Tuesday, 02, Jun, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

State Of Gujarat vs Govindbhai Devayatbhai
2025 Latest Caselaw 8255 Guj

Citation : 2025 Latest Caselaw 8255 Guj
Judgement Date : 24 November, 2025

Gujarat High Court

State Of Gujarat vs Govindbhai Devayatbhai on 24 November, 2025

                                                                                                           NEUTRAL CITATION




                              C/CA/4967/2025                                ORDER DATED: 24/11/2025

                                                                                                            undefined




                                    IN THE HIGH COURT OF GUJARAT AT AHMEDABAD

                         R/CIVIL APPLICATION (FOR CONDONATION OF DELAY) NO. 4967 of
                                                    2025

                                               In F/FIRST APPEAL NO. 25970 of 2025

                       ==========================================================
                                                    STATE OF GUJARAT & ANR.
                                                             Versus
                                                    GOVINDBHAI DEVAYATBHAI
                       ==========================================================
                       Appearance:
                       MR RAHUL DAVE, ASST. GOVERNMENT PLEADER for the Applicant(s) No.
                       1,2
                       RULE SERVED for the Respondent(s) No. 1
                       ==========================================================

                         CORAM:HONOURABLE MRS. JUSTICE M. K. THAKKER

                                                        Date : 24/11/2025

                                                          ORAL ORDER

1. Learned AGP Mr.Dave has explained the delay by making following averments in the application:

"2) The judgment and award were pronounced on 07.02.2023. Subsequently, on 13.02.2024, the Deputy Executive Engineer of Sardar Patel Irrigation Sub-Division, Keshod, District Junagadh, applied for a certified copy of the judgment, which was received on 14.02.2024. Thereafter, on 29.02.2024, the Deputy Executive Engineer prepared a proposal to obtain a grant for depositing the awarded amount and forwarded the same to the Divisional Officer of the Executive Engineer, Junagadh Irrigation Division.

NEUTRAL CITATION

C/CA/4967/2025 ORDER DATED: 24/11/2025

undefined

3) The delay in filing the appeal is neither willful nor deliberate but is solely due to the genuine and bona fide circumstances outlined above. The applicants respectfully submit that they have a substantial and arguable case on merits, and denial of an opportunity to present their case would result in serious prejudice and cause grave injustice.

4) It is submitted that on 12.03.2024 District Public Prosecutor L.O.R, given an opinion under below 131, after that on dated 14.03.2024 the said opinion given to the Deputy Executive Engineer Sardar Patel Irrigation, Keshod issued letter informing about the matter written to Divisional Officer of Executive Engineer Junagadh Irrigation Division, Junagadh office.

5) It is pertinent to note that part of the delay also occurred due to on procedural steps taken 01.06.2024, when the Divisional Office of the Executive Engineer, Junagadh Irrigation Division, Junagadh, made certain remarks on the proposal concerning the present case and by the office of the Dy. Executive Engineer, Keshod, Junagadh verified and submitted to office of the Executive Engineer Irrigation, Junagadh.

6) Furthermore, on 03.07.2024, the Deputy Executive Engineer, Shri Sardar Patel Irrigation, Keshod, issued a letter to the Provincial Officer, Keshod, referring to reliance placed on Land Reference Case Nos. 1467/1999 (Main) to 1481/1999, related to the Naredi-Bodka-Piplana Main Road Scheme, Village: Naredi, District:

Junagadh. In those cases, land was acquired by

NEUTRAL CITATION

C/CA/4967/2025 ORDER DATED: 24/11/2025

undefined

the District Roads and Buildings Sub-Division, Junagadh, and compensation was granted. Accordingly, the office of Dy. Executive Engineer Shri Sardar Patel Irrigation, Keshod, Junagadh requested copies of relevant documents from the District Roads and Buildings Sub-Division, Junagadh, for further proceeding.

7) It is submitted that part of the delay occurred due to the time taken by the Deputy Executive Engineer, Keshod, in communicating with the Deputy Collector and calculating the T.D.S. deduction amount. Further delay was caused by the Executive Engineer, Panchayat R&B Department, Junagadh, who, on 14.10.2024, informed the office of Shri Sardar Patel Participatory Irrigation, Keshod, that the compensation amount, as per the court's judgment, had been deposited in the court, duly acknowledged through receipts (enclosed), and disbursed to the landowners. It was also stated that no appeal had been filed up to that date.

Subsequently, on 07.11.2024, the committee chaired by the Chief Engineer (Act.) and Additional Secretary, Narmada, Water Resources, Water Supply, and Kalpsar Department recommended filing an appeal in the present case.

8) In consonance with the above, vide letter dated 03.02.2025, the Legal Department directed the Public Prosecutor of the Hon'ble Gujarat High Court to file an appeal, in consultation with the Narmada, Water Resources, Water Supply Department. The file was returned to the concerned department on 06.02.2025. The appeal pertains to the judgment dated 07.02.2023 passed

NEUTRAL CITATION

C/CA/4967/2025 ORDER DATED: 24/11/2025

undefined

in Land Reference Case No. 310/2012 by the Principal Senior Civil Judge, Keshod, District Junagadh.

9) It is submitted that part of the delay occurred because the letter dated 07.02.2025 from the Narmada, Water Resources, Water Supply, and Kalpsar Department, regarding the filing of the appeal, was received only on 18.02.2025 by the office of the Deputy Executive Engineer, Sardar Patel Participatory Irrigation, Keshod, via email from the Executive Engineer, Junagadh Irrigation Division. It is further submitted that additional time was consumed by the Executive Engineer's office in obtaining the relevant records and documents from the Learned Principal Senior Civil Judge, Keshod.

10) It is pertinent to note that on 19.02.2025, the Deputy Executive Engineer, Sardar Patel Participatory Irrigation, Keshod, received certified copies of the Suit Petition, Judgment, Decree, and Reply to the Suit Petition. Subsequently, on 20.02.2025, the Executive Engineer, Junagadh Irrigation Division, Junagadh directed the office of Deputy Executive Engineer, Sardar Patel Participatory Irrigation, Keshod, to file an affidavit and represent the Government in the matter, including handling all related proceedings. Thus, the delay that has occurred is bona fide, and the applicant has not derived any benefit from such delay.

2. The endorsement on the cause list indicates that though Rule is served, no appearance has been filed on behalf of the concerned party, nor is anyone present in person.

NEUTRAL CITATION

C/CA/4967/2025 ORDER DATED: 24/11/2025

undefined

3. In view of the explanation offered in the application mentioned hereinabove and in the absence of any opposition, the application for condonation of delay of 819 days deserves to be allowed.

4. Hence, present application is allowed. Delay of 819 days occurred in filing the appeal is condoned. Rule is made absolute accordingly.

(M. K. THAKKER,J) M.M.MIRZA

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter