Citation : 2025 Latest Caselaw 707 Guj
Judgement Date : 9 July, 2025
NEUTRAL CITATION
C/FA/4617/1998 JUDGMENT DATED: 09/07/2025
undefined
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
R/FIRST APPEAL NO. 4617 of 1998
FOR APPROVAL AND SIGNATURE:
HONOURABLE MR. JUSTICE HEMANT M. PRACHCHHAK
=======================================
Approved for Reporting Yes No
No
=======================================
EXECUTIVE ENGINEER
Versus
A PATEL & COMPANY & ANR.
=======================================
Appearance:
PRAPTI BHATT FOR AADITYA D BHATT(8580) for the Appellant
CHANDNI S JOSHI(9490) for the Appellant
MR KG SUKHWANI(871) for the Respondents
=======================================
CORAM:HONOURABLE MR. JUSTICE HEMANT M.
PRACHCHHAK
Date : 09/07/2025
ORAL JUDGMENT
1. Present appeal is filed by the appellant under Section 96 of the Civil Procedure Code against the judgment and order dated 02.05.1998 passed by the learned 6 th Joint Civil Judge (S.D.), Mehsana (hereinafter be referred to as "the trial Court") in Special Civil Suit No. 11 of 1998 whereby the trial Court dismissed the suit.
NEUTRAL CITATION
C/FA/4617/1998 JUDGMENT DATED: 09/07/2025
undefined
2. Facts giving rise to the present appeal are that appellant - original plaintiff had tendered for metalling work of 2 nd layer of the road for the Sami Dudhka Nani Chandur M.D.R. Road. The respondent had filled the tender and it was accepted by the appellant. The tender was accepted for Rs.3,85,407/- and it was 51.25% excess amount than the tender amount and, therefore, considering the said excess 51.25% amount of Rs.1,97,522/- the tender was accepted for the sum of Rs.5,92,929/- and the contract was executed between the plaintiff and defendant No.1. On assigning contract, respondent No.1 has commenced the work upon receipt of the work order issued by the appellant on 23.12.1976. The work was supposed to start from 24.12.1976 and was to be completed before 24.12.1977 i.e. within one year. It is the case of the appellant that the respondents have not completed the work within stipulated time agreed in terms and conditions of the contract. Therefore, appellant had issued notice on various dates mentioned in the memo of plaint, but the respondents did not pay any amount and not completed the work and only executed the work of Rs.3,63,447/- and, therefore, the Public Works Committee of the District Panchayat has passed a resolution dated 21.10.1980 and again issued the work in favour of one another agency to complete work and while doing so, it has incurred extra monetary loss. It is further the case of the appellant that even the respondents had not returned the empty drums and, therefore also, the appellant has incurred damage to the tune of Rs.6440/- in all the appellant has incurred loss of Rs.5,16,024/-. It is the case of the appellant that due to the loss, the appellant filed the suit before the trial Court for recovery of the damages along with 18% interest from the date
NEUTRAL CITATION
C/FA/4617/1998 JUDGMENT DATED: 09/07/2025
undefined
of suit till its realization.
2.1 The respondent No.2 filed written statement at Exhibit 14 and respondent No.1 also accepted the contents of the written statement at Exhibit 14 vide pursis at Exhibit 12, except the facts which is accepted by the respondent. The agreement was in two parts i.e. Schedule - A and Schedule - B. Schedule - A relates to supply of all the materials by the appellant to the respondents and Schedule - B relates to the items and specification contract to be executed. It was also under dispute that since the respondents have not provided the materials in time, therefore, respondents unable to complete the work of contract. It is the contention on the part of the respondents that even the appellant who was not proper party since the work contract was allocated by the Public Works Committee by resolution dated 21.10.1980.
2.2 The trial Court has, after considering the averments made in the plaint and the written statement, has framed the issues at Exhibit 21 as under:-
[1] Whether the plaintiff proves that the defendant No.1 is partnership firm and the defendant No.2 is its partner? [2] Whether the plaintiff proves that the defendant was issued the work of Sami - Dudhka - Nanichandur M.D.R. metalling road 2nd layer by tender and the agreement was executed for the same?
[3] Whether the plaintiff proves that the defendants have not completed the disputed work within time? [4] Whether the plaintiff proves that they are entitled for the
NEUTRAL CITATION
C/FA/4617/1998 JUDGMENT DATED: 09/07/2025
undefined
amount of damages ? If yes, what amount ?
[5] Whether the defendant proves that the plaintiff was failed to perform their part of duty as per the agreement? [6] Whether the defendant proves that the plaintiff has terminated the contract illegally?
[7] Whether this suit is barred for want of necessary parties? [8] Whether this suit is barred by limitation? [9] Whether the plaintiff is entitled for any relief? If yes, what reliefs?
[10] What order and decree?
2.3 Relying upon the issue more particularly issue No.8 where
the Court has framed the issue whether the suit is barred by limitation, which came to be answered by the trial Court in the affirmative after considering the facts of the case, relevant documents and the provision of Article 55 of the Limitation Act, 1963, which reads thus:-
For compensation for the When the contract is broken breach of any contract or [where there are express or implied not Three successive breaches] when herein specifically provided Years the breach in respect of for. which the suit is instituted occurs or [where the breach is continuing] when it ceases.
2.4 The trial Court, after hearing the learned counsel appearing for the respective parties and considering the material on record and evaluating the evidence, has dismissed the suit.
NEUTRAL CITATION
C/FA/4617/1998 JUDGMENT DATED: 09/07/2025
undefined
3. Being aggrieved and dissatisfied with the impugned judgment and order, the appellant has preferred the present appeal.
4. Heard Ms.Prapti Bhatt, learned counsel for the appellant and Mr.Paras Sukhwani, learned counsel for the respondents at length and perused the material on record.
5. Ms.Bhatt, learned counsel for the appellant has submitted the same facts which are narrated in the memo of appeal and has submitted that the impugned judgment and order passed by the trial Court is against the evidence on record. She has submitted that the respondent has not completed the work within the time stipulated as per the agreement and there is a breach of contract after 21.10.1990. She has submitted that as far as the limitation is concerned, the trial Court has wrongly applied Article 55 of the Limitation Act and failed to appreciate the fact that it is not the law that in every case of breach of contract, the limitation would commenced to run from the date of the breach, but only from the date when the party aggrieved is in a position to fix the damages. She has submitted that the occasion for ascertainment of the degree of damages or the precise amount which would represent the injury suffered by the breach is to be distinguished from the date when the cause of action arose and from which the limitation begins to run. She has submitted that when the third party has completed the work and when the final bill was processed then the actual loss caused to the appellant is determined and on the basis that the suit filed for recovery of the damages and compensation. She has submitted that the appeal deserves to be allowed and the
NEUTRAL CITATION
C/FA/4617/1998 JUDGMENT DATED: 09/07/2025
undefined
impugned judgment and order deserves to be quashed and set aside.
6. Mr.Sukhwani, learned counsel for the respondents has submitted that the trial Court has not committed any error of facts and law in passing the impugned judgment and order. He has submitted that the respondent has executed the work as per the terms and conditions of the agreement, however, the appellant had not provided relevant material in time and hence the progress of the work was not done as per the contract. He has submitted that the respondent had demanded the material in the year 1977, but the same was supplied only in the year 1978 and before that such material was not provided. He has submitted that the trial Court has, after considering the evidence and the decisions, has passed the impugned judgment and order and no interference is required to be called for. He has submitted that the appeal being meritless deserves to be dismissed.
7. Mr.Sukhwani, learned counsel has drawn attention to this Court that so far as the limitation to the present appeal is concerned, it is well settled that the breach of contract fall under the provision of Article 55 of the Limitation Act r/w. Sections 73 and 74 Indian Contract Act. It was clear from the provision of Article 55 of the Limitation Act that when the first breach was not noticed, the second contract dated 21.10.1980 was given to the third party is not proper and, thereafter, on completion of the contract work, the actual loss was assessed by the appellant and on the basis cause of action arose it is continuous loss caused to the appellant and, therefore, the provision of Article 55 of the Limitation Act r/w. Sections 73 and 74 of the Indian Contract Act
NEUTRAL CITATION
C/FA/4617/1998 JUDGMENT DATED: 09/07/2025
undefined
is not attracted in the present case.
8. When the respondent has abandoned the work and at that moment only, the cause of action arose and not from the date on which the appellant reckoned the loss or damages. Because prior to the date of issuance of the contract in favour of the third party the breach was already committed by the respondent and it was to their notice and hence, the appellant has connived and decided again to issue tender and, thereafter, given the contract to the third party on 21.10.1980 and, therefore, the contention raised on behalf of the appellant relating to the cause of action, only damage was assessed by the appellant which fact is completely erroneous, illegal and unjust. It is now well settled that the cause of action is abandonedly on fact and on perusal of the same, it is clear that prior to the date i.e. 21.10.1980, the work was abandoned by the respondent and considering that date, it appears that the cause of action arisen with regard to damage against the respondents. However, the said suit was instituted in the year 1990 and, therefore, the trial Court has rightly decided such issue in favour of the respondents and, thus, the appeal is devoid of merits.
