Citation : 2023 Latest Caselaw 1467 Guj
Judgement Date : 13 February, 2023
C/FA/77/2007 ORDER DATED: 13/02/2023
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
R/FIRST APPEAL NO. 77 of 2007
==========================================================
HITH CONSTRUCTION COMPANY
Versus
UNION OF INDIA THRO' THE EXECUTIVE ENGINEER & 1 other(s)
==========================================================
Appearance:
MR KG SUKHWANI(871) for the Appellant(s) No. 1
for the Defendant(s) No. 2
RULE UNSERVED for the Defendant(s) No. 1
==========================================================
CORAM:HONOURABLE MR. JUSTICE A.J.DESAI
and
HONOURABLE MR. JUSTICE RAJENDRA M. SAREEN
Date : 13/02/2023
ORAL ORDER
(PER : HONOURABLE MR. JUSTICE A.J.DESAI)
1. By way of present appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (herein after referred to as "the Act"), the original applicant has challenged the judgment and order dated 05.08.2006 passed by the learned Additional District Judge, Vadodara in Civil Misc. Application No.108 of 2001, by which an application filed by the present appellant under Section 37 of the Act challenging the legality and validity of an order rendered in Agreemtn No.14/TCD/BRD/1995-96 dated 03.05.2001 by the sole arbitrator came to be dismissed.
2. The appeal came to be admitted vide order dated 09.02.2007.
C/FA/77/2007 ORDER DATED: 13/02/2023
3. The brief facts arising from the record are as under;
3.1 The appellant - original petitioner/applicant was awarded a contract for construction of 6 type-II, 6 type-III and 1 type - IV staff quarters at GIDC, Ankleshwar by an Agreement No.14/ TCD/BRD/1995-96 dated 03.05.2001.
3.2 Certain dispute has arisen between the parties and therefore, sole arbitrator was appointed. Learned arbitrator by an award dated 03.05.2001 held that the present appellant would be entitled to Rs.1,08,049/- with simple interest at the rate of 10%. The said order was challenged before the Court of learned Additional District Judge, Vadodara being Civil Misc. Application No.108 of 2001. The learned trial Court having considered the challenge by the present appellant under Section 34 of the Act and relying upon various decisions by the Hon'ble Apex Court, dismissed the application. Hence, this appeal.
4. We have heard learned advocate Mr. Sukhwani for the appellant and Central Government Standing Counsel Mr. Ankit Shah for the respondent.
5. Learned advocates have supplied the xerox copy of documents including award by the arbitrator, which has been taken on record. Learned advocates have stated that issue involved in the present appeal is purely a legal question and has been dealt with by the Hon'ble Apex Court as well as the division bench of this Court in various cases and requested that the appeal may be decided on the legal issue and
C/FA/77/2007 ORDER DATED: 13/02/2023
therefore Record and Proceedings are not required to be called for and therefore, we have not called for the Record and Proceedings.
6. Learned advocate Mr. Sukhwani has tried to argue the appeal by submitting that there is misinterpretation of the terms of contract between the parties by the trial Court as well as by the learned arbitrator. He has submitted that this Court as well as the trial Court can examine the contract and can modify the award or quash and set aside the award passed by the arbitrator. He, therefore, would submit to allow the appeal.
7. Learned advocate Mr. Shah has relied upon a decision of the Hon'ble Apex Court in case of Associate Builders vs. Delhi Development Corporation reported in 2015 (3) SCC 49 and would submit that powers under Section 34 of the Act are very limited, unless the Court finds that award is in conflict with the public policy and violated the principle of judicial approach and not in compliance of principle of natural justice and thus the award is perverse. He would submit that there are series of judgments delivered by the Hon'ble Apex Court on same point. He would submit that the division bench of this Court relying upon a decision of the Hon'ble Apex Court in case of Associates Builder (supra) has held that there is no need to interfere with the award unless the Court finds any perversity as stated herein above. In support of his submission, he has relied upon a decision of the division bench of this Court dated 15.10.2019 in case of State of Gujarat vs. M/s. K. M. Patel passed in First Appeal No.692 of 1990. He has also
C/FA/77/2007 ORDER DATED: 13/02/2023
relied upon series of judgments, however, for the sake of convenience we have not referred them here, since they all are on similar issue.
8. We have heard learned advocates appearing for the respective parties. We have also gone through the award as well as impugned judgment and order passed by the trial Court. The only ground raised is interpreting the clauses, more particularly Clause No. 2. As per the decision of the Hon'ble Apex Court in case of Associate Builders (supra), which has been relied upon by the division bench of this Court in case of M/s. K. M. Patel (supra), we are in the agreement with the submissions advanced by learned advocate Mr. Shah. Apart from that as per the Section 34 of the Act even by this Court for examining the impugned award, similar principle would be applicable. Hence, we do not find any reason to interfere with the judgment and award impugned in this appeal. Hence, the same is dismissed.
9. In view of dismissal of main appeal, Civil Application does not survive and disposed of accordingly.
(A.J.DESAI, J)
(RAJENDRA M. SAREEN,J) DRASHTI K. SHUKLA
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!