of Section 11-B of the Act inasmuch as no final award was
made within a statutory period of two years from the date of the
declaration made under Section 6 of the Act.
05. The defence is that since the urgency provision of Section 17 was
invoked and the possession of the land was taken over, the land had
vested in the State, in which circumstance Section 11-B of the Act
would have no application.
06. It may be important to note that the provisions of the Act are pari
materia with the Land Acquisition Act 1894. The provisions of Section
11-B of the Act are equivalent to Section 11-A of the Land Acquisition
Act., 1894.
07. Section 11-B of the Act which is relevant for our purpose in this
case, is reproduced hereinbelow:-
"[11-B. Period within which an award shall be made.- The Collector shall make an award under Section 11 within a
period, of two years from the date of the publication of the declaration and if no award is made within that period, the entire proceedings for the acquisition of land shall lapse:
Provided that in case where the said declaration has been published before the commencement of the State Land Acquisition (Amendment) Act, 1997, the award shall be made within a period of two years from such commencement."
08. The aforesaid provision mandates that the Collector shall make
an award under Section 11 within a period of two years from the date of
publication of the declaration under Section 6 of the Act and in case no
award is made within the stipulated period, the entire proceedings for
acquisition shall lapse. This is subject to an exception carved out by the
Act where the land vests in the State consequent to invocation of
urgency clause under Section 17 of the Act. Thus, in view of the
aforesaid provision and the exception, we have to see if the proceedings
of the acquisition have lapsed by virtue of Section 11-B of the Act if the
award has not been made within the stipulated time.
09. In order to determine the above aspect of the matter, it would be
appropriate to note some of the relevant and important dates which are
material for the above purpose. The said dates are as under:-
(1) Section 4 Notification dated 02.06.2008
(2) Section 6 Notification dated 21.12.2009
(3) Section 17 Notification dated 27.10.2011
(4) Possession (alleged) dated 20.09.2011
(5) Final award dated 05.11.2016
10. The above dates reveal that the two crucial dates for the purposes
of applying Section 11-B of the Act are the date of notification issued
under Section 6 of the Act, i.e., 21.12.2009 and the date of the final
award, i.e., 05.11.2016.
11. On the simple consideration of the above two dates in context
with Section 11-B of the Act, it would be evident that the award had not
been made within a statutory period of two years from the date of
publication of the notification under Section 6 of the Act and, therefore,
the proceedings would stand lapsed.
12. The perusal of the date of possession which happened to be
20.09.2012 also demonstrates that the possession of the acquired land
was not taken over by the respondents within two years of the final
acquisition of the land and, as such, the land had not vested in the State
till then.
13. In other words, neither the award was made within two years of
the final acquisition of the land nor the land had vested in the State and,
as such, the acquisition proceedings stand lapsed by virtue of Section
11-B of the Act. The taking of possession of the land subsequent to the
lapsing of the proceedings is not a valid possession in the eyes of law. It
would not confer any right in the land upon the respondents.
14. Now we come to the issue that the land acquisition proceedings
would not lapse where the urgency provisions under Section 17 of the
Act have been invoked.
15. In the present case, notification under Section 17 of the Act was
issued on 27.10.2011 enabling the respondents to take possession of the
land even before the award is pronounced. However, the inquiry
required to be made under Section 5-A of the Act was not dispensed
with. The purpose of taking immediate possession is to avoid delay in
the execution of the project. The taking over of the possession of the
land notified for acquisition has the effect of vesting the property in the
State provided the possession is taken over legally within time, i.e.,
before the proceedings lapses.
16. It may be noted that ordinarily possession of the land notified to
be acquired is taken over after the pronouncement of the award except
where urgency provisions are invoked and the possession is taken before
the award. The land once vested in the State with the transfer of
possession subsequent to acquisition cannot be divested and it is for this
reason the above exception has been carved out that the acquisition
proceedings would not lapse simply if the award is not made within time
if the possession has been taken and the vesting is complete.
17. Generally, in view of Section 11-B of the Act, the acquisition
proceedings came to an end on the expiry of two years from the date of
notification dated 21.12.2009 issued under Section 6 of the Act if no
award within the said time is made and the land had not vested in the
State for want of possession. The subsequent taking of possession is not
a valid possession and is immaterial.
18. In 'Satendra Prasad Jain v. State of U.P, (1993) 4 SCC 369 and
Awadah Bihari Yadav and Others v. State of Bihar and Others, (1995)
6 SCC 31,' it has been held that the provision of Section 11-A of the
Land Acquisition Act which is in pari materia with Section 11-B of the
Act would not apply where the land is acquired by invoking the urgency
provisions under Section 17 of the Act. This is for the reason that where
urgency provisions are invoked and the possession of the land is taken
over, it vests in the Government free from all encumbrances and the
Government cannot be divested from such land but the said principle
cannot be applied blindly to cases where though urgency provisions are
invoked but the possession of the land is not taken in a legal manner
within time and the proceedings are allowed to lapse. In such a situation,
subsequent taking over of possession is of no consequence as possession
of land cannot be taken after the proceedings have lapsed.
