Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Through Its Commissioner vs Municipal Corporation
2022 Latest Caselaw 8564 HP

Citation : 2022 Latest Caselaw 8564 HP
Judgement Date : 17 October, 2022

Himachal Pradesh High Court
Through Its Commissioner vs Municipal Corporation on 17 October, 2022
Bench: Ajay Mohan Goel
         IN THE HIGH COURT OF HIMACHAL PRADESH AT SHIMLA

                    ON THE 11th DAY OF OCTOBER, 2022




                                                                  .
                                    BEFORE





                 HON'BLE MR. JUSTICE AJAY MOHAN GOEL

                REGULAR SECOND APPEAL No. 201 OF 2022





    Between:-

    MUNICIPAL CORPORATION SHIMLA





    THROUGH ITS COMMISSIONER..
                                                         ..........APPELLANT

    (BY MR. NARESH KUMAR GUPTA,
    ADVOCATE)


    AND

    1.    BHAG CHAND SHARMA SON
          LATE SH. LACHI RAM SHARMA


          RESIDENTOF        NARAYAN
          BHAWAN, KANLOG SHIMLA, H.P.
                               ..........Respondent/defendant No.1




    2.    RAJEEV      SHARMA,     EX
          ARCHITECT         PLANNER,





          MUNICIPAL     CORPORATION
          SHIMLA PRESENTLY POSTED AS
          ARCHITECT IN THE OFFICE OF





          P.W.D. NIGAM VIHAR SHIMLA,
          H.P.
                                   ......PROFORMA RESPONDENT

    {MR. BHAG CHAND SHAMRA (RESPONDENT
    No.1) PERSENT IN PERSON).
    ___________________________________________________________

                Whether approved for reporting:          No

                This appeal coming on for ORDERS this day, Hon'ble Mr.

    Ajay Mohan Goel, delivered the following:-




                                                 ::: Downloaded on - 17/10/2022 20:03:02 :::CIS
                                          2



                             JUDGEMENT

By way of this appeal, the appellant challenges the judgment

.

and decree passed by the Court of learned Civil Judge, Court No.5,

Shimla, in Civil Suit No.136-1 of 2013, titled as Bhag Chand Sharma vs.

Municipal Corporation, Shimla and another dated 01.12.2021, in terms

whereof, the suit for declaration and injunction filed by respondent No.1

was decreed as well as the judgment and decree passed by the Court of

learned Additional District Judge-II, Shimla H.P. passed in Civil Appeal

No.1-S/13 of 2022, titled as the Municipal Corporation, Shimla vs. Sh.

Bhag Chand Sharma and another, dated 19.04.2022. in terms whereof,

the appeal preferred by the Municipal Corporation against the judgment

and decree passed by the learned Trial Court was dismissed.

2. Brief facts necessary for the adjudication of the present

appeal are as under:-

Respondent/plaintiff (hereinafter to be referred as the plaintiff)

filed a suit for declaration to the effect that he was owner in possession of

the land comprised in Khasra No.1038/494 and 1046/496, measuring

167.20 square meters, situated in Mauza Kanlog, Tehsil and District

Shimla, H.P. The plaintiff had constructed a house upon the same.

Completion of three storey i.e. ground floor measuring 69.85 square

metres, first floor 76.44 square meters and second floor measuring 76.44

square meters was approved in favour of the plaintiff by defendant-

Corporation vide order No.132 AP dated 12.06.1997. Later on, plaintiff

came to know that as per floor area ratio upon a plot measuring 167.20

square metres, permissible built up area could be up to 292.60 square

.

meters whereas he had covered only 222.73 square metres. Therefore, in

these circumstances, he submitted a revised plan to the Municipal

Corporation for sanction, which was duly sanctioned by the Commissioner

vide order No.337 AP dated 02.12.2005, in terms whereof, the plaintiff

was conveyed the sanction of 66.55 square meters of the third floor.

Plaintiff raised construction of the third floor by covering only 62.12 square

metres against sanctioned area of 66.55 square metres. Thereafter, he

submitted the completion plan to the corporation on 05.12.2006 vide Diary

No.395/COM/06. However, the plaintiff did not receive any sanction order

or objections to the said completion plan which he had submitted with the

respondent-Corporation. According to the plaintiff, the non-conveying of

the sanction plan to the plaintiff was on account of a malafide intent to

harass him for extraneous considerations. As per him, the construction

which stood raised by him, was strictly in consonance with the sanction

accorded by the Municipal Corporation. Despite his approaching the

concerned officials of the respondent-Corporation of the defendant-

Corporation on various occasions, nothing fruitful was done and every

time, he was told that the case of the plaintiff was under consideration.