9. This Court has considered the submissions advanced by the learned counsel appearing for the respective parties and the record and proceedings of the case and perused the impugned judgment and order and examined the document at exhibit 61. It appears that there was reciprocal promises given by the appellant to the respondents and on perusing the conditions stipulated in Schedule B, it is necessary to consider the provision of Section 51 to 54 of the Indian Contract Act, which reads thus:-
NEUTRAL CITATION
C/FA/4617/1998 JUDGMENT DATED: 09/07/2025
undefined
"51. Promiser not bound to perform, unless reciprocal promisee ready and willing to perform.--When a contract consists of reciprocal promises to be simultaneously performed, no promiser need perform his promise unless the promisee is ready and willing to perform his reciprocal promise.
Illustration
(a) A and B contract that A shall deliver goods to B to be paid for by B on delivery.
A need not deliver the goods, unless B is ready and willing to pay for the goods on delivery.
B need not pay for the goods, unless A is ready and willing to deliver them on payment.
(b) A and B contract that A shall deliver goods to B at a price to be paid by installments, the first installment to be paid on delivery.
A need not deliver, unless B is ready and willing to pay the first installment on delivery.
B need not pay the first installment, unless A is ready and willing to deliver the goods on payment of the first installment.
52.Order of performance of reciprocal promises.--Where the order in which reciprocal promises are to be performed is expressly fixed by the contract, they shall be performed in that order; and where the order is not expressly fixed by the contract, they shall be performed in that order which the nature of the transaction requires.
Illustrations
(a) A and B contract that A shall build a house for B at a fixed price. A's promise to build the house must be performed before B's promise to pay for it.
(b) A and B contract that A shall make over his stock-in- trade to B at a fixed price, and B promises to give security for the payment of the money. A's promise need not be
NEUTRAL CITATION
C/FA/4617/1998 JUDGMENT DATED: 09/07/2025
undefined
performed until the security is given, for the nature of the transaction requires that A should have security before he delivers up his stock.
53. Liability of party preventing event on which the contract is to take effect.--When a contract contains reciprocal promises, and one party to the contract prevents the other from performing his promise, the contract becomes voidable at the option of the party so prevented; and he is entitled to compensation from the other party for any loss which he may sustain in consequence of the nonperformance of the contract.
Illustration
A and B contract that B shall execute certain work for A for a thousand rupees. B is ready and willing to execute the work accordingly, but A prevents him from doing so. The contract is voidable at the option of B; and, if he elects to rescind it, he is entitled to recover from A compensation for any loss which he has incurred by its non-performance.
54. Effect of default as to that promise which should be first performed, in contract consisting of reciprocal promises.--When a contract consists of reciprocal promises, such that one of them cannot be performed, or that its performance cannot be claimed till the other has been performed, and the promiser of the promise last mentioned fails to perform it, such promiser cannot claim the performance of the reciprocal promise, and must make compensation to the other party to the contract for any loss which such other party may sustain by the non- performance of the contract.
Illustrations
(a) A hires B's ship to take in and convey, from Calcutta to the Mauritius, a cargo to be provided by A, B receiving a certain freight for its conveyance. A does not provide any cargo for the ship. A cannot claim the performance of B's promise, and must make compensation to B for the loss which B sustains by the non-performance of the contract.
(b) A contracts with B to execute certain builder's work for a fixed price, B supplying the scaffolding and timber necessary for the work. B refuses to furnish any scaffolding or timber, and the work cannot be executed. A need not
NEUTRAL CITATION
C/FA/4617/1998 JUDGMENT DATED: 09/07/2025
undefined
execute the work, and B is bound to make compensation to A for any loss caused to him by the non-performance of the contract.
(c) A contracts with B to deliver to him, at a specified price, certain merchandise on board a ship which cannot arrive for a month, and B engages to pay for the merchandise within a week from the date of the contract. B does not pay within the week. A's promise to deliver need not be performed, and B must make compensation.
