Citation : 2021 Latest Caselaw 11266 Guj
Judgement Date : 10 August, 2021
C/SCA/8093/2020 JUDGMENT DATED: 10/08/2021
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
R/SPECIAL CIVIL APPLICATION NO. 8093 of 2020
FOR APPROVAL AND SIGNATURE:
HONOURABLE MR. JUSTICE J.B.PARDIWALA
and
HONOURABLE MS. JUSTICE VAIBHAVI D. NANAVATI
=============================================
1 Whether Reporters of Local Papers may be allowed
to see the judgment ?
2 To be referred to the Reporter or not ?
3 Whether their Lordships wish to see the fair copy
of the judgment ?
4 Whether this case involves a substantial question
of law as to the interpretation of the Constitution
of India or any order made thereunder ?
=============================================
M/S SARASWATI CONSTRUCTION CO. THRU SHRI MAHESHBHAI B.
VANIYA
Versus
UNION OF INDIA, MINISTRY OF HOUSING AND URBAN AFFAIRS,
CENTRAL PUBLIC WORKS DEPT THRU SECRETARY
=============================================
Appearance:
MR DA BAMBHANIA(139) for the Petitioner(s) No. 1
for the Respondent(s) No. 1,2,3,4
MR DEVANG VYAS(2794) for the Respondent(s) No. 5
MR HR PRAJAPATI(674) for the Respondent(s) No. 6
=============================================
CORAM:HONOURABLE MR. JUSTICE J.B.PARDIWALA
and
HONOURABLE MS. JUSTICE VAIBHAVI D. NANAVATI
Date : 10/08/2021
ORAL JUDGMENT
C/SCA/8093/2020 JUDGMENT DATED: 10/08/2021
(PER : HONOURABLE MS. JUSTICE VAIBHAVI D. NANAVATI)
1. By this writ application under Article 226 of the Constitution of India, the writ applicant has prayed for the following reliefs:
"A. Quashing and setting aside the decision and communication dated 16/6/2020, issued by the respondent no.5, at Annexure - A to the petition, including, actions and further actions of the respondent authorities, which authorize and or permit the authorities to further process the remaining tender, and isssuance of work orders and entering into contract with the sole agency, without considering the tender of the Petitioner, as Pre-qualified, and acting on the said communication declaring ineligible and its operation, and further operation may pleased be declared illegal, null and void, and respondents be restrained from taking any further actions and orders pursuant to E-mail- letter, passed and issued by the respondent No.5, by holding it to be illegal, arbitrary, in complete brech of provisions of law, and set procedure and in clear violation of Article 14, 19 and 21 of the Constitution of India.
Be pleased to issue appropriate writ and or direction and or orders, directing the respondents to treat the Petitioner as Pre- qualified, and to entertain the tender bid and decide as if the petitioner is Pre-qualified, as an agency competent to bid and qualified for opening the tender.
B. Quashing and setting aside all the consequential actions and orders, based on declaration as incligible, including action of authority to process further the tenders and take steps relating to the EMD of the Petitioner.
BB. Quashing and setting aside the decision and communication dated 01.07.2020 at Annexure A & J dated 16.06.2020 and 01.07.2020 including actions and further actions pursuant to acceptance of render of Respondent no.6 under Annexure - J, vide communication dated 01.07.2020 and restoring the position prevent prior to 16.06.2020 and directing the respondent authorities to examine the tender bid of the petitioner for pre-bid qualification, in terms of tender clause, and decide in accordance with the set procedure for awarding the contract, by restoring the facts prior to 16.06.2020, as if no further steps have been taken and tender bid of Respondent no.6 and the petitioner are to be process de-novo by declaring that, the petitioner bid reqires to be consider and opened for pre-bid technical qualification, by issuing appropriate writ and/or orders, and directions;
BC. Pending admission, hearing and final disposal of the Petition, this Hon'ble Court may be pleased to restrain the respondents and their agents and servants, from acting upon the communication dated 16.06.2020 and 01.07.2020 Annexure-
C/SCA/8093/2020 JUDGMENT DATED: 10/08/2021
A & J, and further process pursuant to communication and order dated 01.07.2020 (Annexure - J) without deciding and considering the tender of the petitioner;
C. Pending admission, hearing and final disposal of the petition be pleased to restrain by way of injunction, restraining the respondents their agents and servants from implementing and further executing the impugned letter dated 16/6/2020 and further be pleased to make an order restraining the respondents their agents and servant from further operating and deciding on the basis of sole remaining tender of agency, without deciding, and considering the tender of the petitioner.
D. to grant any other relief and or further relief/s which this Hon'ble Court finds it just and proper in the interest of justice.
E. to provide for the cost of the petition.
F. The annexure to the petition is the true copy of the
original."
2. The facts giving rise to the present writ application may be summarized as under:
2.1 The writ applicant is a partnership firm, carrying on business activity as M/s. Saraswati Construction Co., having established and registered as 'AA'-Class Contractor and the same is in operation with Government of Gujarat and with other specified various Government Authorities in the territory of India.
2.2 The respondents authorities invited E-tenders for constructions of Border Road from BP 1175 to G-17 including Protection work, Precast RCC box type culverts, Modular Fencing and flood lighting along Indo-Pak B0rder in Bhuj Sector, Gujarat. The writ applicant submitted E-tender with all documents as per the terms of the Notice inviting E-tender on 24.04.2020. However, on 01.06.2020, the writ applicant was asked to submit the work completion certificate. Thereafter, several E-mail communications were took place between the
C/SCA/8093/2020 JUDGMENT DATED: 10/08/2021
respondents and the writ applicant regarding the requisite documents and certain clarifications. On 16.06.2020, one E- mail communication was addressed by the Executive Engineer of the respondent authority to the writ applicant informing about the ineligibility of the writ applicant for the pre- qualification bid.
2.3 Being aggrieved by the communication dated 16.06.2020, the writ applicant approached this Court by filing the present writ application.
3. Submissions on behalf of the writ applicant: 3.1 Mr. Bambhania, the learned counsel appering for the writ applicant would submit that pursuant to the tender notice No.07/CE/BFZ/EE(P-II)/2019-20 inviting online tender, the writ applicant submitted its tender by following and completing all the formalities for execution of work contract i.e. Construction of Border Road from BP 1175 to G-17 including protection work, Precast RCC Box type culverts, Modular Fencing and Flood lighting along Indo-Pak Border in Bhuj Sector, Gujarat for an estimated cost of Rs.146,88,33,311/-. Mr. Bambhania would submit that while uploading and submitting the tender as per the procedure prescribed, the writ applicant annexed/submitted and uploaded the completion certificate in the prescribed format under the General Law of Contract and CPWD Manual, mode and method of issuance of such certificate as prescribed in the form of "G" Form. Relying upon page 37 of the application, Mr. Bambhania would submit that the writ applicant fulfills all the eligibility criteria as per the terms and conditions of the notice inviting tender.
3.2 Mr. Bambhania, would also submit that the writ applicant
C/SCA/8093/2020 JUDGMENT DATED: 10/08/2021
was fulfilling all the eligibility criteria more particularly, as mentioned in condition no.1.2.1 of the notice inviting tender and has submitted the work completion certificate under the prescribed form in due compliance with the terms and conditions of the Notice inviting Tender. Mr. Bambhania, would further submit that with a view to favour the respondent no.6 for awarding the contract, all the queries and issues were raised in the bid documents of the present writ applicant. Mr. Bambhania, would further submit that the action on the part of the respondents has not only resulted in depriving the writ applicant of benefits which had accrued from the contract agreement in question but it has also adversely affected the writ applicant of other works out of which some are pending and payment has not been made to the writ applicant. Mr. Bambhania, would further submit that there is total non application of mind on the part of the respondents in not considering the facts and circumstances mentioned by the writ applicant in his replies dated 16.06.2020 and 21.06.2020. Mr. Bambhania, would therefore, urge that the writ application may be allowed and the impugned communication dated 16.06.2020 may be quashed and set aside.
3.3 Mr. Bambhania, the learned counsel has relied upon the decisions of the Supreme Court rendered in the cases of Ramana Dayaram Shetty vs. International Airport Authority of India reported in (1979) 3SCC 489, Afcons Infrastructure Ltd. vs. Nagpur Metro Rail Corporation Ltd. & Anr. reported in (2016) 16SCC 818, Vidarbha Irrigation Development Corporation vs. Anoj Kumar Agarwala reported in 2019(2) Scale 134 and Andhra Industrial Works A.P. vs. Chief Controller of imports and ors. reported in AIR 1974 SC 1539.
C/SCA/8093/2020 JUDGMENT DATED: 10/08/2021
4. Submissions on behalf of the respondents:
4.1 Mr. Devang Vyas, the learned ASG would submit that the work of construction of Border road, for which the tendering was done, relates to the National security of the Country. This work has been undertaken to develop protection infrastructure of the boundaries for effective operational domain as also to ensure fullproof security by Border Security Force and other defense forces which are being undertaken as of utmost priority by Ministry of Home Affairs with assistance and execution through CPWD. According to Mr. Vyas, when the bids were invited and the tender documents were floated, one of the most significant and mandatory condition to be fulfilled by potential bidders was tender condition being condition no.1.2.1 of the Notice inviting tender, which inter alia provided for the criteria of eligibility for contractors/bidders and those who fulfills the requirements, were the only entities to be considered as eligible to apply. Considering the national policy formulated by the Central Government, the joint ventures are not accepted and the most essential requirement was that of satisfactory completion of the works mentioned in the said clause.
4.2 Relying upon the condition no.1.2.1 of the Notice inviting tender, Mr. Vyas would submit that the tender conditions/bid conditions are equally applied to every bidding entity and are not only binding to every bidder, but are to be strictly adhered to by the answering respondent while undertaking the entire bidding process. He would also submits that it is an admitted position that the condition in no uncertain terms contemplates that only satisfactorily completed works will be taken into
C/SCA/8093/2020 JUDGMENT DATED: 10/08/2021
consideration. The tender was responded by two bidders i.e. the writ applicant and the respondent No.6. Mr. Vyas would submit that the bid of the writ applicant has not been considered and the same was rejected on two grounds; (1) for want of non-furnishing of completion certificate and (2) for non-submission of contract executed between the original tenderer M/s. Sadbhav Engineering Limited and the writ applicant.
4.3 According to Mr. Vyas, it is impossible for the authorities/ competent authority to ascertain the veracity of the claims made by the writ applicant and the said aspect is therefore, rightly considered by the competent authority against the writ applicant. He would submit that this Court may not entertain the contentions raised by the writ applicant in the present writ application and be pleased to dismiss the present petition as it involves disputed question of facts.
4.4 Relying upon page 37 of the petition, Mr. Vyas would submit that the document, which according to the petitioner fulfills the eligibility criteria, is nothing but a misperception on the part of the writ applicant inasmuch as, the form and format in which the eligibility certificate was to be provided, was not as per the bid document and in fact, the said document is nothing, but just an experience certificate issued by the Executive Engineer, MSRDC (Limited), Mumbai (Camp office Nasik) and the same is not a satisfactorily completed work certificate. Mr. Vyas would also submit that if the said certificate is perused, more particularly, serial no.9 thereof, it clearly indicates that the actual date of completion/expected date of completion is mentioned as 31.03.2020 whereas the
C/SCA/8093/2020 JUDGMENT DATED: 10/08/2021
certificate is issued on 20.03.2020. He would further submit that as the work is not complete and thus, the writ applicant cannot claim himself to be eligible and cannot said to be fulfilling the criteria of NIT bid condition no.1.2.1.
4.5 Mr. Vyas would further submit that it is a settled position of law that when the bidder fails to fulfill the criteria as contemplated in the bid documents/tender documents, he cannot claim any rights for such tender and having failed to meet the eligibility criteria, it would not be open for him to challenge either the tender conditions or to subject grant of tender in favour of a successful bidder. He would submit that when the writ applicant failed to produce a valid completion certificate in support of its claim of being eligible, the other contention raised in the writ application deserve no attention of this Court and therefore, on the same ground, the present writ application may also be dismissed.
