Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Union Of India vs M/S Tayal And Co.
2023 Latest Caselaw 4099 Del

Citation : 2023 Latest Caselaw 4099 Del
Judgement Date : 11 October, 2023

Delhi High Court
Union Of India vs M/S Tayal And Co. on 11 October, 2023
                          $~
                          *     IN THE HIGH COURT OF DELHI AT NEW DELHI
                                                  Judgment pronounced on :11.10.2023
                          +     FAO (COMM) 140/2022 & CM APPLS.41854-41857/2022
                                UNION OF INDIA                                  ... Appellant
                                                         versus
                                M/S TAYAL AND CO.                                ... Respondent

                          Advocates who appeared in this case:
                          For the Appellant        :     Mr. Mukul Singh, CGSC with Ms. Ira
                                                         Singh, Advocate.

                          For the Respondent       :     None.
                          CORAM:
                          HON'BLE MR. JUSTICE RAJIV SHAKDHER
                          HON'BLE MR. JUSTICE TARA VITASTA GANJU
                          TARA VITASTA GANJU, J.:
                                                 TABLE OF CONTENTS
                          Preface...................................................................................1
                          Brief facts .............................................................................2
                          Submissions ................................................................................7
                          Analysis ......................................................................................8
                          Conclusion.................................................................................13
                          Condonation of Delay in filing the Appeal........................................24

                          CM APPL.41854/2022& CM APPL.41857/2022[Exemption]
                          1.    Allowed, subject to just exceptions.
                          FAO (COMM) 140/2022 & CM APPL.41855/2022[Application seeking
                          interim relief]
                          PREFACE:
                          2.    The present Appeal has been filed against the Order/ Judgment dated
                          20.01.2022, passed by the District Judge, Patiala House Courts, New Delhi


                          FAO (COMM) 140/2022                                          Page 1 of 26
Signature Not Verified
Digitally Signed
By:YASHPAL GROVER
Signing Date:13.10.2023
01:50:42
                           [hereinafter referred to as "Impugned Order"] in petition under Section 34 of
                          the Arbitration and Conciliation Act, 1996 [hereinafter referred to as "the
                          Act"] against the Arbitral Award dated 26.03.2019 [hereinafter referred to as
                          "Arbitral Award"].
                          3.     The Appellant/Railways herein has prayed for the setting aside of the
                          Impugned Order, wherein the learned District Judge upheld the Arbitral
                          Award passed by the Sole Arbitrator in favour of the Respondent/Claimant.
                          BRIEF FACTS:
                          4.     Briefly, the facts were that the Respondent/Claimant was awarded a
                          contract for supply of 1,68,000 Sleepers valued at Rs.20,05,92,000/- by the
                          Appellant/Railways. An agreement was executed between the parties on
                          08.01.2010 [hereinafter called the "Contract"] and Respondent/Claimant
                          was to supply the sleepers by 25.12.2011.
                          4.1    During the term of the Contract, the Respondent/Claimant sought
                          extension of time on more than one occasion. It was contended by the
                          Respondent/Claimant that this extension was sought essentially due to non-
                          supply of materials that were necessary for the manufacture of the sleepers,
                          which were not made available for successive months by the company
                          nominated by the Appellant/Railways.
                          4.2    The    Respondent/Claimant       addressed     several     communications
                          including letters dated 09.03.2010, 22.07.2010, 11.10.2011, 20.12.2011 and
                          18.06.2012 wherein this factum of non-supply of cement in time and supply
                          of    insufficient    quantity   was   brought   to    the      attention   of        the
                          Appellant/Railways. These communications additionally highlighted the
                          problems as below:
                                 (i)    Lack of sufficient materials, aggregated sand from Tussan