(d) A promises B to sell him one hundred bales of merchandise, to be delivered next day, and B promises A to pay for them within a month. A does not deliver according to his promise. B's promise to pay need not be performed, and A must make compensation"
10. On perusal of the above referred provision and vis-a-vis condition stipulated in Schedule B, now if this Court considers that the work was not completed within stipulated time, it finds that the appellant had terminated the contract on 21.10.1980 and the respondents have accepted the same and since, the respondents have accepted the said condition as per the tender agreement at Exhibit 78 dated 05.05.1984, the work was allocated to third agency and the respondents have not taken any objections to the said work contract issued to third party and, therefore, the claim of the appellant was commenced from that date and the date can be reckoning for the purpose of cause of arose, however, the suit was filed after about seven years i.e. of the same year i.e. in the year 1990 and, therefore, the trial Court has, after considering the relevant documents and provisions of the Indian Contract Act, discussed the said aspects in para - 51 of the impugned judgment and order. The trial Court has elaborately discussed the provision of Article 55 of the Limitation Act and after considering the relevant dates, the trial
NEUTRAL CITATION
C/FA/4617/1998 JUDGMENT DATED: 09/07/2025
undefined
Court has observed in para - 53 which reads as under:-
"53. In this case, it is very clear that the defendants had made breach of the contract and, therefore, the plaintiff had rescinded the contract on dated 21-10-1980 as per Exh. 76 and the plaintiff had decided to complete the remaining work through another agency. Therefore, the breach of the contract was done by the defendant before dated 21-10-1980, after dated 21-10-1980 the defendant had not executed any work and there was no correspondence between the parties and, therefore, there was no continuing breaches of the contract after dated 21- 10-1980. So, as per the provisions of Article - 55 of the Limitation Act the period of limitation shall be counted from dated 21-10-1980 and the period of limitation is expired on dated 21-10-1983. This suit is filed on dated 5-1-1990 and, therefore, this suit is clearly time barred."
11. The suit is being one for damages for breach of contract, it is governed by Article 55 of the Limitation Act and therefore, the suit should have been filed within three years from the date of the breach. Here, the breach has been committed on 23.12.1976. In pursuance of clause 4 of the agreement, the suit ought to have filed within three years from the date of abandonment by the present respondents within three years from the breach of the agreement. The contract was determined. Thus, the trial Court has rightly held that the suit was barred by the provision of Article 55 of the Limitation Act. It is worthwhile to refer to the decisions of the Hon'ble Supreme Court in the case of Sundaram Finance Limited Vs. Noorjahan Beevi reported in 2016 (0) AIR(SC) 3183 : 2016 (13) SCC 1, in the case of State Of Gujarat Vs. Kothari And Associates reported in 2016 (14) SCC 761 and in the case of Rajagopala Naidu Vs. Aiyyaswamy Chettiar reported in 1965 AIR Madras 532 wherein the Hon'ble Court has held that a suit was
NEUTRAL CITATION
C/FA/4617/1998 JUDGMENT DATED: 09/07/2025
undefined
filed for damages sustained upon a breach and consequent upon a resale, time would commence to run not from the date of the breach but only after the resale when the exact amount of damages could be ascertained by the plaintiff. This argument was not accepted and it was held that time would commence to run under Art. 115 from the date of the breach. The Court has further observed that this claim is definitely out of time. It ought to have been instituted within 3 years of the date of the breach of the contract and it is no defence to this objection to argue that it was only the occasion of resale which enabled the defendant firm to ascertain exactly the degree of damages, or precise amount which would represent the injury suffered by them. The occasion for ascertainment will have to be distinguished from the date upon which the cause of action arose and from which limitation began to run. It is also to be referred to the decision of the Hon'ble Supreme Court in the case of Food Corporation Of India Vs. Babulal Agrawal with Babulal Agrawal Vs. Food Corporation of India reported in (2004) 2 SCC 712.
12. Thus, this Court is of the opinion that in view of the aforesaid observation and the decisions of the Hon'ble Supreme Court, the suit was time barred and it was decided on the aforesaid basis and after considering the oral as well as documentary evidence and the relevant provisions of law, the trial Court has rightly dismissed the suit filed by the appellant on the ground of limitation as observed after relying upon the various decisions of the Hon'ble Supreme Court, this Court as well as other High Courts.
13. In above view of the matter, I am of the opinion that the
NEUTRAL CITATION
C/FA/4617/1998 JUDGMENT DATED: 09/07/2025
undefined
trial Court has not committed any error of facts and law in passing the impugned judgment and order and I do not find any illegality and/or infirmity in the impugned judgment and order. The trial Court has discussed the relevant documentary evidence which goes to the route of the matter and suggests that the cause of action is already commenced from 1980 since the appellant has allocated the work to the third party, however, the suit was filed in the year 1990 and, therefore, the same is grossly time barred. There is no substance in the present appeal to interfere with by this Court and the appeal being meritless deserves to be dismissed.
14. In view of the above, the present appeal is dismissed. Record and proceedings be transmitted back to the concerned Court forthwith. Pending civil application stands disposed of accordingly.
(HEMANT M. PRACHCHHAK,J) V.R. PANCHAL
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!