Faced with this situation, the plaintiff wrote a letter to defendant No.1 on

26.02.2008 by way of UPC which was not replied. This was followed by

another letter dated 30.04.2012, in terms whereof, the plaintiff requested

defendant No.1 for issuance of No Objection Certificate for restoration of

the Electricity Metre so that he could put the accommodation in use as

.

there was a deemed sanction of the plan, as envisaged under Section 247

(1) of the H.P. Municipal Corporation Act, 1994. In response thereto,

defendant issued a letter dated 02.06.2012 under the signatures of

defendant No.2, which as per the plaintiff, was issued without verifying

any record and it was mentioned therein that the plan of the third floor of

the building of the plaintiff was never approved, and in fact, the same

already stood returned to the plaintiff vide letter dated 27.01.2007, and

thereafter, the plan was never re-submitted by the plaintiff to the

Corporation. According to the plaintiff, he had never received the plan

back from the defendant-Corporation after he had submitted the same for

the purpose of grant of completion certificate and the letter was issued by

the Corporation again with ulterior motive to harass and coerce the

plaintiff, and thus, to cause loss to him. According to the plaintiff, the

malice in the conduct of the defendant was on account of the two civil

suits having been instituted by the plaintiff against his neighbours, in

which, he had alleged the non-leaving of set back by the said neighbours

in the course of construction of their respective houses and also on

account of some other complaints having been preferred by the plaintiff

against the respondent-Corporation, in which, the District Consumer

Forum, Shimla, had awarded compensation of Rs.25,000/- in favour of

the plaintiff against the defendant. In this background, the plaintiff after

issuing a legal notice to the defendant dated 22.09.2012 instituted the

suit, in which, prayer was made that the Court may issue declaration to

.

the effect that the revised completion plan of the house of the plaintiff

which was submitted by him to defendant No.1 on 05.12.2006 was never

conveyed back to him by Corporation. Plaintiff also prayed for declaration

that as the revised completion plan of the house of the plaintiff which was

submitted by him to defendant No.1 on 05.12.2006 was neither rejected

nor otherwise conveyed to the plaintiff, therefore, there was deemed

sanction thereof in terms of the provisions of Section 247(1) of the

Himachal Pradesh Municipal Corporation Act, 1994. A decree for

mandatory injunction was also sought against defendant No.1 for the

issuance of 'No Objection Certificate' in respect of second and third floor

for the purpose of the installation of Electricity Metre.

3. The suit was resisted by the defendants intra alia on the

ground that the completion plan, which was submitted by the plaintiff on

05.12.2006, was returned back to the plaintiff by defendant No.1 vide

letter No.MCS/AP/1833/Mukhya/06-07-437 dated 27.01.2007. Defendants

denied that the plaintiff had not received back the completion plan as was

alleged by the plaintiff, and according to them, the same was sent back to

the plaintiff by post on 05.02.2007.

4. On the basis of the pleadings of the parties learned Trial

Court framed the following issues:-

1. Whether the plaintiff is entitled for the relief of

declaration that the revised completion plan of the house

.

of the plaintiff, submitted to defendant No.1 on 05.12.2006

was never conveyed to the plaintiff and is deemed to be

sanctioned under Section 247(1) of the Municipal

Corporation Act, and letter No. MCS/AP/1037/AP/12-3291,

dated 02.06.2012 signed by defendant No.2 is false,

illegal, wrong and not based on facts, as prayed for? OPP

2. If issue No.1 is proved in affirmative, whether the

plaintiff is entitled for the relief of mandatory injunction, as

prayed for? OPP

3. If issues No.1 and 2 are proved in affirmative,

whether the plaintiff is entitled for the relief of damages, as

prayed for? OPP.

4. Whether the suit of the plaintiff is not maintainable,

as alleged? OPD

5. Whether the suit is bad for non issuance of

mandatory notice under Section 392 of the HPMC Act,

1994, as alleged? OPD

6. Whether the plaintiff has not come to the

Court with clean hands, as alleged? OPD

7. Whether the suit has not been properly valued for

the purpose of Court fee and jurisdiction, as alleged? OPD.

8. Whether the suit is liable to be rejected under Order

7 Rule 11 CPC, as alleged? OPD

.

9. Relief.

5. On the basis of pleadings and evidence led by the parties in

support of their respective cases, the Issues so framed were answered by

the learned Trial Court as under:-

                 Issue No. 1:         Yes.





                 Issue No. 2:         Yes.

                 Issue No. 3:
                           r          No.

                 Issue No. 4:         No.

                 Issue No. 5:         No.

                 Issue No. 6:         No.


                 Issue No. 7:         No.

                 Issue No. 8:         No.




                 Relief         :     Suit of the plaintiff is partly decreed as per
                                      operative part of the judgment.





6. Leaned Trial Court thus decreed the suit of the plaintiff by

inter alia holding that whereas the plaintiff had duly demonstrated that he

had submitted the completion plan of the third floor vide Exhibit PW-1/7

and Exhibit PW-1/20 which was duly received by defendant No.1 on

05.12.2006, however, no evidence was placed on record by the defendant

to demonstrate that the completion plan so submitted by the plaintiff was

ever returned back to him as alleged by the defendants. Primarily, on this

count, the suit of the plaintiff was decreed by the learned Trial Court in the

following terms:-

"Accordingly, in view of the above discussion, the suit of

the plaintiff is partly decreed. The plaintiff is held entitled

.

for the relief of declaration that the revised completion plan

of the house of the plaintiff, submitted to defendant No. 1

on 05.12.2006 was never conveyed to the plaintiff and is

deemed to be sanctioned under Section 247(1) of the

Municipal Corporation Act, and letter No. MCS/AP/

1037/12-3291, dated 02.06.2012 signed by defendant No.

2 is false, illegal, wrong and not based on facts. The

plaintiff is held entitled for the relief of mandatory injunction

and the Defendant No. 1 is hereby directed to issue No

Objection Certificate in favour of the plaintiff for second

and third floors. Decree sheet be prepared accordingly. Let

this file complete in all respects be consigned to Record

Room."

7. In appeal, learned Appellate Court while upholding the

findings returned by the learned Trial Court, dismissed the appeal.

Learned Appellate Court held that the findings returned by the learned

Trial Court did not deserve to be interfered with on any count and further,

bare statement of the defendant' witnesses without any documentary

basis that the construction carried out by the plaintiff was against bye laws

etc. could not be accepted. Learned Appellate Court also held that

defendants had failed to communicate the rejection of the completion plan

to the plaintiff without any reasonable cause, and therefore, there was no

infirmity in the judgment and decree passed by the learned Trial Court.

.

8. Feeling aggrieved, defendant-respondent Corporation has

filed the present appeal.

9. I have heard learned Counsel for the appellant as also the

plaintiff, who has appeared in the Court in person and also argued the

case in person. The grievance with which the plaintiff approached the

learned Trial Court has been referred to by me in detail in the above part

of the judgment. There are concurrent findings returned by both the

learned Court below to the effect that defendant-Corporation failed to

prove that the rejection of the completion plan was duly conveyed to the

plaintiff. A perusal of the List of Exhibits demonstrates that, in fact, no

document was filed by the defendants before learned Trial Court in

support of their contention as was raised in the written statement. Thus,

as the defendant-Corporation failed to substantiate its bald contention so

raised in the written statement that the completion plan submitted by the

plaintiff was duly communicated to the plaintiff after its rejection, was not

substantiated by leading any cogent evidence to prove this fact, this Court

can safely say that the findings which have been returned by learned

Courts below to the effect that defendant-Corporation failed to

demonstrate or prove that the completion plan after rejection was duly

returned back to the plaintiff, are correct findings and are duly borne out

from the record of the case. This being the factual position as it emanates

from the record of the case, this Court does not finds any perversity with

the findings which have been returned by the leaned Court below while

.

decreeing the suit of the plaintiff.

Accordingly, in view of the above observations, as this Court

does not finds any substantial question of law involved in the present

appeal as the issues which have been decided by the learned Courts

below are simplicitor issues of fact, the present appeal being devoid of

merit, is dismissed with costs. Pending miscellaneous application(s), if

any, also stand disposed of accordingly.

                           r                            (Ajay Mohan Goel)

                                                              Judge
    October 11, 2022
       (narender)









 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter