Citation : 2024 Latest Caselaw 6774 Del
Judgement Date : 15 October, 2024
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Reserved on: 11th September, 2024
Decided on: 15th October, 2024
+ W.P.(C) 11422/2019, CM APPL. 46999/2019 & CM APPL.
46701/2019
SHRISHTI INFRASTRUCTURE DEVELOPMENT
CORPORATION LTD.
..... Petitioner
Through: Mr. Jayant Mehta, Senior
Advocate with Mr. Vijay K.
Singh, Mr. Kumar Shashwat
Singh and Mr. Ankur
Mishra, Advocates
V
AIRPORT AUTHORITY OF INDIA & OTHERS
..... Respondents
Through: Mr. Digvijay Rai, Advocate
with Mr. Archit Mishra and
Mr. Raghib Ali Khan,
Advocates for Airports
Authority of India/R-1
alongwith Mr. Kamal Kant
Soni, Officer of the Airports
Authority of India for R-1
CORAM
HON'BLE DR. JUSTICE SUDHIR KUMAR JAIN
JUDGMENT
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 1
1. The petitioner filed the present writ petition under Article 226 of
the Constitution of India for issuance of appropriate writ for quashing
the order vide reference no. CHQ File: AAI/20012/21/2011-ARI
(NOC); Case No. ER/241/2010; NOCAS ID:
KOLK/EAST/B/111912/017 dated 08.03.2019 (hereinafter referred
to as "the impugned order") whereby the respondent no.1/Airport
Authority of India (AAI) rejected the request of the petitioner for
Higher Top elevation of Tower-II.
2. The factual background of the case is that the petitioner has made
huge investment in a five star complex at Mouza Jatragachi, AA-
II/CBD/2, Action Area-II, New Town, Rajarhat (West Bengal),
District North 24, Parganas, State of West Bengal which is at a
distance of 7.06 kilometers from the Kolkata Airport. The complex
comprises of two Towers, i.e. Tower-I which includes commercial
and rental units and Tower- II, which is a building of serviced
apartments. Since the two Towers are close to the Kolkata Airport,
the petitioner has to obtain a no objection certificate (NOC) from the
respondent no.1/AAI under applicable law, i.e. the Aircraft Act, 1934
(hereinafter referred to as "the Act").
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 2
2.1 The petitioner applied for the NOC and the respondent no.1/AAI
in pursuance of Letter no. Ry/SC7/16-A/724 dated 13.02.2006 issued
the First NOC for the construction of Tower-II on 26.07.2006 which
was valid for a period of three years i.e. till 26.07.2009. Under this
NOC, a height of the structure 2.75 M (site elevation) plus (+)
141.78M height i.e. 144.53 Meters AMSL (above mean sea level)
was approved for both Tower-I and Tower-II, under then applicable
1988 Notification. The construction of Tower-II could not be
completed within the NOC period i.e. till 26.07.2009 and as such
applied for a revalidation/renewal of the First NOC in 2010, to
complete the construction of Tower-II. The respondent no.1/AAI
informed the petitioner on 13.12.2010 that its case was being
considered for a height of 88.64 Meters AMSL for Tower-II, subject
to the receipt of a revised and duly authenticated section plan.
2.2 The petitioner being aggrieved by the sudden reduction in the
Tower height made representations with the respondent no.1/AAI
seeking a reconsideration of the height of Tower-I to the original
allotted height of 144.53 Meters AMSL and a height of 133.321
Meters AMSL for Tower-II as the petitioner had made investments in
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 3
Tower-I and Tower-II on the basis of the approved plans under the
Original NOC dated 26.07.2006 and this sudden reduction in tower
height would severely jeopardize the commercial interests of the
petitioner and the financial investors.
2.3 The respondent no. 1/AAI on 13.06.2014 issued the Second NOC
under the now applicable 2010 Notification (superseding the earlier
1988 Notification and the interim 2008 Notification) which approved
the height for Tower-I upto 144.53 Meters AMSL and for Tower-II
for 90.30 Meters AMSL from the existing radar as on 13.06.2014
subject to increase upto 105.48 Meters AMSL after the
commissioning of the proposed Air Surveillance Radar (ASR) at the
Kolkata Airport. The petitioner being aggrieved by the Second NOC
dated 13.06.2014 which reduced the height of Tower-II to 90.30
Meters AMSL from the existing radar upto a maximum of 105.48
Meters AMSL subject to the commissioning of the proposed ASR
approached the respondent no.3 on 23.06.2014 protesting the
arbitrary reduction of the height of Tower-II and urging it to take into
account the fact that the petitioner's case pertained to
revalidation/renewal and not for an NOC to be issued de novo that
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 4
the construction had been undertaken only after the First NOC and
that both the Towers do not pose any restriction to the radar visibility
and are well within permissible height limits.
2.4 The respondent no.1/AAI on 03.07.2014 issued a Final NOC
based upon the approval of the respondent no. 3 which approved the
height of Tower-I upto 144.53 Meters AMSL and approved the
height of Tower-II upto 90.30 Meters AMSL from the existing radar.
The Final NOC also stated that an additional height of 15.18 Meters
AMSL for Tower-II may be permitted after commissioning of the
proposed ASR. The Final NOC was valid for a period of 5 years from
the date of issue i.e. till 03.07.2019. The petitioner appealed to the
respondent no.3 against the reduced height of Tower-II granted by
the respondent no.1/AAI in the Final NOC dated 03.07.2014. The
petitioner was given an opportunity of being heard on 24.06.2015 but
the respondent no.3 rejected the case of the petitioner by stating that
request of the petitioner that multi radar criteria should be applied,
cannot be considered since Kolkata Airport had a single radar. The
respondent no. 1/AAI wrote a letter dated 29.07.2015 to the petitioner
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 5
directing it to reduce the height of Tower-II to the approved height as
per the Final NOC dated 03.07.2014.
2.5 The petitioner being aggrieved by the Final NOC dated
03.07.2014, Order dated 24.06.2015 and the letter dated 29.07.2015
filed a Writ Petition bearing no. W.P.(C) 7652/2015 before this Court
on 11.08.2015. The Ministry of Civil Aviation (Height Restrictions
for Safeguarding Aircraft Operations) Rules, 2015 (hereinafter
referred to as "the 2015 Notification") were notified on 30.09.2015
during the pendency of the Writ Petition in supersession of the 2010
Notification. The "Note" under the 2015 Notification clarified that
large objects means those structures which either in isolation, or
collectively subtend the azimuth angle of 0.4 degree or above at the
radar antenna. The Note further specified that in a cluster of buildings
wherein the gap between the two adjacent buildings sub tends an
azimuth angle of less than 0.4 degree on the antenna pedestal, the
entire cluster is to be considered as one object.
2.6 The Writ petition bearing no. W.P.(C) 7652/2015 titled as
Shrishti Infrastructure Development Corporation Limited &
others V Union of India & others was dismissed vide order dated
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 6
25.04.2016. The petitioner filed a Letters Patent Appeal bearing LPA
no. 503/2016 on 24.05.2016 before this Court challenging the order
dated 25.04.2016 and prayed that the order dated 25.04.2016, the
Final NOC dated 03.07.2014, Order dated 24.06.2015 and the letter
dated 29.07.2015 be set aside. The petitioner during the pendency of
the LPA no 503/2016 wrote a letter bearing reference no.
Shristi/Hotel/AAI/17-18/785 dated 21.08.2017 to the respondent no.3
wherein it was stated that the petitioner's request for revalidation of
the Final NOC had been considered under the criteria for the 2010
Notification and that since the 2015 Notification had superseded the
2010 Notification, its case be reviewed applying the criteria under the
2015 Notification. It was also explained in the letter that under the
applicable criteria of the 2015 Notification, the petitioner's Tower-II
qualified under the height restriction imposed therein. The respondent
no.3 had agreed to re-examine the case of the petitioner according to
the criteria under the 2015 Notification and the petitioner was
informed vide an email dated 25.08.2017 in which top officials of the
respondent no.2 were also marked.
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 7
2.7 The respondent no. 1/AAI after receipt of one RTI application
dated 08.09.2017 from a third party to seek information about the
"Tilt angle" for all the ASR/ARSR/MSSR installed in airfields and
enroute, vide response dated 12.09.2017 confirmed that the tilt angle
of the MSSR at Kolkata was 2.5 degrees and said response was also
made available to the petitioner. The petitioner during the pendency
of the re-examination of its case hired Aero Survey Pvt. Ltd. and
obtained a site elevation and site coordinates certificate dated
16.01.2018. The petitioner wrote to the respondent no.1/AAI vide
letter dated 19.01.2018 and also appealed to the respondent no.3 vide
appeal dated 01.03.2018 for a review of its case under the 2015
Notification and requested for a height of 133.32 Meters AMSL for
Tower-II. The petitioner again vide its letter dated 22.06.2018
requested the respondent no.l/AAI to allow the height of 133.321
Meters AMSL for Tower-II by submitting the location map of the
buildings prescribing the coordinates of Tower-I and Tower-II along
with the survey document from Aero Survey Private Limited.
2.8 The respondent no.1/AAI vide email dated 10.10.2018 rejected
the request of the petitioner for proposed height of 133.32 meters
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 8
AMSL for Tower-II. The petitioner being aggrieved by the email
dated 10.10.2018 wrote to the respondent no. 2 and again requested
that its case be reconsidered and the calculation of the permissible
height based on the actual tilt angle of the radar at Kolkata be
calculated at 2.5 degrees and not 0.67 degrees as erroneously adopted
by the respondent no.1/AAI. The petitioner also wrote a second letter
dated 26.10.2018 to the respondent no.1/AAI informing about
petitioner's meeting with the Secretary of the respondent no. 2 on
24.10.2018 wherein the petitioner had explained its entire case to the
Secretary of the respondent no.2 and requested them to re-examine
case of the petitioner and that the respondent no.2 had assured the
petitioner that its case would definitely be re-examined.
2.9 The respondent no.1/AAI vide email dated 30.10.2018 informed
to the petitioner that in order to examine its appeal application, a
team of officials of the respondent no.1/AAI including a surveyor
from CHQ would be visiting the site of Tower-I and Tower-II for a
joint site verification. Accordingly, on 01.11.2018, a team led by Jt.
GM (CNS) of the respondent no.l/AAI visited the site of the
petitioner and surveyed the site and captured the site coordinates. A
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 9
joint verification of the coordinates noted during the site visit was
issued and signed by the representatives of both the petitioner and the
respondent no.l/AAI. The petitioner after the site visit conducted on
01.11.2018 availed the services of a third party independent expert
i.e. Sakthi Aviation for the purposes of carrying out a
Communication Navigation and Surveillance (CNS) Analysis of the
heights of Tower-I and Tower-II as per the criteria contained in the
2015 Notification. The Sakthi Aviation report dated 10.12.2018,
while determining that both the towers satisfied the criteria provided
under the 2015 Notification and did not interfere with the air traffic
control or CNS, therefore recommended a radar simulation of the site
to be carried out.
2.10 The respondent no.1/AAI did not provide a copy of its
analysis/report/findings about the data collected at the site visit on
01.11.2018 to the petitioner. Hence, the petitioner wrote a letter dated
23.01.2019 to the respondent no.3 requesting it to direct the
respondent no.1/AAI to submit the report prepared by them after the
site visit on 01.11.2018 and also requested to carry out radar
stimulation study by any independent agency to ascertain the
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 10
permissible height of the Tower-II. The report of the respondent no.1
was still not given to the petitioner. The respondent no.1 responded to
the petitioner's appeal and numerous representations vide email dated
08.03.2019 i.e. the impugned order by stating that Tower-II does not
qualify for higher height as along with Tower-I, it becomes a large
structure and accordingly restricted the height of Tower-II to the
earlier top elevation granted i.e. 105.48 meters AMSL.
2.11 The petitioner being aggrieved by the impugned order dated
08.03.2019 wrote a letter dated 22.04.2019 whereby requested the
respondent no.2 to allow it to conduct an independent study of its
case and re-examine the same through a radar simulation study to
demonstrate to the respondent no.1/AAI that its towers qualified the
applicable height restrictions under the applicable 2015 Notification.
The petitioner received no response to its abovementioned letter. The
respondent no.1/AAI responded vide email dated 18.07.2019 to
Mr.Ambrish Parekh's RTI Application seeking a list of
buildings/structures in and around the Kolkata airport which form an
obstruction with respect to the ASR/MSSR at Kolkata airport and
confirmed that there was no recorded information with respect to the
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 11
query raised. This information had been provided to the petitioner
from Mr. Ambrish Parekh. Mr. Ambrish Parekh on 07.08.2019 filed
another RTI application seeking information with respect to Tower-I
and Tower-II regarding inter alia the calculation method employed in
determining height restriction; noting sheets of decisions; the method
of calculating azimuth angle 0.4 degrees; and information about
radars.
2.12 The petitioner during the proceedings in the LPA no 985/2013
vide CM APPL. 22134/2019 prayed before this Court to direct the
respondent no.1/AAI to provide the petitioner with a copy of the
Report prepared pursuant to the site visit on 01.11.2018 and to further
allow it to conduct a radar simulation study. The application was
dismissed vide order dated 02.07.2019 but a copy of the Report
prepared by the respondent no.l/AAI post the site visit on 01.11.2018
was directed to be provided to the petitioner within a week and no
directions for a radar simulation study to be carried out by an
independent third party was given. The respondent no.l/AAI provided
a copy of the Report to the petitioner in compliance of the order of
this Court dated 02.07.2019.
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 12
2.13 The respondent no.1/AAI responded to the 2nd RTI application
of Mr. Parekh dated 07.08.2019 vide response dated 02.09.2019
wherein notings were made by various senior officials of the
respondent no.1/AAI based upon the coordinates and the information
collected during the site visit on 01.11.2018. The file noting by Mr.
Sanjeev Shah, Joint GM of the respondent no.1/AAI stated that the
methodology adopted to arrive at a conclusion that the two towers
formed a cluster subtending an angle of more than 0.4 degrees and
therefore forming a large object, was based on "crude method and
without any mathematical solution or computer simulated modelling
available at present". This noting was absent in the Report provided
to the petitioner in compliance of the order of this Court dated
02.07.2019.
2.14 The petitioner brought the aforementioned information and the
discrepancies in the Report to the knowledge of this Court during the
proceedings in the LPA no 985/2013 and submitted that in light of
new facts i.e. since the 2015 Notification is now applicable, the
existence of two radars and the admission of the respondent no.l/AAI
that a crude methodology was applied to assess its case, sought leave
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 13
of this Court to withdraw the LPA no 985/2013 with liberty to assail
the impugned order in a fresh action and leave was accordingly
granted vide order dated 24.09.2019. The petitioner has filed the
present petition with the prayer which is produced verbatim as
under:-
(a) Issue an appropriate writ, order or direction setting aside the Impugned Order dated March 08, 2019, passed by the Respondent No. 1/Airport Authority of India;
(b) Issue an appropriate writ, order or direction to the Respondents restraining them from any coercive action towards Tower-I and Tower-II, specifically the demolition of Tower-II to reduce the structure from its current height of 133.32 Meters. AMSL; and
(c) Pass any such other order(s) which this Hon'ble Court may deem fit and proper in the facts and circumstances of the present case.
