Citation : 2021 Latest Caselaw 1502 HP
Judgement Date : 2 March, 2021
IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA
CWP No.710 of 2021 Reserved on: 26th February, 2021 Decided on: 2nd March, 2021
.
-------------------------------------------------------------------------------------
Satish Chandra Mishra .....Petitioner Versus
Satluj Jal Vidyut Nigam Ltd. and others .....Respondents
------------------------------------------------------------------------------------- Coram
The Hon'ble Mr. Justice Tarlok Singh Chauhan, Judge
The Hon'ble Ms. Justice Jyotsna Rewal Dua, Judge
Whether approved for reporting? 1 No
For the Petitioner: Mr. Ajay Vaidya, Advocate. For the Respondents: Mr. K.D. Shreedhar, Senior Advocate
with Mr. Sameer Thakur, Advocate, for respondents No.1 and 2.
---------------------------------------------------------------------------------- Jyotsna Rewal Dua, Judge
Petitioner is a Senior Additional General
Manager (HR) with the respondent-Satluj Jal Vidyut Nigam
Limited. Vide office order dated 06.01.2021 (Annexure P-1),
he was transferred from Liasoning Office (LO), Dehradun to
Liasoning Office, Patna. CWP No.423 of 2021 filed by the
petitioner assailing this transfer order, was disposed of on
1 Whether the reporters of Local Papers may be allowed to see the judgment?
01.02.2021, granting liberty to the petitioner to represent to
the respondent/concerned authority within three days.
Operation of interim order passed on 18.01.2021 with
.
respect to stay of the impugned transfer order qua the
petitioner was to remain in force till decision of the
representation.
The representation so preferred by the petitioner
was rejected by the respondent on 04.02.2021. Aggrieved,
"(i) r to he has once again approached this Court with the following
substantive prayers:-
That a writ in the nature of Certiorari for quashing and setting
aside the impugned transfer order (Annexure P-1) may very kindly be issued against the respondents.
(iv) During the pendency of petition the Respondent be directed to allow the petitioner to function at the post of Sr. AGM (P&A) at Dehradun or alternatively he may be posted at his choice of
place of posting Delhi Office or at Kathmandu office. Such other or further order, as may be deemed just and may kindly be passed in favour of the Petitioner."
Transfer to LO Patna has been challenged on
the grounds that (i) it was neither in public interest nor for
any administrative exigency. It was rather based upon
extraneous consideration; (ii) petitioner is left with one year
and four months in his retirement and; (iii) petitioner was
not permitted transfer to a place of his choice as per Clause
10.4 of the transfer policy.
2. We have heard learned counsel for the parties
and gone through the pleadings. During hearing of the
case, it has been informed that the petitioner stands
.
relieved from the post in question at LO Dehradun w.e.f.
05.02.2021.
3. The stand taken by the respondent is that its
Regional Office (RO) Dehradun alongwith some other
similar offices in Himachal Pradesh were under
consideration for
closure. Since,
Executives were no more required at RO Dehradun,
therefore, on
12.05.2020, various Senior/Middle
executives Level
were
transferred from RO Dehradun to places of their
requirement depending upon administrative exigencies.
Whereafter, the Regional Office was renamed as Liasoning
Office for limited purpose of carrying out liasoning activities
relating to various clearances/approvals of projects of
Uttarakhand. In December, 2020, respondent-SJVNL
submitted an Asset Monetization Plan (AMP) to the
Government of India for approval, making clear that SJVNL
plans to consider option of sale/lease/development of
building/land in Dehradun. The Government of India
accorded the approval of competent authority to AMP vide
communication dated 04.01.2021 and directed the
respondents to take appropriate action in that regard.
The respondent further submits that as per the
.
approved AMP, its target to dispose of LO Dehradun is by
31.03.2021. In this process, the petitioner was transferred
from LO Dehradun to LO Patna on 06.01.2021. The order of
transfer was necessitated because of abovementioned
administrative exigency. The respondent has further
submitted that no
Executive Level Officer
Department is presently stationed at LO Dehradun in view
of impending closure of LO Dehradun and that at present in HR
only skeletal staff is posted there. Owing to above stated
administrative exigency, petitioner had to be transferred
outside LO Dehradun. His transfer to LO Patna has been
justified on the ground that the petitioner is a Senior
Additional General Manager in the scale of Rs.1,20,000-3%-
2,80,000/-. The post is equivalent to that of Superintending
Engineer in the State with more than four years' tenure on
the said post. The respondents require the expertize of the
petitioner for setting up Buxar Thermal Power Plant in
Buxar, Bihar, where the main plant works have statedly
been awarded and are in progress. The petitioner being a
Senior Executive in HR Department was required in LO
Patna for managing the manpower at Patna.
4. The stand of the respondent reflects that having
.
taken a decision to close their liasoning office at Dehradun,
the services of the petitioner, an officer of the high rank and
drawing the gross salary of Rupees Sixty Lacs per annum,
were certainly not required there. Therefore, no infirmity
can be inferred in transfer of the petitioner from LO
Dehradun. Learned
counsel for the petitioner
contended that the petitioner is due for superannuation in
less than two years', therefore, in accordance with Clause next
10.4 of the transfer policy, he should have been posted at a
place of his choice. This is countered by the respondents by
submitting that the word used in the said clause is 'may'
and subject to vacancy and has to be harmoniously read
alongwith other clauses. Further, his pleaded choice of
place of posting at Delhi office cannot be accepted as no
post is statedly lying vacant there. Additionally, this is a
discretionary power vested with the respondents to be
exercised after considering the administrative exigencies
and requirement of replying respondents. Petitioner, who
belongs to Ranchi (Jharkhand), has been now posted at LO
Patna, inter alia, for managing the manpower at Buxar,
Bihar, where works related to a Thermal Power Plant were
in progress. We find force in this contention of the
.
respondents, more particularly in view of the facts noticed
above. We may also notice here that even at the time of his
transfer to RO Dehradun, the petitioner had unsuccessfully
laid challenge to his posting there by way of CWP No.2013
of 2016. The petitioner has not been able to demonstrate
allegations of malafides levelled against the respondents.
For all the aforesaid reasons, we do not find any
merit in the instant writ petition and the same is
accordingly dismissed, so also the pending miscellaneous
application(s), if any.
(Tarlok Singh Chauhan)
Judge
(Jyotsna Rewal Dua)
March 02, 2021 Judge
Mukesh
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!