4.6 Mr. Vyas, the learned ASG has relied upon the decisions in case of Municipal Corporation, Ujjain and another vs. BVG India Limited and others reported in (2018) 5SCC 462, Consortium of Titagarh Firema Adler, S.P.A., Titagarh Wagons Ltd. Through Authorized Signatory, West Bengal vs. Nagpur Metro Rail Corporation Ltd., through its General Manager (Procurement) and Ors. reported in (2017) 7 SCC 486, and JSW Infrastructure Limited and Ors. vs. Kakinada Seaports Limited and Ors. reported in (2017) 4 SCC 170.
Submissions on behalf of the respondent no.6:
5. Mr. H.R. Prajapati, the learned counsel appearing for the respondent no.6 would submit that the respondent no.6 has
C/SCA/8093/2020 JUDGMENT DATED: 10/08/2021
fully qualified all the relevant terms and conditions of the tender document and after following all the due procedure, the respondent no.6 is awarded the contract work. He would submit that the writ applicant was not qualified as per the terms and conditions of the tender and therefore, the contract work has not been awarded to the writ applicant. Mr. Prajapati, would also submit that the contract for which the tender was issued and in respect of which grievance is raised by the writ applicant, is not a statutory contract. Mr. Prajapati, would further submit that the Supreme Court in numerous cases, has held that the terms of the invitation to tender cannot be open to judicial scrutiny because the same are within the realm of the contract. Mr. Prajapati, would further submit that the Hon'ble Supreme Court has held that the State while inviting tenders can fix its own terms of invitation to the tender and that is not open to judicial scrutiny.
5.1 Mr. Prajapati, would submit that the writ applicant agreed upon an acceptance of all the terms and conditions while participating in the tender proceedings and therefore, it is now not open for the writ applicant to contend anything contrary to the terms and conditions of the tender documents. Mr. Prajapati would also submit that the writ applicant could not produce the required successful completion certificate which is specifically and mandatorily required as per the tender documents and therefore, the writ applicant was not found eligible to award the contract. Mr. Prajapati, would further submit that instead of providing the successfully completed work certificate, the writ applicant has provided the work experience certificate, which cannot be termed as the successfully completed work certificate. Mr. Prajapati, would
C/SCA/8093/2020 JUDGMENT DATED: 10/08/2021
submit that the writ applicant being a company, cannot seek any relief under Article 19 of the Constitution of India, and therefore, the present writ application at the instance of the company is not maintainable and the same is required to be dismissed.
6. We have heard Mr. D. A. Bambhania, the learned counsel appearing for the writ applicant, Mr. Devang Vyas, the learned Additional Solicitor General appearing for the respondent no.5 and Mr. H.R. Prajapati, the learned counsel appearing for the respondent no.6.
Analysis:-
7. Having heard the learned counsel appearing for the respective parties and having gone through the material placed on record, the short question which falls for our consideration is whether the writ applicant has duly complied with the eligibility criteria of the bid document providing eligibility criteria and conditions more particularly, condition no.1.2.1 which provides for the criteria of eligibility for submission of the bid document.
8. At this stage, we would like to refer the condition no.1.2.1 of the Notice inviting Tender, which reads as under:
"1.2.1 Criteria of eligiblity for submission of dib documents. Contractors who fulfill the following requirements shall be eligible to apply.
Joint ventures are not accepted.
(a) should have satisfactorily completed the work as mentioned below in the last Seven years ending on the last day of the month previous to the one in which the bids are invited. This hould be certified by an officer not below the rank of Executive Engineer/ Project Manager or equivalent:-
Three similar works of each costing not less than R.5875/- lacs.
C/SCA/8093/2020 JUDGMENT DATED: 10/08/2021
Two similar works each costing not less than Rs.Rs.8815/- lacs. One similar work costing not less than Rs.11,750/- lacs."