3. The respondent no. 1 filed counter-affidavit wherein stated that the
height granted to the petitioner for Tower-II (up to a height of 105.48
Meters AMSL) was affirmed by the impugned order dated
08.03.2019 after a joint survey and based on the latest Notification
dated 30.09.2015 being published vide G.S.R. 751 (E). The
impugned order is based on a scientific method adopted by the
respondent i.e. the NOCAS system which is computerized and in
conformity with the principles of natural justice and equity and
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 14
cannot be said to be unreasonable and arbitrary. The respondent
agreed to re-examine the petitioner's case even after a decision by the
Appellate Committee and even in the process of re-evaluation, the
height granted to the petitioner vide NOC dated 03.07.2014 did not
qualify for a higher height. The expression "crude analysis" refers
only to the pictorial diagram drawn manually for explanation
purpose. The bare perusal of the Report dated 18.07.2019 reflects that
as far as large/small angle calculation or gap angle calculations are
concerned, these are accurate and without any ambiguity as they are
based on bearing information obtained automatically using a
scientific tool known as "No Objection Certificate Application
System" (NOCAS). The co-ordinates provided by the petitioner
were entered in the NOCAS System and thereafter based on the
readings on the NOCAS System, calculations were carried out as per
which Tower-I and Tower-II as a whole cluster subtends an angle
more than 0.4 degree on ASR/MSSR Kolkata and MSSR Kolkata.
3.1 The multi radar as per para 2.5.2 of G.S.R. 751 (E) refers to more
than one ASR (Airport Surveillance Radar). At present, Kolkata
Airport is being served with only one ASR collocated with MSSR.
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 15
The other Radar at Kolkata is an MSSR being used as Air Route
Surveillance Rader (ARSR) which is defined under clause 2.6.1 and
2.6 of G.S.R. 751 (E) and hence, Kolkata Airport does not qualify as
Multi Radar criteria. The Delhi and Mumbai Airports only qualify as
multi radar Airports.
3.2 There is no building around Tower-II except for Tower-I which
forms a cluster together with Tower-II as per the Site Visit dated
01.11.2018 and the Report dated 18.07.2019. The large/small
structure and gap analysis between Tower-I and Tower-II is done in
accordance with the provisions of G.S.R. 751 (E) which shows that
Tower-I and Tower-II together form a cluster of more than 0.4 degree
and hence form a large structure. The Report of M/s Sakthi Aviation
is incorrect as the site co-ordinates for calculating gap angle has been
selected as per their own convenience whereas the correct method
has been elaborated in the Report dated 18.07.2019. Only the
designated officer as per Clause 5 is empowered to issue NOC on
behalf of the Central Government in respect of civil aerodrome.
3.3 The respondent no.1/AAI issued NOC dated 19/26.07.2006
granting approval to the petitioner to construct upto a height not
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 16
exceeding 144.53 meters AMSL and the said NOC was valid for a
period of three years from the date of issue. The petitioner could not
complete the construction within the period of three years and
applied for renewal of the NOC. The respondent no.1/AAI vide its
communication dated 13.12.2010 informed the petitioner that the
case of the petitioner could be considered for NOC upto a maximum
height of 88.64 meters AMSL on receipt of required revised sanction
plan duly authenticated and asked the petitioner to submit a revised
undertaking and revised sanction plan for a restricted height of upto
88.64 meters AMSL. The petitioner appealed to the respondent
no.3/Appellate Committee and the respondent no.1/AAI vide its letter
dated 05.07.2012 informed the petitioner that the appeal of the
petitioner will be considered by the Grievance Redressal Committee
of the respondent no.2/Ministry of Civil Aviation and also asked the
petitioner to apply online for NOC. The respondent no.1/AAI vide
letter dated 13.06.2014 to the Regional Executive Director, Eastern
Region of AAI and with copy to the petitioner authorised the
Regional Executive Director, Eastern Region of AAI to issue revised
height clearance to the petitioner with respect to Tower-I of 144.53
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 17
meters AMSL and with respect to Tower-II of 105.48 meters AMSL
on compliance of certain other conditions by the petitioner. The
petitioner again appealed to the respondent no.3/Appellate
Committee. The respondent no.1/AAI in the interregnum issued NOC
to the petitioner permitting the height of Tower-I upto 144.53 meters
AMSL i.e. for the same height for which NOC was earlier issued on
26.07.2006 but restricted the height for Tower-II upto 105.48 meters
AMSL as against the height of 144.53 meters AMSL for which NOC
was issued on 26.07.2006. The respondent no.3/Appellate Committee
after giving opportunity of being heard to the petitioner on
21.01.2015 and 24.06.2015 considered the appeal of the petitioner
and observed as under:-
i. The site of the petitioner lies in Outer Conical Surface and is at a distance of 6307 meters from Kolkata Airport runway;
ii. The petitioner had initially requested a height of 144.53 meters AMSL and against which they were granted an NOC dated 26th July, 2006 for a height of 144.53 meters AMSL with a three years validity;
iii. The petitioner on 27th August, 2010 i.e. after the expiry of the NOC asked for revalidation;
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 18
iv. The provision of revalidation of NOC as per the Rules is applicable in those cases which were received for revalidation within the validity period;
v. The case of the petitioner was re-examined and NOC for the permissible height of 88.64 meters AMSL was issued;
vi. The change in height from the earlier NOC dated26th July, 2006 was due to the revised norms which were notified in January, 2010;
vii. The matter was examined on representations / appeal of the petitioner with respect to CNS (Communication Navigation and Surveillance) criteria and it was observed that individually "both the objects (i.e. towers) are small but collectively become large object and should not be considered for higher height than permissible from ASR (Air Surveillance Radar);
viii. The respondent no.3/ Appellate Committee in meeting held on 7th March, 2014 decided that re-examination of the case from CNS criteria for Tower-2 for the requested height of 133.321 meters AMSL taking into consideration the new radar at Kolkata Airport be carried out by the respondent No.1/ AAI and issue permission for the admissible height from new radar for Tower-2 and 144.53 meters AMSL for Tower-1;
ix. The authorisation after re-examination was given vide letter dated 13.06. 2014 for the permissible height of Tower
-1 of 144.53 meters AMSL and of Tower-2 for 90.30meters AMSL from existing radar and 105.48 meters AMSL after proposed ASR is commissioned;
x.The petitioner continued to represent and cited relaxations due to second radar granted to number of structures in Mumbai;
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 19
xi. The petitioner during the hearing on 21.01 2015 had revealed that they had constructed Tower-2 beyond the permissible height of 105.48 meters AMSL after expiry of their NOC and thereafter an enquiry was ordered into, how such construction was permitted after the expiry of the validity of the earlier NOC;
xii. The request of the petitioner for application of multi radar criteria was considered but not found tenable as Kolkata has only one single ASR and that the benefits accruing from the present positioning of the existing radar had been applied in the CNS examination;
xiii. Accordingly, directions were issued for demolition of the excess height of Tower-2 as per the Aircraft Rules.
3.4 The writ petition bearing W.P.(C) no. 7652/2015 filed by the
petitioner was dismissed by this Court vide judgment dated
25.04.2016 and it was held that the petitioner had no reason to go
ahead with the construction beyond the height of 88.64 meters AMSL
which was communicated to them by the respondent no.1/AAI vide
communication dated 13.12.2010 and that the order of the respondent
no.3/Appellate Committee dated 24.06.2015 is unambiguous, lucid
and well-considered and does not show any need for any third party
opinion. The petitioner challenged the judgment dated 25.04.2016 by
way of LPA no. 503/2016 which was withdrawn on the ground that
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 20
certain fresh facts have emerged that are required to assail the
impugned order dated 08.03.2019.
3.5 Section 9A of the Act empowers the Central Government to
direct that no building or structure shall be constructed or erected on
any land within such radius, not exceeding 20 Kilometers from the
Aerodrome Reference Point, as may be specified in the Notification
and/or to direct that no building or structure higher than such height
as may be specified in the notification shall be constructed or erected
on such land. The respondent is only concerned with the safety of
Aircraft Operations and not the commercial interests of the petitioner.
3.6 The petitioner was granted initial NOC in July, 2006 was as per
notification bearing no. S.O.988 and NOC dated 03.07.2014 was
based on notification dated 14.01.2010 bearing no. S.O. 84 (E). The
impugned order dated 08.03.2019 was based on the latest notification
dated 30.09.2015 i.e. GSR 751 (E). The petitioner allowed the initial
NOC dated 26.07.2006 to lapse and the provision of revalidation of
NOC as per Rules was applicable in those cases only which were
received for revalidation within their validity period. The letter dated
13.06.2014 issued by the respondent no 1/AAI is not a NOC but an
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 21
authorization letter issued by the Corporate Headquarter of the
respondent no1/AAI to direct the Regional Office at Kolkata to issue
the revised NOC as per the authorization letter.
3.7 The ASR calculations for height restrictions is not based on Tilt
Angle but is based on Minimum Sector Altitude (MSA) and Pedestal
height of Antenna, as per para 2.5.1.1 of GSR 751 (E). Hence, the
assumption of the petitioner to examine the height restrictions based
on Tilt Angle is totally incorrect. The petitioner during the pendency
of LPA no. 503/2016 formally requested for a review vide letter
dated 01.03.2018 with respect to GSR 751 (E), Section 2.5 and sub-
section 2.5.1. The petitioner was informed vide e-mail dated
07.06.2018 that the location map submitted by the petitioner did not
cover the entire building, the curved portions were not fully covered
within the location coordinates and therefore was requested to submit
fresh location map prescribing the co-ordinates of entire Tower-I and
Tower-II building. The petitioner replied vide letter dated
22.06.2018. The petitioner's case was re-examined as per its request
based on GSR 751 (E) and the petitioner was duly informed of the
outcome of the re-examination vide e-mail dated 10.10.2018 which
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 22
stated that under the applicable criteria of the 2015 Notification, the
petitioner's Tower-II does not qualify for a higher height.
3.8 The Tilt Angle is not the criteria for height restriction from
Airport Surveillance Radar. The calculations for height restrictions in
case of ASR Kolkata is based on Minimum Sector Altitude (MSA)
and Pedestal height of Antenna as per para 2.5.1.1 of GSR 751 (E).
M/s Sakthi Aviation selected the site coordinates for calculating gap
angle as per its own convenience whereas the correct method has
been elaborated in the Report provided to the petitioner vide letter
dated 18.07.2019 and M/s Sakthi Aviation has tried to give various
reasons suiting the requirement of the petitioner whereas the case is
dealt as per the provision contained in GSR 751 (E). It is also
submitted that with regard to the quote given by M/s Sakthi Aviation
that the gap angle calculation is not possible from space and there is
no requirement to measure gap angle from space as angle calculation
can be easily done mathematically based on coordinates of Radar
along with co-ordinates of Tower-I and Tower-II and the "Bearing
Direction" can be calculated in degree with respect to each of site co-
ordinates when seen from Radar site. The co-ordinates were recorded
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 23
in the presence of the representative of the petitioner on 01.11.2018
and once the site co-ordinates are entered in the NOCAS application
system, the "Bearing" information is automatically provided in the
NOCAS Height Sheet from which various angles can be found and
the result can be finalized.
3.9 The site elevation is the elevation of the highest point on the
proposed site/plot and the site elevation of 2.75 meters AMSL as
provided by the petitioner shall be the elevation of the highest point
on the plot whereas site, elevation of 1.492 meters AMSL cited in the
report is elevation of a random point on the plot/site. The report was
based on the file of Site Survey/file noting/calculations carried out
based on site survey by various sections/Departments and it was
compiled for submission as a formal report. The report provided is a
single report only with 04 numbers of enclosures. The report derived
data from the enclosures and thus few facts may appear to be
duplicate. The report is neither incomplete nor tampered with and
hence, there is no misconduct on the part of the respondent.
3.10 The "crude method" refers to the hand drawn pictorial
diagrams. The angle calculation is purely scientific and correct and
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 24
the result based on scientific procedures will always remain the same
irrespective of the person handling the case. The hand drawn pictorial
diagrams which are for explanatory purposes may differ and hence
are termed as crude.
3.11 The petitioner in compliance to the order passed by this Court in
Appeal was given a report explaining the procedure, containing the
method of calculations of small/ large object along with NOCAS
height sheets and pictorial representation. The petitioner has a
misconception that the Multi Radar criteria is applicable at Kolkata
Airport and that there is only one ASR (Airport Surveillance Radar)
which is co-located with MSSR at Kolkata Airport, hence multi radar
criteria as per GSR 751 (E) is not applicable. The other Radar is
MSSR which is an Air Route Surveillance Radar (ARSR) and cannot
be considered for Multi Radar criteria. Para 2.5 of GSR-751 (E)
applies to ASR (Airport Surveillance Radar) and para 2.6 applies for
ARSR.
3.12 The Officers dealing with the case of the petitioner are experts
in relevant areas and are bound by the Rules, Regulations and
provisions for height restrictions as are clearly mentioned in GSR
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 25
751 (E). The present case is also dealt with as per GSR 751 (E) using
scientific tools and mathematical calculations. The clause 2.5.2.2 of
GSR 751 (E) as quoted by M/s Sakthi Aviation is not applicable in
this case as Kolkata Airport has only one Airport Surveillance Radar
(ASR). The angle calculations are based on scientific methods and
hence the results arrived at are accurate. The petitioner vide e-mail
dated 08.03.2019 was communicated the decision of the respondent
after a joint survey and detailed consideration of the petitioner's case
along with documents relied upon and hence does not require any
detailed reasoning being technical in nature. The Kolkata Airport
does not qualify as a multi radar airport as it has only one
ASR/MSSR being used as ASR and one MSSR, being used as ARSR
and hence, the 2015 Notification has rightly been applied in the case
of the petitioner. It was prayed that the petition be dismissed.
4. The petitioner filed a rejoinder to the counter affidavit filed in
response to petition wherein reiterated the facts stated in the petition
and denied the averments made by the respondent no.1 in its counter
affidavit. It was prayed that the petitioner be granted relief as prayed
for.
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 26
5. Mr. Jayant Mehta, learned Senior Counsel advanced oral
arguments on behalf of the petitioner and written submissions are
also filed on behalf of the petitioner. Sh. Mehta narrated the factual
position that the petitioner is seeking to set aside and/or quash the
impugned order dated 08.03.2019 passed by the respondent no.1/AAI
whereby the respondent no.1/AAI had restricted the maximum
permissible height of Tower-II of the site complex of the petitioner to
105.58 meters as per No Objection Certificate dated 03.07.2014 from
the originally granted height of 144.53 Meters AMSL granted under
No-Objection Certificate dated 26.07.2006. Sh. Mehta further stated
that the petitioner had constructed a complex comprising of Tower-I
and Tower-II at Mouza Jatragachi, AA-II/CBD/2, Action Area-II,
New Town, Rajarhat (West Bengal), District North 24, Parganas,
State of West Bengal which is situated at a distance of 7.06
Kilometres from NSCB International Airport, Kolkata. The complex
comprises of two Towers, i.e. Tower-I which includes commercial
and rental units and Tower-II which is a building of serviced
apartments. The petitioner had sought permission for height clearance
from the respondent no.1/AAI vide application dated 13.02.2006
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 27
under Section 9A of the Act 1934 for the construction of Tower-I and
Tower-II of the site complex. The respondent no.1/AAI had on
26.07.2006 issued a NOC dated 26.07.2006 which was valid for a
period of three years and approved height of 144.53 Meters AMSL
for Tower-I and Tower-II of the site complex. The petitioner had
made investments on the basis of the approved plans under the
original NOC dated 26.07.2006. The petitioner had applied for
revalidation of First NOC on 27.08.2010 but the respondent
no.1/AAI vide letters dated 13.12.2010 and 03.07.2014 had approved
the height of the Tower-I up to 144.53 Meters AMSL and approved
the height of Tower-II up to 90.30 Meters AMSL from the existing
radar. The height of Tower-II was to be increased up to only 105.48
Meters AMSL after proposed ASR had been commissioned. The
petitioner has filed a Writ Petition bearing no. 7652/2015 to
challenge the order dated 24.06.2015, NOC dated 03.07.2014 and
Letter dated 29.07.2015 issued by the respondent no.1/AAI which
was dismissed vide order dated 25.04.2016 passed by the learned
Single Judge of this Court. The petitioner filed appeal vide LPA no.
503/2016 which was allowed to be dismissed as withdrawn vide the
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 28
order dated 24.09.2019 without expressing any view on the merits or
the pleas taken by the appellants i.e. the petitioner.
5.1 The respondent no.2/the Ministry of Civil Aviation during the
pendency of the Writ Petition on 30.09.2015 again notified new
General Statutory Rules (G.S.R.) No. 751 (E), 2015 on height
restrictions for safeguarding of aircraft operations under the
applicable provisions of the Act. The petitioner vide letter dated
21.08.2017 approached the respondent no.1/AAI to consider its case
for revalidation under the 2015 Notification which was issued in
supersession of the 2010 Notification. The respondent no.3 agreed to
re-examine the case of the petitioner as per the criteria under the
2015 Notification. The respondent no.3 vide letter dated 25.08.2017
informed the petitioner that the respondent no.3 had decided to re-
evaluate and re-examine the case of the petitioner as per the criteria
under the 2015 Notification. The respondent no.1 despite multiple
rounds of representations and requests made by the petitioner had
vide impugned Order dated 08.03.2019 restricted the maximum
permissible height of Tower-II of site complex of the petitioner to
105.58 meters as per No Objection Certificate dated 03.07.2014.
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 29
5.2 Sh. Mehta assailed validity of the impugned order dated
08.03.2019 by arguing that the respondent no.1/AAI has failed to
provide any reason while passing the impugned order dated
08.03.2019 which is discriminatory and arbitrary. The impugned
order dated 08.03.2019 issued by the respondent no.l/AAI did not
give any reason in its support. Sh. Mehta referred the impugned order
dated 08.03.2019 which simply stated that "On examination, it was
concluded that the Tower-II does not qualify for higher height, as
along with Tower-I it becomes a large structure". The respondent
no.1/AAI being a public authority was legally bound to record valid
and cogent reasons explaining the decision arrived at in the impugned
order dated 08.03.2019 and Sh. Mehta referred Kranti Associates
Pvt. Ltd & another V Masood Ahmed Khan & others, (2010) 9
SCC 496 and Punjab State Electricity Board & others V Jit
Singh, (2009) 13 SCC 118. He also argued that the exercise of
discretion in discharge of statutory duties must involve application of
mind and must consider all the matter that are required for
consideration and the decision by the statutory authority must be non-
arbitrary and due consideration be given to the reasonable or
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 30
legitimate expectation of the person affected by the decision and
Rameshwar Prasad and others V Union of India, AIR 2006 SC
980 and Food Corporation of India V Kamdhenu Cattle Feed
Industries, (1993) 1 SCC 71 were referred.
5.3 Sh. Mehta further argued that the examination of case of the
petitioner for height restriction vide the impugned order dated
08.03.2019 was based on "crude method" and without any
mathematical solution or computer simulated modelling. The
respondent no.1/AAI has concealed file noting which reflected use of
"crude method without any mathematical solution or computer
simulated modelling". He stated that Site Visit Report prepared by
the respondent no.1/AAI contained a file noting which reflects that
methodology adopted to arrive at a conclusion that the two towers
formed a cluster subtending an angle of more than 0.4 degrees and
therefore forming a large object was based on "crude method and
without any mathematical solution or computer simulated
modelling". The respondent no 1 made available complete Site Visit
Report including file noting to the petitioner in response to RTI
Application 02.09.2019. The specific noting from Mr. Sanjeev Shah,
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 31
Joint GM of the respondentno.1/AAI was missing in the Site Visit
Report shared by the respondent no.1/AAI pursuant to order dated
02.07.2019 passed by this Court and the said file noting culminated
in the impugned order dated08.03.2019. The respondent no.1/AAI
being a statutory authority was bound to make a complete and fair
disclosure of facts and reliance was placed on Sarvjit Singh V
NDMC & others, ILR (2008) II Delhi 212. Sh. Mehta also countered
the argument advanced by Sh. Digvijay Rai, the learned counsel for
the respondent no.1/AAI that the expression "crude analysis" refers
only to the pictorial diagram drawn manually for explanation purpose
as the same is not drawn to scale. Sh. Mehta further argued that Site
Visit Report of the respondent no.1/AAI itself notes that the Tower-II
when assessed in isolation is classified as a 'small structure' and
admittedly is not "Large object" as defined in Clause 2.5.1.1 of the
2015 Notification as the angle formed by the Tower-II when seen
from the ASR/MSSR radar is 0.25 Degree and the angle formed by
the Tower-II when seen from MSSR (ARSR) is 0.19 degree which is
less than 0.4 Degree. Sh. Mehta after relying on file noting
empathetically argued that it is evident from the contents of the file
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 32
noting that the calculation of Gap Angle analysis i.e. determination of
whether two structures subtend an azimuth angle of less than 0.4
degrees was undertaken via "crude method without mathematical
solution or computer simulated modelling". Sh. Mehta further
highlighted that the respondent no.1/AAI has wrongly assessed the
permissible height without considering the tilt angle which has been
obtained by the petitioner in RTI reply dated 12.09.2017 and the
respondent no.1/AAI in counter affidavit stated that ASR calculations
for height restriction are not based on Tilt Angle. The calibrated tilt
angle of the Badu Radar as per the calculation sheet of the respondent
no. 1 was 3.00 degree because NOCAS was not updated as on date to
determine the gap angle. Sh. Mehta in light of these submissions
argued that the observations made by the respondent no.1/AAI in
impugned order dated 08.03.2019 that the two Towers form a cluster
was not undertaken in accordance with any scientific or mathematical
process rather the impugned order dated 08.03.2019 has admittedly
relied upon "crude method with any mathematical solution" to reject
the request of the petitioner for permissible height.
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 33
5.4 Sh. Mehta also argued that the respondent no.1/AAI has wrongly
stated that gap between Tower-I and Tower-II was calculated by
NOCAS application and during argument it was wrongly stated that
the calculation of the permissible height was carried out based on
NOCAS system. The respondent no.1/AAI in a tender dated
28.10.2020 admitted that the facility to calculate the angle between
two structures for examination of small/large/cluster forming purpose
is not available in NOCAS system and when applicant applies for
two or more structures within his plot then Gap Angle Analysis is
done manually. Sh. Mehta referred Report dated 10.12.2018 prepared
by Sakthi Aviation, a third-Party Independent expert in aviation
wherein highlighted that there was no measurement technique or
application available to measure the gap between towers from space
with respect to radar. Sakthi Aviation Report after considering
different combination of coordinates found that the gap between
Tower-I and Tower-II is more than 0.4 degree and building width
facing ASR/MSSR is 0.3595 and 0.2525 respectively and concluded
that Tower-I and Tower-II did not form a cluster as per Clause
2.5.2.2 sub clause IV of the 2015 Notification. Sh. Mehta ultimately
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 34
argued that observations made by the respondent no.1/AAI in the
impugned order dated 08.03.2019 that two towers form a cluster was
not undertaken in accordance with any scientific or mathematical
process rather the impugned order dated08.03.2019 has relied upon
"crude method without any mathematical solution" to reject request
of the petitioner for permissible height.
5.5 Sh. Mehta also argued that the case of the petitioner must be
assessed by criterion of multi-radar. Sh. Mehta after referring Site
Visit Report stated that it is evident from Report that there were more
than one radar at Kolkata airport at the time of assessing the height of
Tower-I and Tower-II on 01.11.2018. The second radar is installed at
Badu and Kolkata Airport is responsible to safeguard the radar
installed at Badu and second radar installed at Badu is "MSSR" radar
which can operate as ASR and/or ARSR based on operational usage.
Accordingly, the case of the petitioner be assessed on the basis of the
2015 Notification criteria with the confirmed presence of two radars.
The petitioner is entitled to the benefits of Multiple Radar Criterion
as provided for in Clause 2.5.2 of the 2015 Notification. Sh. Mehta
concluded by stating that the petitioner is committed to safety and
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 35
security of air-traffic arising to and from Kolkata Airport and the
petitioner is merely seeking relief against the arbitrary impugned
order dated 08.03.2019 passed by the respondent no. 1. The petitioner
is also ready to participate in the cost of the installation of any more
additional radar/equipment at Kolkata Airport which may be required
apart from the two radars existing. It is argued that the present
petition be allowed.
6. Sh. Digvijay Rai, the learned counsel for the respondentno.1/AAI
advanced oral arguments and written submissions were also
submitted on behalf of the respondent no.1/AAI. Sh. Rai stated that
this Court cannot sit as an appellate court against the decision taken
by an expert body due to lack of technical expertise and decision be
left for decision of those who are qualified to address the issues. The
petitioner is seeking to set aside the impugned order dated
08.03.2019 passed by the respondent no.1/AAI whereby the
petitioner was intimated Tower-II constructed by the petitioner does
not qualify for higher height as it with Tower-1 forms a large object.
The respondent no.1/AAI issued NOC dated 19/26.07.2006 to the
petitioner whereby granting no objection to construct a Tower upto a
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 36
height not exceeding 144.53 meters AMSL which was valid for three
years as per the prevalent rules. It was provided that if the
construction is not completed within the stipulated time then fresh
NOC would have to be taken by the petitioner. The petitioner
commenced construction after November, 2008 and was not
completed within three years. The petitioner on 27.08.2010 applied to
the respondent no.1/AAI for revalidation /renewal of the NOC but the
respondent no.1vide communication dated 13.12.2010 informed the
petitioner that the petitioner is only entitled upto maximum height of
88.64 meters AMSL for Tower-II on receipt Sanction Plan. The
petitioner preferred an appeal to the respondent no.3. The
respondentno.1/AAI during pendency of Appeal vide letter dated
05.07.2012 informed the petitioner that its Appeal would be
considered by the Grievance Redressal Committee of the respondent
no.2 and the petitioner asked to apply online for NOC. The
respondent no.1/AAI vide letter dated 13.06.2014 addressed to the
RED, Eastern Region authorised the said officer to issue revised
height clearance to the petitioner with respect to Tower-I for 144.53
meters and with respect to Tower-II for 105.48 meters AMSL on
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 37
compliance of certain conditions by the petitioner. The Petitioner
again appealed to respondent no.3 and the respondent no 1 in the
interregnum on 03.07.2014 issued NOC for Tower-1 upto 144.53
meters AMSL i.e. for the same height for which NOC was earlier
issued 26.07.2006 but the height of 105.48 meters was given in NOC
for Tower-II subject to operation of new radar. The respondent no 3
after hearing the petitioner observed in the meeting held on
24.06.2015 that the matter was examined with respect to CNS
(Communication Navigation and Surveillance) criteria and
individually "both the object (i.e. towers) are small but
collectively become large object and should not be considered for
higher height than permissible from ASR (Air Surveillance
Radar)". The petitioner had also revealed that the Tower-II has been
constructed beyond the permissible height of 105.48 meters for
which an enquiry was ordered. The request of the petitioner for
application of multi radar criteria was considered but was not found
tenable as Kolkata only has one single ASR Radar and accordingly
directions were issued for demolition of the excess height of the
Tower-II as per the Aircraft Rules.
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 38
6.1 Sh. Rai further stated that the petitioner filed a W.P.(C) no.
7652/2015 which was dismissed vide judgment dated 25.04.2016
passed by this Court by observing that there was no arbitrariness in
any action taken by the respondent no.1/AAI and the NOC
admittedly was not forever and it was further observed that a fresh
NOC would have to be obtained after expiry of validity. The Hon'ble
Court further held that the case of the petitioner was considered fairly
and permissible height was granted to the petitioner. The petitioner
filed LPA bearing no.503/2016 which was withdrawn on the ground
that additional information came in knowledge of the petitioner and
as such findings of the learned Single Judge vide judgment dated
25.04.2016 remain conclusive. The respondent no.1/AAI is only
concerned with the safety of Aircraft Operations and not the
commercial interests of the petitioner and the initial NOC granted to
the petitioner in July, 2006 was as per notification bearing no.
S.O.988 and the NOC dated 03.07.2014 was based on notification
dated 14.01.2010 bearing no. S.O.84 (E).
6.2 Sh. Rai further stated and argued that the petitioner has
challenged the impugned order dated 08.03.2019 on basis of
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 39
notification dated 30.09.2015 i.e. GSR 751 (E). It is further stated
that both S.O. 84(E) and GSR 751 (E) contained a stipulation
regarding "Large object" i.e. the structure/s in isolation or
collectively subtending azimuth angle of 0.4 degree or above at
Radar antenna. The entire cluster should be considered as one object
in case of cluster of buildings wherein the gap between the two
adjacent buildings subtends an azimuth angle of less than 0.4 degree
on the antenna pedestal and Tilt Angle is not the criteria for height
'restriction from Airport Surveillance Radar. Sh. Rai also stated that
in case of ASR Kolkata, calculation for height restrictions is based on
Minimum Sector Altitude (MSA) and Pedestal height of Antenna as
per para 2.5.1.1 of GSR 751 (E) and as such no benefit can be
granted to the petitioner and the height of 105.48 meters is final and
beyond which no construction is permissible.
6.3 Sh. Rai further referred Sakhti Aviation Report relied on by the
petitioner and argued that said Report is also incorrect as M/s. Sakhti
selected the site co-ordinates for calculating gap angle as per its own
convenience, whereas the correct method has been elaborated in the
Report provided to the petitioner vide letter dated 18.07.2019 and
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 40
M/s Sakhti failed to consider the case as per GSR 751 (E). M/s Sakhti
Aviation in report stated that gap angle calculation is not possible
from space but there is no need to measure gap angle from space as
angle calculation can be easily done mathematically based on
coordinates of Radar along with the co-ordinates of Tower-I and
Tower-II. It was further highlighted that once the site co-ordinates are
entered in the NOCAS application system, the "Bearing" information
is automatically provided in the NOCAS Height Sheet and report of
Sakhti Aviation is not binding on the respondent no.1/AAI as per the
existing rules.
6.4 Sh. Rai further argued that the petitioner strongly relies upon the
site visit report and the internal noting of the respondent no.1/AAI.
Sh. Rai stated that the petitioner had changed the site co-ordinate data
multiple times which made it necessary for the respondent no.1/AAI
to physically verify the site and obtain actual site co-ordinate of the
buildings i.e. Tower-I and Tower-II and accordingly a team of
officials of the AAI including a Surveyor visited the site in the
presence of the representative of the petitioner on 01.11.2018. There
is only one ASR (Airport Surveillance Radar) at Kolkata Airport and
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 41
as such multi radar criteria as per GSR 751 (E) is not applicable as
another radar is MSSR which is an Air Route Surveillance Radar
(ARSR) and cannot be considered for multi radar criteria. The Final
Report was prepared and was supplied to the petitioner. The Report
was based on the Site Survey/file noting/calculations carried out
based on site survey by the officials of respondent no.1/AAI. Sh. Rai
also countered the contention of the petitioner that the respondent
no.1/AAI has applied rudimentary or unscientific methods which was
crude and argued that the calculation method to arrive at structure
angle individually or the gap angle between the two buildings was
purely scientific and accurate. Sh. Rai categorically stated that the
crude method mentioned in the file noting refers only to the pictorial
depiction which was drawn just for explanation purpose that how the
angle calculation is arrived at and the pictorial representation is crude
as it is not drawn to the scale and the drawn angles and sizes of the
buildings will not be able to represent the actual ones and Tower-I
and Tower-II are indicated as spots in two dimensional
representations for easy understanding. The angle calculation is based
on "Bearing" information of the site coordinates when seen from the
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 42
Radar and the said information is calculated automatically by
NOCAS ARC, GIS software of ESRI which is elaborated in the
Report dated 18.07.2019.
