Thursday, 23, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Narender Kumar & Others vs Nhai & Another
2024 Latest Caselaw 15156 HP

Citation : 2024 Latest Caselaw 15156 HP
Judgement Date : 16 October, 2024

Himachal Pradesh High Court

Narender Kumar & Others vs Nhai & Another on 16 October, 2024

IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA

                                        Arbitration Case No. 607 of 2024
                                        Date of Decision :16.10.2024

Narender Kumar & others                                       ...... Petitioners

                                  Versus

NHAI & another                                                ......Respondents

Coram:

The Hon'ble Mr. Justice Bipin Chander Negi, Judge
Whether approved for reporting?1

For the petitioner        :       Mr. Karun Negi, Advocate.

For the respondents           :   Ms. Shreya Chauhan, Advocate, for respondent
                                  No.1.

                                  Mr. Raj Kumar Negi, Additional Advocate General,
                                  for respondent No.2/State.

Bipin Chander Negi, Judge (oral)

The arbitral dispute arises out of the land acquisition in District

Solan, H.P. for the purpose of building (widening/ four laning etc.)

maintenance, management and operation of National Highway- 22. The

land has been acquired under the provisions of National Highways Act,

1956.

2. Arbitration case No. 607 of 2024 pertains to Award No. 17 dated

27.06.2016, with respect to the aforesaid, the petitioner had preferred a

Claim Petition No. 333 of 2017, under Section 3(g) (5) of the National

Highways Act. In the aforesaid claim petition, the arbitrator had issued

notice for 27.09.2018. Reply in the claim petition was filed on 13.05.2020.

Whether reporters of Local Papers may be allowed to see the judgment? Yes Vide order dated 26.05.2023, it was observed that the mandate of

arbitrator had expired. Hence, the aforesaid arbitral proceedings were

kept in abeyance, till the time period for completing the arbitral

proceedings, was extended under Section 29-A.

3. From a perusal of the aforesaid, it is evident that the Reference

Petition against the award had been filed by the land owners about 5

years back.

4. The relevant extract of the provisions involved in the present lis, as

amended by the Act No 33 of 2019 w.e.f 31.08.2019, are being

reproduced here-in-below for a ready reference:-

"29-A. Time limit for arbitral award.--(1) The award in matters other than international commercial arbitration be made by the arbitral tribunal within a period of twelve months from the date of completion of pleadings under sub- section (4) of Section 23:

(2)..............

(3) The parties may, by consent, extend the period specified in sub-section (1) for making award for a further period not exceeding six months.

(4) If the award is not made within the period specified in sub-section (1) or the extended period specified under sub-

section (3), the mandate of the arbitrator(s) shall terminate unless the court has, either prior to or after the expiry of the period so specified, extended the period: Provided that while extending the period under this sub- section, if the court finds that the proceedings have been delayed for the reasons attributable to the arbitral tribunal, then, it may order reduction of fees of arbitrator(s) by not exceeding five per cent for each month of such delay: Provided further that where an application under sub- section (5) is pending, the mandate of the arbitrator shall continue till the disposal of the said application: Provided also that the arbitrator shall be given an opportunity of being heard before the fees is reduced.

(5) The extension of period referred to in sub-section (4) may be on the application of any of the parties and may be granted only for sufficient cause and on such terms and conditions as may be imposed by the court.

Section 23. Statements of claim and defence (4) The statement of claim and defence under this section shall be completed within a period of six months from the date the arbitrator or all the arbitrators, as the case may be, received notice, in writing, of their appointment."

The sum and substance of the aforesaid provisions is that from the

date the arbitrator receives notice the statement of claim and defence

(pleadings) shall be completed within a period of six months there from.

Further the award shall be made by the arbitral tribunal within a period of

twelve months from the date of completion of pleadings. However, the

parties may, by consent, extend the period specified for making award for

a further period not exceeding six months. If the award is not made within

the period specified or the extended period specified the mandate of the

arbitrator shall terminate unless the court has, either prior to or after the

expiry of the period so specified, extended the period. The extension may

be on the application of any of the parties .The same may be granted only for sufficient cause and on such terms and conditions as may be imposed

by the court.

5. Having gone through the order sheets appended with the petition

carefully, this Court is pained to observe that the proceedings have been

conducted by learned Arbitrator by observing statutory provisions as are

contained in the Arbitration and Conciliation Act, 1996 more in their

breach rather than in their observance.

6. This Court is of the considered view that when the law requires a

particular act to be done in a particular manner, then the same is

mandatorily required to be followed. In the case at hand, the onus was

upon the Arbitrator to perform the task entrusted to him within the time

schedule prescribed in the statute. The delay, if any, has to be bonafide

and explainable.

7. The record appended alongwith the present petition demonstrates

that the matters were adjourned by the learned Arbitrator on numerous

occasions. This Court fails to understand, as to how the Arbitrator can

with such a callous attitude take upon the task of deciding the arbitration

proceedings knowing fully well that if the proceedings are not completed

within the time schedule mentioned in the Act, then unless the same is

extended by a Court of Law, the mandate of the Arbitrator shall stands

terminated.

8. At this juncture, it would be appropriate to refer to the

judgment of the Apex Court delivered in Cognizance for Extension of

Limitation, In re, (2022) 3 SCC 117 : (2022) 1 SCC (Cri) 580 :

(2022) 2 SCC (Civ) 46 : (2022) 1 SCC (L&S) 501, wherein the

following direction had been issued:

"5.4. It is further clarified that the period from 15-3-2020 till 28-2-2022 shall also stand excluded in computing the periods prescribed under Sections 23(4) and 29-A of the Arbitration and Conciliation Act, 1996, Section 12-A of the Commercial Courts Act, 2015 and provisos (b) and (c) of Section 138 of the Negotiable Instruments Act, 1881 and any other laws, which prescribe period(s) of limitation for instituting proceedings, outer limits (within which the court or tribunal can condone delay) and termination of proceedings."

The benefit of exclusion of the aforesaid period specified herein

above also needs to be given to the petitioners before this Hon'ble Court.

9. The Divisional Commissioner, Mandi was appointed as an

Arbitrator in the case at hand vide order dated 22.03.2012 by the Central

Government, in pursuance to sub Section 5 of the National Highways Act,

1954 for the revenue District of Shimla and Solan.

10. Be that as it may, the Court is restraining from making any further

observation in the case, save and except, that hence forth, if the Court

finds the Arbitrator to be remiss in his duties then it shall not hesitate in

invoking its powers as are enshrined in Section 29 (A) (6) of the 1996 Act

to terminate the mandate of the Arbitrator de hors the fact that the

Arbitrator happens to be appointed, in terms of the aforesaid notification,

issued by the Central Government under the National Highways Act,

1956.

11. The lands of the petitioners have been acquired and they are

entitled to fair and just compensation, if in case, the mandate of the

learned Arbitrator is allowed to be terminated on account of him having

failed to complete proceedings within time great prejudice would be

caused to the petitioners who had been fighting for their rightful claim for

years together.

12. Consequently, in view of the above the petition is allowed with the

directions to the learned Arbitrator to conclude arbitration proceedings on

or before 16.04.2025. Learned Arbitrator is impressed upon to make a

time table, indicating therein the time schedule, in terms whereof, the

parties have to move forward in the matter.

13. Petition stands disposed of, so also the pending miscellaneous

applications, if any.



                                              (Bipin Chander Negi)
October 16, 2024 (Nisha)                             Judge
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter