Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Ramjus vs B.S.E.S Rajdhani Power Ltd
2026 Latest Caselaw 857 Del

Citation : 2026 Latest Caselaw 857 Del
Judgement Date : 13 February, 2026

[Cites 9, Cited by 0]

Delhi High Court

Ramjus vs B.S.E.S Rajdhani Power Ltd on 13 February, 2026

                          *      IN THE HIGH COURT OF DELHI AT NEW DELHI
                          %                                Judgment Reserved on: 10.02.2026
                                                           Judgment pronounced on: 13.02.2026

                          +      CRL.A. 371/2018 & CRL.M.A. 5700/2018
                                 RAMJUS                                               .....Appellant
                                                      Through:   Mr. Satyajit Kumar Singh, Advocate.

                                                      Versus

                                 B.S.E.S RAJDHANI POWER LTD                  .....Respondent
                                                Through: Mr. Sharique Hussain, Ms. Kirti Garg
                                                         and Mr. Raghav Awasthi, Advocates
                                                         for BSES RPL.

                          CORAM:
                          HON'BLE MS. JUSTICE CHANDRASEKHARAN SUDHA
                                                      JUDGMENT

CHANDRASEKHARAN SUDHA, J.

1. In this appeal filed under Section 374 of the Code of

Criminal Procedure, 1973 (the Cr.P.C) read with Section 156 of

the Electricity Act, 2003 (the Act), the 1st accused in CC No.

505/2014 on the file of the Additional Sessions Judge, Special

Electricity Court, Saket Courts, New Delhi, assails the judgment

dated 07.11.2017 as per which he has been convicted for the

offence punishable under Section 135 of the Act.

2. In the complaint filed under Section 151 of the Act, it

was alleged by the complainant (respondent herein) thus:- on

07.03.2014, an inspection was conducted by the complainant,

namely, P. Bhaskar, Assistant Manager (PW1), Tausif Ahmad,

Engineer and Anoop, Lineman(PW3) at a jhuggi, situated near

Shri Mata Kirtan Mandali, B 15711, Freedom Fighter Enclave,

New Delhi 110068. The jhuggi was found to be in use and

occupation of the 1st and 2nd accused. During the inspection, it was

found that the accused persons were indulging in theft of

electricity for domestic purposes with a connected load of 6.775

KW by illegally tapping electricity from the complainant's service

cable, thereby causing loss and damage to the complainant.

2.1. After the inspection and raid, the inspection team

prepared the inspection report, load report and seizure memo dated

07.03.2014at the site. Videography was also carried out. As it was

a case of direct theft of electricity, a theft bill dated 12.03.2014

was raised to the tune of ₹ 2,22,445/-, assessed in accordance with

the provisions of Delhi Electricity Supply Code and Performance

Standards Regulations, 2007 and as per the applicable tariff

prevalent at the time of the inspection, against the accused persons,

which was served on them. As the accused persons failed to pay

the same, the complaint was filed alleging commission of the

offence punishable under Section 135 of the Act.

3. On receipt of summons from the trial court, the 1st

accused entered appearance. However, the 2nd accused absconded

and hence was declared a proclaimed absconder. The substance of

the accusation was read over and explained to the accused, to

which he pleaded not guilty. A1 submitted that it is a false and

fabricated case made against him by the complainant and that he

was not liable to pay any loss or damage to the complainant.

4. On behalf of the prosecution, PWs.1 to 4 were

examined and Exts. PW. PX, PW. PY, CW.1/A-B, CW. 2/A-G, P-

1, EX.PX were marked in support of the case.

5. After the close of the prosecution evidence, the 1st

accused was questioned under Section 313 Cr.P.C regarding the

incriminating circumstances appearing against him in the evidence

of the complainant. The 1st accused denied all those circumstances

and maintained his innocence. He submitted that he did not

commit any theft of electricity. The premises do not belong to him.

It belongs to the 2nd accused. A1 is residing at B 125A, Freedom

Fighter Colony, Maidan Garhi, Neb Sarai, New Delhi and that at

the time of inspection, he was merely present at the jhuggi, as A2,

the owner had gone to his native place. No oral or documentary

evidence was adduced by the accused.

6. Upon consideration of the oral and documentary

evidence on record and after hearing both sides, the trial court,

vide the impugned judgment dated 07.11.2017 held the 1st accused

guilty of the offence punishable under Section 135 of the Act and

hence sentenced him to undergo rigorous imprisonment for a

period of three months and to pay fine of ₹ 3,20,958/-, and in

default of payment of fine, to undergo simple imprisonment for

two months and also directed to pay an amount of ₹ 2,13,975/-,

towards his civil liability. Aggrieved, the 1st accused has preferred

this present appeal.

7. It was submitted by the learned counsel for the

appellant/ 1st accused that the latter cannot be held liable for the

offence punishable under Section 135 of the Act, inasmuch as the

2nd accused, who has been declared a proclaimed absconder, is the

owner of the jhuggi involved in the alleged theft of electricity and

the A1is residing at B 125A, Freedom Fighter Colony, Maidan

Garhi, Neb Sarai, New Delhi and that he was merely present at the

jhuggi, as the 2nd accused had asked him to look after the same..

In support of this submission, reliance was placed on the Aadhaar

card of the wife of the 2nd accused, annexed with the pleadings.

When questioned regarding his own Aadhaar card, it was

submitted that the same had not been prepared at the relevant time.

It was further submitted that, considering the nature of the jhuggi,

the number of equipment and machinery mentioned in the load

report, Ext. CW2/B, is highly improbable. It was also submitted

that none of the documents or reports prepared by the raiding

members were signed by him.

8. Per Contra, it was submitted by the learned counsel for

the respondent that the impugned judgment does not suffer from

any infirmity warranting interference by this court as the trial court

has duly considered each and every ground raised in the present

appeal. It was submitted that, as per the third proviso to Section

135(1) of the Act, once the existence of artificial means or

unauthorised abstraction of electricity is established, a statutory

presumption arises against the consumer or the person in

occupation of the premises. The burden thereafter shifts upon such

person to rebut the presumption by leading cogent and credible

evidence. In the present case, the accused has failed to discharge

the said burden or to place any material on record to disprove the

presumption.On the other hand,the complainant has led credible

evidence to that effect, the videography has also been duly proved,

and the accused persons have been rightly identified, goes the

argument.

9. Heard both sides and perused the records.

10. The only point that arises in the appeal is whether the

impugned judgment suffers from any infirmity calling for an

interference of the court.

11. I shall first briefly refer to the evidence on record relied

on by the complainant in support of the case. The inspection/raid

in this case is alleged to have taken place on 07.03.2014 at 02:00

PM.

12. PW1, Manager of the Complainant Company deposed

that, on 07.03.2014, he inspected the premises i.e. jhuggi near

Mata Kiran Mandal, B-15711, Freedom Fighter Enclave, New

Delhi-68.The inspection team consisted ofTausif Ahmed, Engineer

and Anoop, Lineman as well as Rahul Sharma, Videographer from

M/s Arora Photostudio Ltd..On reaching the spot, it was found that

there was no electricity meter and the accused persons were

committing theft of electricity by directly tapping from the BSES

pole with the help of a wire i.e., two blue colour multi strand

copper wire of size 2.5 mm sq. which were further connected to

the connected load of the premises in question. PW1 further

deposed that the above said premises were being used by 1st and

2ndaccused at the time of inspection. The connected load of the

premises which was running through direct theft of electricity was

assessed and the total connected load was found to be

approximately 6.775 KW. The wires approximately 1 meter long

were removed and seized. PW1 deposed that the inspection report,

load report and seizure memo were prepared at the site which have

been marked as Ex.CW-2/A to Ex.CW-2/C. The videography of

the inspection and connected load of the premises was conducted

by Sh. Rahul Sharma/Videographer during the inspection. PW1

identified A1 in the video clipping contained in Ext. CW-2/D CD.

13. PW1, in his cross examination, admitted that the

number of jhuggi has not been mentioned in the documents

prepared by him or in the complaint. During the cross examination,

when the video was again played at the request of the defence

counsel, PW1 identified the person seen wearing red cloth in the

clipping as the 2ndaccused. PW1 denied the suggestion that the

premises in question belonged to 2nd accused and not to 1st accused

and that 1st accused was not concerned with the premises in

question in any manner and that he was residing at B-125 A,

Freedom Fighter Colony, New Delhi. PW1 also denied the

suggestion that 1st accused was not concerned with the use of

electricity at the premises. He denied the suggestion that 1st

accused was falsely implicated due to his mere presence at the

spot.

14. PW3, Lineman, when examined fully supported the

case of PW1.

15. PW4 deposed that assessment of theft bill was prepared

by him on the basis of the inspection report and load report marked

Ex/CW-2/A (colly) and Ex.CW-2/B provided by the complainant

office. The theft bill, marked as Ex.CW-2/E was also prepared by

him on the basis of the formula provided under the DERC

Regulations.

16. As per Section 135(1)(a) of the Act, if any person

dishonestly taps, makes or causes to be made any connection with

overhead, underground or under water lines or cables, or service

wires, or service facilities of a licensee or supplier, as the case may

be, so as to abstract or consume or use electricity, is liable to be

punished.

17. The Section does not say proof of ownership of the

premises is required or that it should be shown that the person

found using the electricity is the owner of the premises. Hence,

even if the A1 is not the owner of the premises, as contended by

him, he was found in the said jhuggi and in control thereof during

the time of inspection/raid, and hence can be held liable insofar as

he was the occupier and beneficiary of the dishonest abstraction

and use of electricity, thereby attracting liability under Section 135

of the Act. This fact stands duly proved by the documents prepared

contemporaneously, that is, Ext.CW2/A inspection

report,Ext.CW2/B load report,Ext.CW2/C seizure memo as well as

the videography conducted during the inspection. These

documents corroborate the testimonies of PW1 and PW3.

18. Further, the argument advanced by A1by placing

reliance upon his wife's Aadhaar card to contend that he is a

resident of the address mentioned therein cannot also be accepted

because the testimony of PW1 and PW3 corroborated with the

documents prepared contemporaneously proved that he was in the

possession and use of the premises at the relevant time. Moreover,

the Aadhaar card of his wife cannot, in any event, be relied upon

as substantive evidence to establish his residential address so as to

absolve him from such criminal liability.

19. With regard to the number of equipment and machinery

reported to be in use in the jhuggi, as given in Ext CW2/B load

report, which recorded four lamps/bulbs of 100 W each, three

CFLs of 15 W each, one geyser with I rod of 1500 W, two cooking

heaters of 2000 W each, three televisions of 110 W each, and one

small I rod of 500 W, with the total connected load at the time of

inspection approximately 6.775 kW, the learned counsel for the 1st

accused contended that such high usage is improbable given the

nature and size of the jhuggi. However, it is seen that such a

defence was never taken up by the 1st accused during the trial stage

and not even a single question or suggestion in this regard is seen

put to PW1, the manager, or PW3, the lineman, who were

members of the inspection team. Therefore, such a contention

cannot be raised at the appellate stage.

20. It is true that Section 135(3) of the Act mandates that

the list of items seized during an inspection or raid shall be

prepared and delivered to the occupant or person, who is required

to sign the same. However, PW1 and PW3 deposed that A1 had

refused to sign the documents. Moreover, A1 was identified by

PW1 and PW3 in their testimony while reviewing the videography.

Therefore, it cannot be contended that the A1 was not present

during the preparation of these inspection documents. In view of

the aforesaid discussion, this Court does not find any infirmity in

the reasoning of the trial court which would warrant interference

through this appeal proceeding.

21. The present appeal, sans merit is dismissed.

22. Application(s), if any, pending, shall stand closed.

CHANDRASEKHARAN SUDHA (JUDGE)

FEBRUARY 13, 2026/ABP

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter