Tuesday, 02, Jun, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Gujarat Water Supply And Sewerage Board vs Pashim Gujarat Vij Cop Ltd
2025 Latest Caselaw 8834 Guj

Citation : 2025 Latest Caselaw 8834 Guj
Judgement Date : 17 December, 2025

[Cites 4, Cited by 0]

Gujarat High Court

Gujarat Water Supply And Sewerage Board vs Pashim Gujarat Vij Cop Ltd on 17 December, 2025

                                                                                                                   NEUTRAL CITATION




                             C/FA/2555/2005                                     JUDGMENT DATED: 17/12/2025

                                                                                                                    undefined




                               IN THE HIGH COURT OF GUJARAT AT AHMEDABAD

                                               R/FIRST APPEAL NO. 2555 of 2005

                       FOR APPROVAL AND SIGNATURE:

                       HONOURABLE MR. JUSTICE DEVAN M. DESAI
                       ==================================================
                                     Approved for Reporting                       Yes                   No

                       ==================================================
                                   GUJARAT WATER SUPPLY AND SEWERAGE BOARD & ANR.
                                                        Versus
                                           PASHIM GUJARAT VIJ COP LTD & ANR.
                       ==================================================
                       Appearance:
                       MR KH BAXI(150) for the Appellant(s) No. 1,2
                       MS MAYA S DESAI(285) for the Defendant(s) No. 1
                       RULE SERVED for the Defendant(s) No. 2
                       ==================================================

                            CORAM:HONOURABLE MR. JUSTICE DEVAN M. DESAI

                                                            Date : 17/12/2025

                                                            ORAL JUDGMENT

1. This appeal is preferred by the appellants - original

defendants under Section 96 of the Code of Civil

Procedure, 1908 (for short, hereinafter referred to as

`the Code') challenging the judgment and decree

dated 29.6.2005 (for short, `the impugned judgment')

passed by the learned Principal Senior Civil Judge,

Surendranagar in Special Civil Suit No.60 of 2001.

NEUTRAL CITATION

C/FA/2555/2005 JUDGMENT DATED: 17/12/2025

undefined

2. Heard learned advocate Mr. K. H. Baxi for the

appellants and learned advocate Ms. Maya Desai for

respondent No.1. Though served, none appeared for

respondent No.2. Perused the record.

3. The facts in brief of the case are as under:

* The respondent No.1 herein - original plaintiff had

filed a suit for recovery of Rs.12,22,548-98 Paisa from

the present appellant Nos.1 and 2 - original defendant

Nos.1 and 2 and present respondent No.2 - original

defendant No.3. As per the case of the plaintiff, the

defendant had undergone Surendranagar underground

gutter project for which defendants demanded 375 KVA

electric load for which an agreement was executed by

defendants in favour of plaintiff. It is contended by

plaintiffs that defendants agreed to pay minimum

charges for the period of 2 years. As defendants did not

NEUTRAL CITATION

C/FA/2555/2005 JUDGMENT DATED: 17/12/2025

undefined

submit test report and did not pay the amount of

deposit though informed, a notice dated 19.3.1998 was

issued and defendants were asked to submit the

report.

* As defendants failed to pay agreed minimum

charges for the period of 1997-98, the suit came to be

filed for recovery of Rs.9,02,017.07 Paisa towards

connection of 375 KVA and R.20,351-91 Paisa towards

connection of 130 KVA. The defendants upon service

of summons appeared and filed Written Statement at

Exhibits 12 and 22 respectively. On the basis of

pleadings, issues were framed at Exhibit 23. Plaintiff

examined Praveenchandra Himmatlal at Exhibit 41 and

Lavjibhai Bhudarbhai Bagadia at Exhibit 75. Defendant

Nos.1 and 2 examined Surendrakumar Motilal,

Assistant engineer at Exhibit 106. Defendant No.3 did

not examine any witness.

NEUTRAL CITATION

C/FA/2555/2005 JUDGMENT DATED: 17/12/2025

undefined

* After considering the evidence, learned Court

below decreed the suit and defendants were jointly and

severally directed to pay an amount of Rs.12,22,548.98

Paisa to the plaintiff with interest at the rate of 9% per

annum from the date of suit till realization.

* Being aggrieved and dissatisfied with the

impugned judgment and decree, original defendant

Nos.1 and 2 - present appellants have filed this appeal.