9. The Supreme Court in case of Municipal Corporation, Ujjain and another vs. BVG India Limited and others reported in (2018) 5SCC 462, has held as under:
"48. The authority concerned is in the best position to find out the best person or the best quotation depending on the work to be entrusted under the contract. If a bidder had faced a number of show-cause notices from various municipal corporations in the matter of non-performance of door to door collection of garbage etc., the Court cannot compel the authority to choose such undeserving person/company to carry out the work. Ultimately, the public interest must be safeguarded. The public would be directly interested in the timely fulfilment of the contract so that the services become available to the public expeditiously and effectively. The public would also be interested in the quality of work undertaken. Poor quality of work or goods can lead to tremendous public hardship and substantial financial outlay either in correcting mistakes or in rectifying defects or even at times in re-doing the entire work. Lethargy or tardiness in collecting door to door garbage on a day-to-day basis would definitely lead to increase collection of garbage on the roads and public properties, which leads to health hazards and also reduces the cleanliness of the city. Since the public is directly interested and would be affected if the work entrusted is not carried out appropriately, and as the technical expert has found that respondent no.1 would not be a suitable company to be entrusted the work inasmuch as it had faced 73 show-cause notices from different Municipal Corporations, the High Court could not have interfered with the decision taken by the authority. In our considered opinion, the High Court has ignored the element of public interest involved in the matter.
49. As aforementioned, unless the Court concludes that the decision making process or the decision taken by the authority bristles with mala fides, arbitrariness, or perversity, or that the authority has intended to favour someone, the Constitutional Court will not interfere with the decision-making process or the decision.
50. Thus, the questions to be decided in this appeal are answered as follows:
(a) Under the scope of judicial review, the High Court could not ordinarily interfere with the judgment of the expert consultant on the issues of technical qualifications of a bidder when the consultant takes into consideration various factors including the basis of non-performance of the bidder;
(b) A bidder who submits a bid expressly declaring that it is submitting the same independently and without any 52 partners, consortium or joint venture, cannot rely upon the
C/SCA/8093/2020 JUDGMENT DATED: 10/08/2021
technical qualifications of any 3rd Party for its qualification.
(c) It is not open to the Court to independently evaluate the technical bids and financial bids of the parties as an appellate authority for coming to its conclusion inasmuch as unless the thresholds of mala fides, intention to favour someone or bias, arbitrariness, irrationality or perversity are met, where a decision is taken purely on public interest, the Court ordinarily should exercise judicial restraint."
9.1 The Supreme Court in case of Consortium of Titagarh Firema Adler, S.P.A., Titagarh Wagons Ltd. Through Authorized Signatory, West Bengal vs. Nagpur Metro Rail Corporation Ltd., through its General Manager (Procurement) and Ors. reported in (2017) 7 SCC 486, has held as under:
"30. The learned counsel for the appellants invited our attention to the authority in W.B. Electricity Board v. Patel Engineering Co. Ltd. wherein it has been ruled:
"24. ... The appellant, Respondents 1 to 4 and Respondents 10 and 11 are all bound by the ITB which should be complied with scrupulously. In a work of this nature and magnitude where bidders who fulfil prequalification alone are invited to bid, adherence to the instructions cannot be given a go-by by branding it as a pedantic approach, otherwise it will encourage and provide scope for discrimination, arbitrariness and favouritism which are totally opposed to the rule of law and our constitutional values. The very purpose of issuing rules/instructions is to ensure their enforcement lest the rule of law should be a casualty. Relaxation or waiver of a rule or condition, unless so provided under the ITB, by the State or its agencies (the appellant) in favour of one bidder would create justifiable doubts in the minds of other bidders, would impair the rule of transparency and fairness and provide room for manipulation to suit the whims of the State agencies in picking and choosing a bidder for awarding contracts as in the case of distributing bounty or charity. In our view such approach should always be avoided. Where power to relax or waive a rule or a condition exists under the rules, it has to be done strictly in compliance with the rules. We have, therefore, no hesitation in concluding that adherence to the ITB or rules is the best principle to be followed, which is also in the best public interest.
xxxxx
31. ... Thae Project undertaken by the appellant is undoubtedly for the benefit of the public. The mode of execution of the work of the Project should also ensure that the public interest is best served. Tenders are invited on the basis of competitive bidding for execution of the work of the Project as it serves dual purposes. On the one hand it offers a fair opportunity to all those who are interested in competing for the contract relating to
C/SCA/8093/2020 JUDGMENT DATED: 10/08/2021
execution of the work and, on the other hand it affords the appellant a choice to select the best of the competitors on a competitive price without prejudice to the quality of the work. Above all, it eliminates favouritism and discrimination in awarding public works to contractors. ... Merely because a bid is the lowest the requirements of compliance with the rules and conditions. ..."
31. Having stated this, we have to see, how the 1st respondent has perceived the offer of the respondent No. 2 in the backdrop of the tender conditions. It is not in dispute that the project in question has been funded by KfW Development Bank, Germany and as per Clause ITB 35.8, it is necessary at all stages of bid evaluation and contract award has to be subject to no-objection from KfW Development Bank. Emphasis has been laid on the approach of the High Court which has taken note of the fact that the respondent No. 2 had been awarded the tender by the Delhi Metro Rail Corporation. It has also been highlighted that the papers relating to the financial bid along with report were forwarded to KfW which gave its no- objection. Be it noted, the appellants have been quite critical about the acceptance of the offer and the 1st respondent has given a number of reasons to justify the same. As indicated earlier, we are only concerned with the eligibility criteria and not with the fiscal aspect.
34. As is noticeable, there is material on record that the respondent No. 2, a Government company, is the owner of the subsidiaries companies and subsidiaries companies have experience. The 1st respondent, as it appears, has applied its commercial wisdom in the understanding and interpretation which has been given the concurrence by the concerned Committee and the financing bank. We are disposed to think that the concept of "Government owned entity" cannot be conferred a narrow construction. It would include its subsidiaries subject to the satisfaction of the owner. There need not be a formation of a joint venture or a consortium. In the obtaining fact situation, the interpretation placed by the 1st respondent in the absence of any kind of perversity, bias or mala fide should not be interfered with in exercise of power of judicial review. Decision taken by the 1st respondent, as is perceptible, is keeping in view the commercial wisdom and the expertise and it is no way against the public interest. Therefore, we concur with the view expressed by the High Court.
"36. That it is further clear from the record that besides being the lowest bidder, the experience of R 2 in supplying Metro Trains across the world exceeds the Petitioner's experience by a huge margin. Where for clause 12, R 2 has shown a figure of 594 Metro Cars, Petitioner has shown only 72 Cars; and for clause 12.1 where R 2 has shown 432 Cars, Petitioner has again shown only 72 Cars. This vast experience of R 2 would be beneficial for the project and would further public interest.
37. That R 1 without any malice, or malafide has treated R 2 along with its 100% subsidiaries as one entity. This understanding of the clause has been at the ends of both parties viz. R 1 and R 2, who were ad idem vis-à- vis the eligibility of the
C/SCA/8093/2020 JUDGMENT DATED: 10/08/2021
parent company to bid using the experience and executing the contract through its various 100% wholly owned subsidiaries.
38. That the above understanding of R 1 of treating R 2 along with its 100% subsidiaries is supported by the understanding of the Delhi Metro Rail Corporation Ltd., which has on a similarly, if not same, worded bid- document granted the tender/agreement to R 2, which had even there bid as a parent company claiming experience of and execution through 100% wholly owned subsidiaries."
9.2 The Supreme Court in case of JSW Infrastructure Limited and Ors. vs. Kakinada Seaports Limited and Ors. reported in (2017) 4 SCC 170, has held as under:
"8. On a bare reading of the Policy Clause some weightage and meaning has to be given not only to the word "next" as done by the High Court but also to the words "only one private operator" appearing in the opening part of the Clause. The words "only one private operator" cannot be treated as surplusage. The entire clause has to be read as a whole in the context of the purpose of the policy which is to avoid and restrict monopoly. In our opinion, this Clause will apply only when there is one single private operator in a port. If this single private operator is operating a berth, dealing with one specific cargo then alone will he not be allowed to bid for next berth for handling the same specific cargo. The High Court erred in interpreting the clause only in the context of the word "next" and ignored the opening part of the Clause which clearly indicates that the Clause is only applicable when there is only one private berth operator. It appears to us that the intention is that when a port is started, if the first berth for a specific cargo is awarded in favour of one private operator then he cannot be permitted to bid for the next berth for the same type of cargo. However, once there are more than one private operators operating in the port then any one of them can be permitted to bid even for successive berths. In the present case, as pointed out above there already 5 private operators other than the first consortium.
9. We may also add that the law is well settled that superior courts while exercising their power of judicial review must act with restraint while dealing with contractual matters. A Three Judge Bench of this Court in Tata Cellular vs. Union of India[3] held that (i) there should be judicial restraint in review of administrative action; (ii) the court should not act like court of appeal; it cannot review the decision but can only review the decision making process (iii) the court does not usually have the necessary expertise to correct such technical decisions.; (iv) the employer must have play in the joints i.e., necessary freedom to take administrative decisions within certain boundaries.
10. In Jagdish Mandal vs. State of Orissa[4] this Court held that evaluation of tenders and awarding contracts are essentially
C/SCA/8093/2020 JUDGMENT DATED: 10/08/2021
commercial functions and if the decision is bonafide and taken in the public interest the superior courts should refrain from exercising their power of judicial review. In the present case there are no allegations of mala fides and the appellant consortium has offered better revenue sharing to the employer.
11. In Afcons Infrastructure Ltd. Vs. Nagpur Metro Rail Corporation Ltd. & Anr.[5] This Court held as follows :-
"14.....a mere disagreement with the decision making process or the decision of the administrative authority is no reason for a constitutional Court to interfere. The threshold of mala fides, intention to favour someone or arbitrariness, irrationality or perversity must be met before the constitutional Court interferes with the decision making process or the decision. xxx xxx xxx
16. We may add that the owner or the employer of a project, having authored the tender documents, is the best person to understand and appreciate its requirements and interpret its documents. The constitutional Courts must defer to this understanding and appreciation of the tender documents, unless there is mala fide or perversity in the understanding or appreciation or in the application of the terms of the tender conditions. It is possible that the owner or employer of a project may give an interpretation to the tender documents that is not acceptable to the constitutional Courts but that by itself is not a reason for interfering with the interpretation given.
17. In the present appeals, although there does not appear to be any ambiguity or doubt about the interpretation given by NMRCL to the tender conditions, we are of the view that even if there was such an ambiguity or doubt, the High Court ought to have refrained from giving its own interpretation unless it had come to a clear conclusion that the interpretation given by NMRCL was perverse or mala fide or intended to favour one of the bidders. This was certainly not the case either before the High Court or before this Court...." The view taken in Afcons (supra) was followed in Monte Carlo Ltd. Vs. NTPC Ltd.[6] . Thus it is apparent that in contractual matters, the Writ Courts should not interfere unless the decision taken is totally arbitrary, perverse or mala fide.
12. Strong reliance has been placed on behalf of the second consortium on the judgment rendered in APM Terminals B.V. vs. Union of India and Another. We are of the considered view that the said judgment cannot be applied to the present case because in that case this court considered the clauses of the contract. The policy which was applicable in APM Terminal, was not the policy of 2010 but the policy of 2007, the wording of which is totally different. True it is, that in the said judgment reference has also been made to the new policy but that was not specifically dealt with by the Court, and the matter was decided on an interpretation of the terms of the contract and the policy of 2007."