6.5 Sh. Rai also countered the reliance of the petitioner on the noting
of the officer of the respondent no.1/AAI wherein said officer has
referred the methodology to be crude and stated that said officer in
conclusion of note mentioned that "Cluster of both towers
subtends angle of more than 0.4 degrees and hence become Large
Structure." The noting in the official files is essentially an internal
matter of the Government and does not have any legal sanctity unless
approved by the Competent Authority and communicated to the
concerned person and reliance was placed on Pimpri Chinchwad
New Township Development Authority V Vishnudev Coop.
Housing Society, (2018) 8 SCC 215. Sh. Rai argued that the present
petition be dismissed.
7. The petitioner in present petition has sought for quashing of
impugned order dated 08.03.2019 passed by the respondent
no.1/AAI. It is reflecting that the respondentno.1/AAI had restricted
the maximum permissible height of Tower-II to 105.58 meters
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 43
ASML in terms of No Objection Certificate dated 03.07.2014 in
contrast to height of 144.53 Meters AMSL which was granted in
terms of No-Objection Certificate dated 26.07.2006 which was valid
for a period of three years. The site of the petitioner pertaining to
Tower-II is situated at a distance of 7.06 Kilometres from NSCB
International Airport, Kolkata. The petitioner could not conclude
construction within stipulated time and applied for revalidation of
First NOC on 27.08.2010 but the respondent no 1 vide letters dated
13.12.2010 and 03.07.2014 had approved height of Tower-II up to
90.30 Meters AMSL from the existing radar. The respondent no 1 has
increased height of Tower-II up to 105.48 Meters AMSL after
proposed ASR had been commissioned. The petitioner filed a Writ
Petition bearing no. 7652/2015 to challenge the order dated
24.06.2015, NOC dated 03.07.2014 and Letter dated 29.07.2015
issued by respondent no 1 and said petition was dismissed vide order
dated 25.04.2016. The petitioner filed appeal vide LPA no. 503/2016
which was allowed to be dismissed as withdrawn vide the order dated
24.09.2019 but without expressing any view on the merits or the
pleas taken by the appellants i.e. the petitioner. The respondent no.2
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 44
on 30.09.2015 again notified new General Statutory Rules (G.S.R.)
No. 751 (E), 2015 on height restrictions for safeguarding of aircraft
operations. The petitioner again approached the respondent no.1 vide
letter dated 21.08.2017 to consider its case for revalidation under
2015 Notification. The respondent no.1/AAI vide impugned Order
dated 08.03.2019 restricted the maximum permissible height of
Tower-II to 105.58 meters ASML as per No Objection Certificate
dated 03.07.2014.
8. Sh. Jayant Mehta, the learned Senior Counsel for the petitioner
strongly and primarily argued that the case of the petitioner for height
restriction imposed vide the impugned order dated 08.03.2019 was
examined on basis of "crude method" and without resorting to any
mathematical solution or computer simulated modelling and file
noting in Site Inspection Report of the respondent no.1/AAI also
reflected use of "crude method without any mathematical solution or
computer simulated modelling" to arrive at a conclusion that the two
towers formed a cluster subtending an angle of more than 0.4 degrees
and as such forming a large object. Sh. Mehta after referring Site
Visit Report argued that Report itself notes that the Tower-II if
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 45
assessed in isolation is classified as a 'small structure' and is not
"Large object" as defined in Clause 2.5.1.1 of the 2015 Notification
as the angle formed by the Tower-II when seen from the ASR/MSSR
radar is 0.25 Degree and the angle formed by the Tower-II when seen
from MSSR (ARSR) is 0.19 degree which is less than 0.4 Degree.
Sh. Mehta further highlighted that the respondent no.1/AAI has
wrongly assessed the permissible height without considering the tilt
angle.
8.1 Sh. Rai, the learned counsel for the respondent no.1/AAI
countered arguments advanced by Sh. Mehta on behalf of the
petitioner and argued that S.O. 84(E) and GSR 751 (E) contained a
stipulation regarding "Large object" i.e. the structure/s in isolation or
collectively subtending azimuth angle of 0.4 degree or above at
Radar antenna and entire cluster should be considered as one object
in case of cluster of buildings wherein the gap between the two
adjacent buildings subtends an azimuth angle of less than 0.4 degree
on the antenna pedestal and Tilt Angle is not the criteria for height
restriction from Airport Surveillance Radar and the height of 105.48
meters ASML in respect of Tower-II is final. Sh. Rai further strongly
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 46
argued that once the site co-ordinates are entered in the NOCAS
application system, the "Bearing" information is automatically
provided in the NOCAS Height Sheet. The Kolkata Airport is not
considered for multi radar criteria. Sh. Rai strongly argued that the
calculation method used to arrive at structure angle individually or
the gap angle between the two buildings was purely scientific and
accurate and the crude method mentioned in the file noting refers
only to the pictorial depiction which was drawn just for explanation
purpose and not drawn to the scale. Sh. Rai also stated that office rof
the respondent no.1/AAI in conclusion of note mentioned that
"Cluster of both towers subtends angle of more than 0.4 degrees
and hence become Large Structure."
8.2 The perusal of Site Inspection Report reflects that a team duly
constituted by the competent authority visited site on 01.11.2018 to
verify and record coordinates of the structures. In respect of the
Tower-II, it was concluded that angle is less than 0.4 degree, hence
Tower-II is a small structure in isolation. The Tower-I and Tower-II
were treated as cluster as gap was found to be less than 0.4 degree on
gap analysis between Tower-I and Tower-II. The angle analysis for
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 47
Tower-II based on NOCAS sheet was also done. It was noticed that
since the angle was less than 0.4, Tower-II was a structure in
isolation. It was concluded at end on basis of calculation that the
Tower-II along with Tower-I forms a large structure when seen from
ASR/MSSR Kolkata and accordingly, higher height as claimed by
the petitioner was not granted and permissible top elevation remained
at 104.57 meters ASML for Tower-II. It is reflecting that angle
analysis in respect of Tower-I and Tower-II was done based on
NOCAS Sheet which is a scientific method. There is no force in
argument advanced by Sh. Jayant Mehta, the learned Senior Counsel
for the petitioner that height restriction vide impugned order dated
08.03.2019 was examined on basis of "crude method" and without
resorting to any mathematical solution or computer simulated
modelling. Even if file noting in Site Inspection Report contained
reflected use of "crude method without any mathematical solution or
computer simulated modelling", it does not provide much help to the
petitioner. More over this Court cannot sit as an appellate court over
the decision is taken by an expert body due to lack of technical
expertise as rightly argued by the counsel for the respondent no.1.
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 48
9. Sh. Mehta also referred Report dated 10.12.2018 prepared by
Sakhti Aviation wherein highlighted that there was no measurement
technique or application available to measure the gap between towers
from space with respect to radar and found that the gap between
Tower-I and Tower-II is more than 0.4 degree and concluded that
Tower-I and Tower-II did not form a cluster as per Clause 2.5.2.2 sub
clause IV of the 2015 Notification. Sh. Rai argued that Sakhti
Aviation Report is incorrect as M/s. Sakhti selected the site co-
ordinates for calculating gap angle as per its own convenience and
report of Sakhti Aviation is not binding on the respondent no.1/AAI
as per the existing rules. There is force in arguments advanced by Sh.
Rai as Report given by M/s Sakhti Aviation is without any legal
sanctity.
10. Sh. Mehta after referring Site Visit Report also stated that there
was more than one radar at Kolkata airport at the time of assessing
the height of Tower-I and Tower-II on 01.11.2018 and the case of the
petitioner must be assessed by criterion of multi-radar and due to this
reason, the case of the petitioner be assessed on the basis of the 2015
Notification. Sh. Rai stated that Kolkata only has one single ASR
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 49
Radar and as such multi radar criteria as per GSR 751 (E) is not
applicable as another radar is MSSR which is an Air Route
Surveillance Radar (ARSR) and cannot be considered for multi radar
criteria. There is no material on record to show that Kolkata Airport
is having more than one radar. The argument so advanced by Sh.
Mehta is misconceived and misplaced.
11. Sh. Mehta also attacked the impugned order dated 08.03.2019 by
arguing that the respondent no.1/AAI being a public authority was
bound to record valid and cogent reasons explaining the decision
arrived at vide impugned order dated 08.03.2019 but the respondent
no.1/AAI has failed to provide any reason while passing the
impugned order dated 08.03.2019. The impugned order dated
08.03.2019 reads as under:-
Sir, Please refer your Building project case located at Plot No.AAII/CBD/2 ,New Town, Kolkata, West Bengal.
On examination, it was concluded that the Tower-II does not qualify for higher height, as along with Tower-I, it becomes a large structure.
Therefore, Tower-II is restricted to the earlier Top Elevation granted by AAI.
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 50
11.1 The principles of natural justice involve a procedural
requirement of fairness and have become an essential part of any
system of administrative justice. Natural Justice is considered to be
part of rule of law. The Supreme Court in Sangram Singh V
Election Tribunal Kotah, AIR 1955 SC 425 observed that one
should not be condemned unheard and decision should not be
reached behind the back. The Supreme Court in Maneka Gandhi V
Union of India, AIR 1978 SC 597 emphasized that natural justice is
an essential element of procedure established by law and state action
must be right, just and fair and not arbitrary, fanciful and oppressive.
It was held that Article 14 of the Constitution strikes at arbitrariness
of state action and ensures fairness and equality of treatment.
11.2 The Supreme Court in Indian Oil Corporation Limited and
others V Shashi Prabha Shukla and another, (2018) 12 SCC 85
observed as under:-
33. (a) public authority in its dealings has to be fair, objective, non arbitrary, transparent and non discriminatory. The discretion vested in such an authority, which is a concomitant of its power is coupled with duty and can never be unregulated or unbridled. Any decision or action contrary to these functional precepts would be at the pain of invalidation thereof. The State and its instrumentalities, be it a public authority, either as an
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 51
individual or a collective has to essentially abide by this inalienable and non negotiable prescriptions and cannot act in breach of the trust reposed by the polity and on extraneous considerations. In exercise of uncontrolled discretion and power, it cannot resort to any act to fritter, squander and emasculate any public property, be it by way of State largesse or contracts, etc. Such outrages would clearly be unconstitutional and extinctive of the rule of law which forms the bedrock of the constitutional order.
11.3 The Supreme Court in Southern Power Distribution
Company Limited of Andhra Pradesh (APSPDCL) & another V
M/s Hinduja National Power Corporation Limited & Another,
2022 Livelaw (SC) 117 and also cited on behalf of the petitioner
observed as under:-
Every action of a State is required to be guided by the touchstone of non arbitrariness, reasonableness and rationality. Every action of a State is equally required to be guided by public interest. Every holder of a public office ·is a trustee, whose highest duty is to the people of the country. The Public Authority is therefore required to exercise the powers only for the public good.
11.4 The principles of natural justice are equally applied in purely
administrative functions. The Supreme Court in A.K. Kraipak V
Union of India, AIR 1970 SC 150 observed that the principles of
natural justice are applicable to administrative inquiries and
established that observance of principles of natural justice in decision
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 52
making process of the administrative body having civil
consequences.
11.5 The purpose of the principles of natural justice is to prevent
miscarriage of justice. The expression audi alteram partem implies
that a person must be given an opportunity to defend himself and
ensures that no one should be condemned unheard. The
administrative authority is also required to afford reasonable
opportunity to the party to present his case. A real, rationale and
effective hearing includes disclosure of all relevant material or
information which the authority wishes to use against the individual
in arriving of its decision. The administrative authority cannot take a
decision on the basis of any material unless the person against whom
it is sought to be utilized is given an opportunity to rebut or explain
the same.
11.6 The Supreme Court in Engineer and Manufacturing Co. V
Union of India, AIR 1976 SC 1785 reiterated the principle with an
emphasis that the rule requiring reasons to be given in support of an
order is a basic principle of natural justice, which must inform the
quasi-judicial process. It should be observed in its proper spirit and
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 53
"mere pretence of compliance with it would not satisfy the
requirement of law". It was observed in Maneka Gandhi V Union of
India, AIR 1990 SC 1984 that giving of reasons is a healthy check
against abuse or misuse of power. The requirement of duty to give
reasons was further crystallized in S.N. Mukherjee V Union of
India, AIR 1990 SC 1984 and reasons due to which a reasoned
decision must be passed were discussed. It was observed that
reasoned decision: (i) guarantee consideration by the authority; (ii)
introduce clarity in decisions; and (iii) minimize chances of
arbitrariness in decision-making thereby ensuring fairness in the
process. It was observed as under:
In our opinion, therefore, the requirement that reason must be recorded must be recorded should govern the decisions of govern the an administrative authority exercising quasi judicial functions irrespective of fact whether the decision is subject to appeal, revision or judicial review. It may, however, be added that it is not required that the reasons should be as elaborate as in the decision of a court of law. The extent and nature of the reasons would depend on particular facts and circumstances. What is necessary is that the reasons are clean and explicit so as to indicate that the authority has given due consideration to the points in controversy.
11.7 The Supreme Court in Rani Lakshmi Bai Kshetriya Gramin
Bank V Jagdish Sharan Varshney & others, (2009) 4 SCC 496
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 54
held that the purpose of disclosure of reasons is that people should
have confidence in judicial and quasi-judicial authorities and
minimize chances of arbitrariness. It was held as under:-
The purpose of disclosure of reasons, as held by a Constitution Bench of this Court in the case of S.N. Mukherjee vs. Union of India reported in (1990) 4 SCC 594, is that people must have confidence in the judicial or quasi-judicial authorities. Unless reasons are disclosed, how can a person know whether the authority has applied its mind or not? Also, giving of reasons minimizes chances of arbitrariness. Hence, it is an essential requirement of the rule of law that some reasons, at least in brief, must be disclosed in a judicial or quasi-judicial order, even if it is an order of affirmation.
11.8 The Supreme Court in the case of Namit Sharma V Union of
India, (2013) (1) SCC 745 regarding duty to give reasons held as
under:-
It is not only appropriate but is a solemn duty of every adjudicatory body, including the tribunals, to state the reasons in support of its decisions. Reasoning is the soul of a judgment and embodies one of the three pillars on which the very foundation of natural justice jurisprudence rests. It is informative to the claimant of the basis for rejection of his claim, as well as provides the grounds for challenging the order before the higher authority/constitutional court. The reasons, therefore, enable the authorities, before whom an order is challenged, to test the veracity and correctness of the impugned order. In the present times, since the fine line of distinction between the functioning of the administrative and quasi- judicial bodies is gradually becoming faint, even the administrative bodies are required
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 55
to pass reasoned orders. In this regard, reference can be made to the judgments of this Court in the cases of Siemens Engineering & Manufacturing Co. of India Ltd. v. Union of India &Anr. [(1976) 2 SCC 981]; and Assistant Commissioner, Commercial Tax Department Works Contract and Leasing, Kota v. Shukla & Brothers [(2010) 4 SCC 785].
12. The perusal of impugned order dated 08.03.2019 passed by the
respondent no.1/AAI reflects that it was issued without properly
appreciating the material and without assigning any reason and is in
violation of the Principles of Natural Justice. The respondent
no.1/AAI being a statutory authority in discharge of its duties was
legally bound to record valid and cogent reasons explaining the
decision arrived at in the impugned order dated 08.03.2009 but it was
passed without giving reasons for its decision. The decision by the
statutory authority must be non-arbitrary and be supported by
sufficient reason. The impugned order dated 08.03.2019 is cryptic,
mechanical and is passed without application of mind. The impugned
order dated 08.03.2019 is passed without giving reasons and is
accordingly set aside. However, the respondent no.1 shall be at
liberty to initiate appropriate action in accordance with law.
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 56
13. The present petition is accordingly allowed. The pending
application, if any, also stands disposed of.
DR. SUDHIR KUMAR JAIN (JUDGE) OCTOBER 15, 2024 N/AK
Signing Date:16.10.2024 W.P.(C).11422/2019 Page 57
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!