4. Learned advocate for the appellants, at the outset,

contended that the defendant No.1 is an agent of

defendant No.3 and as defendant No.3, was in need of

electric load for the purpose of laying down

underground sewage project, original defendant No.3 -

Corporation applied for the power supply of 375 KVA

with the plaintiff. The application Exhibit 50 establishes

the aforesaid fact that the application was made by the

Chief Officer, Surendranagar Municipality,

NEUTRAL CITATION

C/FA/2555/2005 JUDGMENT DATED: 17/12/2025

undefined

Surendranagar.

5. It is further contended that the defendant Nos.1 and 2

had never applied for any supply of electric load. It is

contended that though the agreement Exhibits 42 and

43 for 375 KVA and 130 KVA were signed by defendant

Nos.1 and 2, the contracting party is defendant No.3

and the conditions stipulated in the 2 agreements also

contemplate that the consumer, namely; the

Corporation, shall be liable to pay the amount of

minimum guarantee as if the supply is actually

commenced from the date of expiration of said notice

of three months. It is further contended that both the

agreements were signed by the defendant Nos.1 and 2

as agents of defendant No.3 and the terms and

conditions stipulated in both the agreements cannot be

made applicable to the defendant Nos.1 and 2.

6. It is further contended that the entire project was

NEUTRAL CITATION

C/FA/2555/2005 JUDGMENT DATED: 17/12/2025

undefined

budgeted by the Municipality. The defendant Nos.1 and

2 were only to execute the work entrusted by

defendant No.3. After completion of the project, as per

the provisions contained in the Gujarat Water Supply

and Sewerage Board Act, 1978, the site was to be

handed over to defendant No.3. The defendant Nos.1

and 2 are not the ultimate consumer. The ultimate

consumer is defendant No.3. It is, therefore, contended

that the learned trial Court has wrongly held defendant

Nos.1 and 2 liable for the amount of minimum charges.

No other submissions are made except the above.

7. Per contra, learned advocate for the plaintiff -

respondent No.1 herein has supported the judgment

and decree and contended that all defendants have

signed the agreements exhibit 42 and 43 and,

therefore, terms and conditions stipulated in the

agreements are binding to defendant Nos.1 and 2 also.

Learned Advocate for the Plaintiff has taken this Court

NEUTRAL CITATION

C/FA/2555/2005 JUDGMENT DATED: 17/12/2025

undefined

through the Written Statement at exhibit 22 filed by

the Municipality, wherein, it is contended that as per

the order of defendant No.3, defendant Nos.1 and 2

were supposed to carry out the work of underground

sewerage project. Defendant Nos.1 and 2 were

entrusted the work and the work was to be undertaken

under the supervision of defendant Nos.1 and 2. The

sum and substance of the defense of defendant No.3 is

that since the work was not completed by defendant

Nos.1 and 2, defendant Nos.1 and 2 are solely liable for

the amount claimed by plaintiff.

8. It is further contended by learned advocate for the

respondent that the learned trial Court has considered

the undisputed fact that bills were issued in the name

of defendant No.3 but was given to defendant Nos.1

and 2. The defendant Nos.1 and 2 in their oral

deposition have admitted that test report was

supposed to be submitted by them as per agreements

NEUTRAL CITATION

C/FA/2555/2005 JUDGMENT DATED: 17/12/2025

undefined

Exhs.42 and 43. It also comes out on record that during

the cross examination of witness of defendant Nos.1

and 2 that the test report was not submitted by

defendant Nos.1 and 2. Notices Exhs.45 and 46 though

were duly received by defendants were neither replied

to nor acted upon by defendants. Therefore, as per the

Agreements Exhibits 42 and 43, defendants have

rightly been held liable for the minimum charges. No

other submissions are made except the above.

9. I have considered the submissions canvassed by

learned advocates for the parties and perused Record

& Proceedings.

10. The question which is under consideration in the

present appeal is whether the appellants-original

defendant Nos.1 and 2 can be held liable for the breach

of the terms and conditions of Agreements Exhibit 42

and 43, which is undisputedly signed by defendant

NEUTRAL CITATION

C/FA/2555/2005 JUDGMENT DATED: 17/12/2025

undefined

Nos.1 and 2 and not signed by defendant No.3.

11. The preamble of the Agreement indicates that the

contracting parties are the plaintiff and defendant

No.3, namely; Chief Officer, Surendranagar

Municipality, Surendranagar. It is also an admitted fact

coming out from perusal of Written Statement of

defendants that defendant Nos.1 and 2 acted as an

agent of defendant No.3 and the work of defendant

No.3 under Surendranagar Underground Sewage

Project, for which defendant No.3 applied with the

plaintiff for the supply of electrical energy. Exhibit 50 is

an application which undisputedly mentions the name

of applicant as Chief Officer, Surendranagar

Municipality Surendranagar. The application also

stipulates that defendant No.3 agreed to take supply

and pay for this energy, service connection and other

dues, including the deposit of such security as to be

demanded by the Plaintiff Board. Exhibits 42 and 43

NEUTRAL CITATION

C/FA/2555/2005 JUDGMENT DATED: 17/12/2025

undefined

are the agreements executed between the plaintiff and

defendant No.3 for supply of 375 KVA load and 130

KVA load respectively. The contention of the learned

advocate for the appellants is mainly that though the

agreements have been signed by defendant Nos.1 and

2, the contracting parties are plaintiff and defendant

No.3, as defendant No.3 was the Principal who

undertook the work of laying underground sewage.

Defendant Nos.1 and 2 being an agent of defendant

No.3 cannot be held liable for the minimum used

charges as claimed by the plaintiff. Upon perusal of

Exhibits 42 and 43, it is found that the plaintiff except

the supply of electric load, all other terms and

conditions are same. Therefore, for the purpose of

convenience, condition No.2(b) of Exhibit 42 is

reproduced hereunder for the sake of convenience:

"2(b) If the supplier is ready to commence supply save in respect of any work or works remaining to be done on the consumer's premises due to non-completion of suitable accommodation and / or in complete work of the consumer to receive supply the consumer shall be liable to pay the amount of minimum guarantee as hereinafter provided as if the supply is actually commenced from the

NEUTRAL CITATION

C/FA/2555/2005 JUDGMENT DATED: 17/12/2025

undefined

date of expiration of said notice of three months unless the General Manager (Comm.) has granted any extension of time as provided in sub-clasue (a) above."

* The aforesaid clause binds defendant No.3 that

the consumer namely defendant No.3 shall be liable to

pay the amount of minimum guarantee charges. Under

the head of charges for supply at page No.4 of Exhibit

42, the defendant No.3 has agreed to pay to the

supplier every month which includes minimum charges

mentioned in the Supplier's Tariff Schedule. On

scrutinizing the entire evidence, the execution of

agreements Exhibits 42 and 43 are not in dispute.

12. The only dispute is with regard to whether defendants

jointly and severally can be held liable for the demand

of minimum charges. If the case of defendants is

perused, defendant Nos.1 and 2 have projected

themselves as an agent of defendant No.3. Though

defendant No.3 has not stepped into the witness box,

the burden of payment of minimum charges has been

NEUTRAL CITATION

C/FA/2555/2005 JUDGMENT DATED: 17/12/2025

undefined

thrown upon defendant Nos.1 and 2 as defendant

Nos.1 and 2 were entrusted the work of laying down

underground sewage. For non-compliance of the work,

defendant No. 3 has tried to escape from the liability of

payment of minimum charges to the plaintiff. The

application for supply of electric load was undisputedly

applied by defendant No.3 and defendant No.3 is

termed as a consumer as mentioned in the preamble of

agreements.

13. At this stage, relevant provisions as contemplated

under the Indian Contract Act, 1872 are required to be

considered. Section 211 of the Act deals with agent's

duty in conducting principal's business. Section 211 of

the Act is reproduced hereunder:

"211. Agent's duty in conducting principal's business.--

An agent is bound to conduct the business of his principal according to the directions given by the principal, or, in the absence of any such directions, according to the custom which prevails in doing business of the same kind at the place where the agent conducts such business. When the agent acts otherwise, if any

NEUTRAL CITATION

C/FA/2555/2005 JUDGMENT DATED: 17/12/2025

undefined

loss be sustained, he must make it good to his principal, and if any profit accrues, he must account for it."

* The aforesaid provision contemplates that the

agent is bound to conduct the business of his

principal according to the directions given by the

principal and when the agent acts otherwise, if any

loss is sustained, the agent must make it good to his

principal. Similarly, if any profit accrues out of the

acts done by agent, he must account for it to the

principal.

14. In the present case, as evident from the record that the

test report was to be submitted by defendant Nos.1

and 2 and the same, admittedly, were not supplied by

defendant Nos.1 and 2 though demanded by plaintiff. It

is not the case of the defendant Nos.1 and 2 that the

work which was entrusted by the principal-defendant

No. 3 was successfully concluded. Since the evidence

does not indicate with regard to the completion of

NEUTRAL CITATION

C/FA/2555/2005 JUDGMENT DATED: 17/12/2025

undefined

project, it can be presumed that the work remained

incomplete for one reason or the other. Agreements, in

the present case, in clear terms make the consumer

liable to pay minimum charges and when such

minimum charges are not paid by the consumer,

defendant No.3 - the consumer is liable for payment of

such amount. Similarly, defendant Nos.1 and 2 being

the agent of defendant No.3 and being the signatory of

the agreements, equally cannot escape from the

liability of payment of minimum charges. The Contract

Act deals with agent's duty to principal as well as

principal's duty to agent. Section 222 of the Indian

Contract Act, 1872 deals with indemnification of agent

against consequences of lawful acts. Section 222 of the

Act is reproduced hereunder:

"222. Agent to be indemnified against consequences of lawful acts.--

The employer of an agent is bound to indemnify him against the consequences of all lawful acts done by such agent in exercise of the authority conferred upon him."

NEUTRAL CITATION

C/FA/2555/2005 JUDGMENT DATED: 17/12/2025

undefined

* The aforesaid provision mandates that the agent

is bound to be indemnified by the principal against the

consequences of all lawful acts in exercise of the

authority conferred upon him.

15. Learned trial Court after appreciating the evidence

found that all defendants are jointly and severally

liable to pay the amount of minimum charges as

demanded by plaintiff. During the course of

submissions, I have been informed that defendant No.3

has not assailed the impugned judgment and decree

and, therefore, the impugned judgment and decree has

attained finality qua defendant No.3.

16. Learned advocate for the appellant could not point out

any proposition of law on the question that the terms

and conditions of the agreements are not binding

merely on signing the agreements. In my view, a

person who signs a contract is legally bound by the

NEUTRAL CITATION

C/FA/2555/2005 JUDGMENT DATED: 17/12/2025

undefined

terms and conditions of the contract. Such party is

legally responsible for fulfilling the terms and

conditions outlined in the contract. In the present case,

defendant Nos.1 and 2 have asserted that defendant

No.3 appointed them as agent and defendant No.3 also

affirms that defendant Nos.1 and 2 were the agent. It is

not the case of defendant Nos.1 and 2 that the

agreements were signed under misrepresentation or

the agreements were executed by practiced upon

fraud. Since both the agreements are legally and

validly executed, defendant Nos.1 and 2 cannot escape

their liability to pay any amount for the breach of any

terms and conditions of agreements.

17. Learned Advocate for the appellant has further

submitted that the decreetal amount has been

deposited by the appellant before the learned trial

Court. A decree of jointly and severely liable to pay

means more than one defendants are responsible for

NEUTRAL CITATION

C/FA/2555/2005 JUDGMENT DATED: 17/12/2025

undefined

the entire decreetal amount. The judgment holder is

permitted to recover the entire decreetal amount

from any of the judgment debtor or from all of them

together. Even if one of the judgment debtor cannot

pay, while paying party can then seek reimbursement

from other judgment debtors for their share. The

judgment debtor who has paid more than its share,

can then claim reimbursement for the portion by way

of filing execution against the other judgment debtor.

Therefore, appellant may recover the amount paid

more than its share from original defendant No.3 if

permissible under law.

18. In the aforesaid facts and in absence of any contrary

evidence as well as in absence of any provisions of law,

I do not find any reason to interfere in the findings

arrived at by learned trial Court. Resultantly, the

appeal lacks merit and it deserves to be dismissed and

accordingly it is dismissed.

NEUTRAL CITATION

C/FA/2555/2005 JUDGMENT DATED: 17/12/2025

undefined

19. Record & Proceedings, if any, be sent back to the

concerned Court forthwith. Interim Relief, if any, stands

vacated forthwith. No order as to costs.

(D. M. DESAI,J) VATSAL

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter