Citation : 2025 Latest Caselaw 4705 Gua
Judgement Date : 20 August, 2025
Page No.# 1/6
GAHC010277502024
undefined
THE GAUHATI HIGH COURT
(HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
Case No. : Arb.P./5/2025
RKD INFRASTRUCTURE PVT. LTD.
A COMPANY INCORPORATED UNDER THE COMPANIES ACT, 1956 HAVING
ITS REGISTERED OFFICE AT 49, P.C. SORCAR SARANI, KOLKATA- 700019
AND IS REPRESENTED BY ITS DIRECTOR SHRI RATAN KUMAR DAS,
RESIDENT OF 9A, BROAD STREET, BALLYGUNGE, S.O., BALLYGUNGE,
KOLKATA- 700019.
VERSUS
THE UNION OF INDIA AND 4 ORS.
REPRESENTED BY THE SECRETARY, MINISTRY OF RAILWAYS, RAILWAY
BOARD, RAILWAY BHAWAN, NEW DELHI.
2:THE GENERAL MANAGER/ CONSTRUCTION
OFFICE OF THE GENERAL MANAGER/ CON.
NORTHEAST FRONTIER RAILWAY
MALIGAON
GUWAHATI- 781011.
3:THE CHIEF ADMINISTRATIVE OFFICER/ CON-VIII
OFFICE OF THE GENERAL MANAGER/ CON.
NORTHEAST FRONTIER RAILWAY
MALIGAON
GUWAHATI- 781011.
4:THE CHIEF ENGINEER/ CONSTRUCTION-VIII
NORTHEAST FRONTIER RAILWAY
MALIGAON
GUWAHATI- 781011.
5:THE DEPUTY CHIEF ENGINEER/ CONSTRUCTION
Page No.# 2/6
NORTHEAST FRONTIER RAILWAY
RANGIA- 781534
Advocate for the Petitioner : MR G N SAHEWALLA, MS G DUGAR,MS T J SAHEWALLA,MS
K SARMA,MR M SAHEWALLA
Advocate for the Respondent : DY.S.G.I., MRS. R DEVI (C.G.C)
BEFORE
HONOURABLE MR. JUSTICE SOUMITRA SAIKIA
ORDER
20.08.2025
Heard Mr. GN Sahewalla, learned Senior Counsel assisted by Ms. TJ Sahewalla, learned counsel for the petitioner and Ms. R Devi, learned CGC for the respondents.
2. This is an application filed under Section 11 (5) of the Arbitration and Conciliation Act, 1996 seeking for appointment of the arbitrator to adjudicate the disputes between the parties arising out of the Contract Agreement No. CON/N-A/2729 dated 29.06.2022 for execution of work, namely, Linking of BG track with 60 kg single/long welded panels with 1660 nos. PSC sleeper per km in main line and 60 kg/52 kg single/three rails welded panels with 1540 nos. PSC sleeper per km in loop lines including linking of 1 in 12, 1 in 8 ½ and derailing switches on PSC sleepers (Fan Shaped Layout) laying of SEJs etc..., dismantling of BG track, point & crossings from km 355/0 to 394/5 (CH 103700 To 143470)= 39.77 KM (including RNY-AGT yard)." Subsequently, the contract stood terminated by the NF Railway Authorities vide notice dated 15.09.2023, whereby the contract stood rescinded in terms of the Clause 62 of the Standard General Condition of Contract. The petitioner represented before the authority Page No.# 3/6
and also served a notice under Section 21 of the Arbitration and Conciliation Act, 1996, calling upon the respondents to appoint an arbitrator. Since the respondents did not refer the matter to the arbitration, the present application under Section 11 (5) of the Arbitration and Conciliation Act, 1996 has been filed.
3. Learned counsel for the parties have been heard. Pleadings available on record have been perused.
4. The respondents have filed their objection disputing the claim made by the petitioner. The primary objection raised is that due to the mismanagement of the petitioner's agency, the progress of the work could not be achieved. Therefore, there is no question of conceding to the prayer or making a reference to arbitration.
5. Having considered the submissions made by the learned counsel for the parties and also upon conserving the judgment referred before the Court it is seen that the Co-ordinate Bench of this Court in Arb.P. No.20/2021 & others passed by the order dated 18.12.2022 arrived at a finding that the referral Court under Section 11 of the Arbitration and Conciliation Act, 1996 should have minimal intervention at the stage of appointment of an Arbitrator. All questions may be raised before the appointed Arbitrator for decision, and if the parties are aggrieved by the award, they shall have recourse to file an application under Section 34. This judgment was also referred to and relied upon in a subsequent judgment of this Court rendered in W.P.(C) No. 1076/2024, wherein, by judgment and order dated 31.08.2024, similar issues were decided while considering an application challenging a decision rendered by the arbitral tribunal.
6. The law in this respect has been settled by the judgment of the Apex Page No.# 4/6
Court in SBI General Insurance Co. Ltd. v. Krish Spinning (2024 INSC
532), wherein it was held that a referral court is primarily required to examine whether an arbitration agreement exists. If such an agreement is found to be in existence, and the parties have agreed to refer the matter to arbitration--either to an arbitrator suggested by the petitioner or one appointed by the Court--the reference must be made accordingly.
7. The agreement prescribing a sole Arbitrator to be appointed from the panel of arbitrators maintained by the respondents can no longer be a valid clause in view of the law laid down by the Apex Court in Central Organization for Railway Electrification Vs. ECI SPIC SMO MCML (JV), reported in 2024 SCC Online SC 3219. A Constitution Bench of five Hon'ble Judges of the Supreme Court passed the judgment in three parts, the majority view of the Judgment is extracted as under:
"a. The principle of equal treatment of parties applies at all stages of arbitration proceedings, including the stage of appointment of arbitrators;
b. The Arbitration Act does not prohibit PSUs from empanelling potential arbitrators. However, an arbitration clause cannot mandate the other party to select its arbitrator from the panel curated by PSUs;
c. A clause that allows one party to unilaterally appoint a sole arbitrator gives rise to justifiable doubts as to the independence and impartiality of the arbitrator. Further, such a unilateral clause is exclusive and hinders equal participation of the other party in the appointment process of arbitrators;
d. In the appointment of a three-member panel, mandating the other party to select its arbitrator from a curated panel of potential arbitrators is against the principle of equal treatment of parties. In this situation, there is no effective counterbalance because parties do not participate equally in the process of appointing arbitrators. The process of appointing arbitrators in CORE (supra) is unequal and prejudiced in favour of the Railways;
e. Unilateral appointment clauses in public-private contracts are violative of Article 14 of the Constitution;
f. The principle of express waiver contained under the proviso to Section 12(5) also Page No.# 5/6
applies to situations where the parties seek to waive the allegation of bias against an arbitrator appointed unilaterally by one of the parties. After the disputes have arisen, the parties can determine whether there is a necessity to waive the nemo judex rule; and
g. The law laid down in the present reference will apply prospectively to arbitrator appointments to be made after the date of this judgment. This direction applies to three-member tribunals"
The majority view of the larger Bench of the Apex Court in Central Organization for Railway Electrification (Supra) held that the prescription of the reference to an Arbitrator to be determined by the employer even in the face of the waiver by the petitioner will be contrary to the spirit of mandate of Arbitration and Conciliation Act, 1996 and accordingly held that such provisions will no longer be binding notwithstanding the same being a part of the Arbitration Agreement.
8. Under such circumstances, this Court is inclined to allow the petition and refer the matter to arbitration to decide the differences arising between the parties to the Contract Agreement No. CON/N-A/2729 dated 29.06.2022 for execution of work, namely, Linking of BG track with 60 kg single/long welded panels with 1660 nos. PSC sleeper per km in main line and 60 kg/52 kg single/three rails welded panels with 1540 nos. PSC sleeper per km in loop lines including linking of 1 in 12, 1 in 8 ½ and derailing switches on PSC sleepers (Fan Shaped Layout) laying of SEJs etc..., dismantling of BG track, point & crossings from km 355/0 to 394/5 (CH 103700 To 143470)= 39.77 KM (including RNY-AGT yard)." This Court considers it appropriate to appoint Shri PK Mushahary, Former Hon'ble Judge of the Gauhati High Court to be a prospective Arbitrator to decide the dispute arising by and between the parties. The Presiding Arbitrator will furnish a written declaration as required under Section 12 (1)(b) of the Arbitration and Conciliation Act, 1996 and upon such declaration being furnished before the Court, the appointment will be made absolute.
Page No.# 6/6
9. The parties are permitted to place a copy of this Order before Shri PK Mushahary, Former Hon'ble Judge of the Gauhati High Court within a period of 2 (two) weeks from the date of receipt of a certified copy of this order and apprise the learned prospective arbitrator about the Order of the Court. The appointment of the prospective sole arbitrator shall be confirmed upon receipt of the written disclosure as presented under Section 12 (1)(b) of the Arbitration and Conciliation Act, 1996.
10. Accordingly, let the matter be listed again on 10.09.2025 enabling the parties to place the disclosure of the learned prospective Arbitrator sought to be appointed by this Court and place it before the Court. The order confirming the appointment of the Arbitrator will be passed upon receipt of the disclosure.
JUDGE
Comparing Assistant
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!