C/SCA/8093/2020 JUDGMENT DATED: 10/08/2021
10. The Supreme Court in case of Vidarbha Irrigation Development Corporation reported in 2019(2) Scale 134 has held as under:
"14. However, learned counsel appearing on behalf of the appellant strongly relied upon Afcons Infrastructure Ltd. v. Nagpur Metro Rail Corpn. Ltd., (2016) 16 SCC 818, and paragraphs 14 and 15 in particular, which state:
"14. We must reiterate the words of caution that this Court has stated right from the time when Ramana Dayaram Shetty v. International Airport Authority of India [Ramana Dayaram Shetty v. International Airport Authority of India, (1979) 3 SCC 489] was decided almost 40 years ago, namely, that the words used in the tender documents cannot be ignored or treated as redundant or superfluous -- they must be given meaning and their necessary significance. In this context, the use of the word "metro" in Clause 4.2(a) of Section III of the bid documents and its connotation in ordinary parlance cannot be overlooked.
15. We may add that the owner or the employer of a project, having authored the tender documents, is the best person to understand and appreciate its requirements and interpret its documents. The constitutional courts must defer to this understanding and appreciation of the tender documents, unless there is mala fide or perversity in the understanding or appreciation or in the application of the terms of the tender conditions. It is possible that the owner or employer of a project may give an interpretation to the tender documents that is not acceptable to the constitutional courts but that by itself is not a reason for interfering with the interpretation given."
It is clear even on a reading of this judgment that the words used in the tender document cannot be ignored or treated as redundant or superfluous - they must be given meaning and their necessary significance. Given the fact that in the present case, an essential tender condition which had to be strictly complied with was not so complied with, the appellant would have no power to condone lack of such strict compliance. Any such condonation, as has been done in the present case, would amount to perversity in the understanding or appreciation of the terms of the tender conditions, which must be interfered with by a constitutional court."
11. In view of the ratio laid down in the above referred decisions, we are of the view that the tender conditions are required to be read as provided in the tender document and if there are two views or construction possible than the view of the authority interpreting the tender document should be
C/SCA/8093/2020 JUDGMENT DATED: 10/08/2021
accepted. The owner/employer of the project having authored the tender document is the best person to understand and appreciate the terms and conditions of the said document. The Court should be slow in interpreting the tender conditions unless the interpretation sought to be put forward smacks of malafide or is perverse.
11.1 In the case on hand, the certificate produced by the writ applicant at page 37 cannot be termed as a work completion certificate but it is an experience certificate. By communication dated 01.06.2020, the relaxations were given by the Government and the writ applicant was asked to submit the certificate at the earliest. However, the writ applicant informed the authority that although the work had been completed yet due to nation wide lockdown in view of Covid-19 pandemic, the completion certificate could not be procured. Further, by communication dated 02.06.2020, the writ applicant was asked to submit the agreement executed between the M/s. Sadbhav Engineering and the writ applicant, who claims to have completed the work as sub-contractor, for the work of Shreenathji- Udaipur Toll Way Pvt. Ltd. project 4 laning of Gomati-Choraha to Udaipur section NH-8 from 177.00 to 260.100in the State of Rajasthan under NHDP Phase 4 on toll basis. By communication dated 09.06.2020, the respondent authority once again asked the writ applicant to submit the aforesaid agreement, however, the same was not furnished.
12. We have no hesitation in coming to the conclusion that the writ applicant was unable to produce the work completion certificate, which is a mandatory requirement and also the agreement between the M/s. Sadbhav Engineering Ltd. and
C/SCA/8093/2020 JUDGMENT DATED: 10/08/2021
Principal Agency, in-spite of the extension of time granted by the State Government for production of such certificate and as requested by the concerned authority, the writ applicant has not made a positive submission asserting that the writ applicant was possessing the required documents.
13. In view of the aforesaid, we are not inclined to interfere with the decision dated 16.06.2020 of the respondent no.5 and the consequent decision of awarding the contract in favour of the respondent no.6. Further, the Union awarded the contract in favour of the respondent no.6 way back on 10.07.2020. Since the contract has been awarded to respondent no.6 as back as on 10.07.2020 as also considering the fact that the respondent no.6 has mobilized its menpower and machinery and is already undertaking the awarded work, we are not inclined to exercise jurisdiction under Article 226 of the Constitution of India.
14. In the result, the present writ application fails and is hereby dismissed.
(J. B. PARDIWALA, J)
(VAIBHAVI D. NANAVATI,J)
NEHA
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!