19. The Apex Court distinguishing the above two judgments in
'Laxman Pandya v. State of U.P, (2011) 14 SCC 94,' held that the
above two authorities are applicable where the possession of the land
has been taken within two years of the declaration under Section 6(1) of
the Act and the acquired land had vested in the State within the said
time. Thus, it was held that where possession of the land has not been
taken and no award has been passed within two years of the publication
of the declaration under Section 6(1) of the Act, the land acquisition
proceedings automatically lapse by virtue of Section 11-A of the Act,
i.e., Section 11-B of the Act in the instant case. This is also a situation in
the case we are dealing with, wherein also neither any award was made
within the stipulated period nor the land had vested in the State within
the said period despite invoking of the urgency provisions.
20. The case of 'Satendra Prasad Jain' (supra) has been considered
and distinguished by the two other decisions of the Supreme Court in
the case of 'Laxami Devi vs. State of Bihar and Ors. 2015 (10) SCC
241'and M/s Soorajmull Nagarmull vs State of Bihar & ors. 2015 AIR
(SC) 3400,' wherein it has been reiterated that the Government is
obliged to pass an award within two years and, if the award is not so
passed, it would render the acquisition void in view of Section 11-A of
the Land Acquisition Act.
21. Sh. Nanda, relied upon 'New Okhla Industrial Development
Authority v. Harkishan through LRS and Others, (2017) 3 SCC 588,
to contend that once the award is passed and it is not challenged
immediately, no relief can be granted to the petitioners.
22. In the aforesaid case, it has been held that failure to challenge the
award at the earliest possible instance and challenging it in a fresh
litigation is barred by principles of Order 2 Rule 2 CPC and also by
delay and laches. In the said case before the Supreme Court, the
petitioners have first challenged the acquisition proceedings in the High
Court which ended against them and, therefore, they preferred SLP to
the Supreme Court. In the meantime, an award was passed. Thereafter
when the SLP was taken up, it was dismissed but with liberty to the
petitioners to make a representation to the State Government for the de-
notification of the land. Once the representation was made and rejected,
a challenge was unsuccessfully made before the High Court. It was
thereafter in the third round that the petitioners challenged the award on
the ground that it has lapsed by virtue of Section 11-A of the Act. It is in
the facts and circumstances of the above case, the court held that there
was no prompt challenge to the award and that the challenge stands
defeated on the principles of Order 2 Rule 2 CPC.
23. The above is not the situation in the present case. Here, the award
was passed on 5th November 2016 and immediately thereafter the writ
petition was filed in the year 2016 itself and, as such, there is neither
any undue delay or laches in filing the same and since there was no prior
litigation, it cannot be said that the principles of Order 2 Rule 2 CPC
would stand attracted.
24. In view of the aforesaid facts and circumstances and the legal
position, the land acquisition proceedings pursuant to the declaration
dated 21.12.2009 automatically lapses for want of award under Section
11 of the Act and vesting of land within two years thereof.
25. In the end, a faint effort was made to contend that the period
during which some stay order in respect of the above acquisition
proceedings has remained operative is liable to be excluded for
calculating the period of two years for making the award from the date
of the declaration made under Section 6(1) of the Act. In this regard, it
is submitted that in OWP No. 477 of 2010, a stay order was passed on
03.05.2010 and that of status quo on 01.01.2016 which remained in
operation till 06.10.2016 on which date the petition was disposed of.
26. The above submission is completely mis-conceived as the
challenge in the above writ petition was to different proceedings of land
acquisition which commenced with the notification dated 24.06.2006. It
was not in connection with the acquisition proceedings in question and,
as such, any interim order passed therein would not have any bearing on
the lapsing of the above proceedings.
27. In view of the aforesaid facts and circumstances, we have no
option and hesitation but to declare that the land acquisition proceedings
pursuant to the notification dated 2nd June 2008 issued under Section 4
of the Act and the declaration dated 21st December 2009 issued under
Section 6 (1) of the Act have lapsed by virtue of Section 11-B of the Act
and consequently the taking over of the possession, if any, on
20.09.2012 is illegal and of no consequence insofar as it relates to the
land involved in the writ petition.
28. Accordingly, we direct the respondents either to restore the
possession of the land to the petitioners or in the event it is not possible
to do so, to acquire it afresh or alternatively to offer the petitioners fair
market value of the said land as on date as may be assessed/determined
by applying the principles for determination of compensation as laid
down under the Right to Fair Compensation and Transparency in Land
Acquisition, Rehabilitation and Resettlement Act, 2013 which has been
enforced in the Union Territory of Jammu and Kashmir with effect from
31.10.2019.
29. The writ petition is allowed with no order as to costs.
(PUNEET GUPTA) (PANKAJ MITHAL)
JUDGE CHIEF JUSTICE
JAMMU
23.12.2021
Tilak
Whether the order is speaking ? : Yes.
Whether the order is reportable? : Yes.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!