                          FAO (COMM) 140/2022                                                    Page 2 of 26
Signature Not Verified
Digitally Signed
By:YASHPAL GROVER
Signing Date:13.10.2023
01:50:42
                                  because digging of the Aravalli Hills had been banned by an order
                                 passed by the High Court of Punjab and Haryana at Chandigarh.
                                 (ii)    The SGCI Inserts required for the Sleepers were not
                                 supplied regularly and insufficient quantities by the two
                                 "approved" companies for SGCI Inserts in Northern India and this
                                 supply was the essential material for production of the sleepers.
                                 (iii)   On account of the Commonwealth Games in Delhi
                                 scheduled for October, 2010, there was a shortage of raw materials
                                 like cement, steel, aggregate sand in the open market.
                                 (iv)    The payments for Sleepers already supplied and other
                                 railway components were being delayed by Appellant/Railways
                                 for each running invoice.
                          4.3    The Respondent/Claimant, initially, by its letter dated 11.10.2011,
                          requested for extension of delivery period for six months without the
                          imposition of liquidated damages.
                          4.4    Thereafter, by letter dated 20.12.2011, the issues being faced by the
                          Respondent/Claimant in adhering to the time schedule were reiterated.
                          4.5    The Appellant/Railways extended the delivery period up to
                          30.06.2012 in the first instance but imposed liquidated damages on the
                          Respondent/Claimant for this extension.
                          4.6    By letters dated 30.04.2012 and 07.05.2012, the Respondent/Claimant
                          had requested the Appellant/Railways to collect the finished „normal
                          sleepers and turn out sets‟ lying at the factory after inspection to enable
                          them    to     utilize   full   capacity   of   their   factory.   Thereafter,        the
                          Respondent/Claimant by its communication dated 18.06.2012 requested for
                          further extension of delivery period.

                          FAO (COMM) 140/2022                                                    Page 3 of 26
Signature Not Verified
Digitally Signed
By:YASHPAL GROVER
Signing Date:13.10.2023
01:50:42
                           4.7    A supplementary agreement was executed by the parties on
                          06.11.2012 [hereinafter referred to as "Supplementary Agreement"] wherein
                          the   delivery      period    under        the    Contract    was   extended       by        the
                          Appellant/Railways upto 31.12.2012. However, it was done on imposition
                          of    liquidated     damages       and      without     the    benefit   of    the      price
                          escalation/variation clause.
                                       "...The delivery period is extended up to 31.12.2012 with LD,
                                       without PVC and with denial clause. However, in case of fall in PVC
                                       indices, PVC will be applicable on negative side.
                                       The other conditions, stipulations, rates etc. applicable to the said
                                       Original Agreement and Subsidiary letters shall also be applicable to
                                       the Subsidiary Agreement unless repugnant to or excluded by the
                                       context....."
                                                                                           [Emphasis is ours]

                          4.8    The Appellant/Railways initially cancelled supply of 8,668 Sleepers
                          and imposed a penalty of Rs.7,77,553.35/- on 05.12.2011, and thereafter,
                          cancelled supply of 13,354 Sleepers and imposed a penalty of
                          Rs.12,75,387.13/- on 22.02.2012. The Appellant/Railways also imposed
                          liquidated      damages       in     the         sum   of     Rs.25,10,835/-      on         the
                          Respondent/Claimant.
                          4.9    The Respondent/Claimant requested for initiation of Arbitral
                          Proceedings in terms of Arbitration Clause as set forth in Clause 2900 of the
                          Indian Standard Railway Conditions of Contract, including by its letter dated
                          18.06.2012. The Arbitral Clause, which is reproduced below, provided for
                          appointment of a Gazetted Railway Officer as a Sole Arbitrator by the
                          Appellant/Railways:
                                         "2900. Arbitration.
                                         (a) In the event of any question, dispute or difference arising under
                                         these conditions or any special conditions of contract, or in
                                         connection with this contract (except as to any matters the decision


                          FAO (COMM) 140/2022                                                           Page 4 of 26
Signature Not Verified
Digitally Signed
By:YASHPAL GROVER
Signing Date:13.10.2023
01:50:42
                                         of which is specially provided for by these or the special
                                        conditions) the same shall be referred to the sole arbitration of a
                                        Gazetted Railway Officer appointed to be the arbitrator, by the
                                        General Manager in the case of contracts entered into by the
                                        Zonal Railways and Production Units; by any Member of the
                                        Railway Board, in the case of contracts entered into by the
                                        Railway Board and by the Head of the Organisation in respect of
                                        contracts entered into by the other Organisations under the
                                        Ministry of Railways. The Gazetted Railway Officer to be
                                        appointed as arbitrator however will not be one of those who had
                                        an opportunity to deal with the matters to which the contract
                                        relates or who in the course of their duties as railway servant have
                                        expressed views on all or any of the matters under dispute or
                                        difference. The award of the arbitrator shall be final and binding
                                        on the parties to this contract......."
                                                                                       [Emphasis is ours]

                          4.10 The Appellant/Railways appointed Sh. Surinder Kumar, Chief
                          Engineer, P&D, Northern Railways Headquarters, New Delhi as the Sole
                          Arbitrator to adjudicate the disputes between the parties on 22.05.2012.
                          4.11 The Respondent/Claimant filed a Statement of Claim on 21.02.2013
                          for the following recoveries:
                                (i)     Claim No.1: Refund of Rs.7,77,553.35/- along with 9%
                                interest w.e.f. date of recovery.
                                (ii)    Claim No.2: Deduction of Rs.12,75,387.13/- to be quashed.
                                (iii)   Claim No.3: Refund of Rs.25,10,835/- along with 9%
                                interest w.e.f. date of recovery.
                                (iv)    Claim No.4: Payment of unpaid PVC in the sum of
                                Rs.18,63,527.66/-along with 9% interest w.e.f. date of recovery.
                                (v)     Claim No. 5: Towards loss of profit.
                          4.12 The Appellant/Railways filed the following as its counter claims on
                          19.03.2014:
                                (i)     Counter Claim No.1: Retention of Rs.7,77,553.35/- along


                          FAO (COMM) 140/2022                                                       Page 5 of 26
Signature Not Verified
Digitally Signed
By:YASHPAL GROVER
Signing Date:13.10.2023
01:50:42
                                 with 24% interest w.e.f. date of notice of demand.
                                (ii)    Counter Claim No.2: Recovery of Rs.12,75,387.13/- along
                                with 24% interest from the respondent w.e.f. date of notice of
                                demand.
                                (iii)   Counter Claim No.3: Rs.1,25,000/- as legal expenses of
                                Arbitration along with Rs.1,00,000/- towards legal expenses of
                                proceedings before this Court.
                          5.    The Respondent/Claimant contended that the delay, if any, was
                          attributable solely to the Appellant/Railways and not on account of any
                          failure of the Respondent/Claimant but was caused due to circumstances
                          beyond the control of the Respondent/Claimant. It was further contended,
                          that action of imposing and recovering penalty and liquidated damages by
                          the Appellant/Railways was unwarranted, unlawful and unjustified.
                          5.1   The Appellant/Railways contended, that the delay was caused by the
                          Respondent/Claimant and hence the liquidated damages levied and
                          deductions made, were rightly made from the payments made to the
                          Respondent/Claimant under the Contract.
                          5.2   The Sole Arbitrator published the Award on 26.03.2019 allowing
                          Claims 1 to 4 of the Respondent/Claimant and dismissed the Counter Claims
                          of the Appellant/Railways.
                          6.    The Arbitral Award was challenged by the Appellant/Railways by
                          filing a Petition under Section 34 of the Act before the District Judge.
                          6.1   By the Impugned Order, the District Judge dismissed the Petition
                          holding that the Arbitral Award does not suffer from any perversity and is
                          not against public policy. It was further held that the Petition was filed
                          belatedly by the Appellant/Railways without sufficient cause.

                          FAO (COMM) 140/2022                                               Page 6 of 26
Signature Not Verified
Digitally Signed
By:YASHPAL GROVER
Signing Date:13.10.2023
01:50:42
                           6.2   Thus, the Impugned Order dismissed the petition filed under Section
                          34 of the Act both on maintainability and on merits as well.
                          SUBMISSIONS OF THE APPELLANT/RAILWAYS:
                          7.    Learned Counsel for the Appellant/Railways raised the following
                          contentions in this Appeal:
                                (i)     The Arbitral Award passed by the Sole Arbitrator is sans
                                merit and is in clear violation of the guidelines set forth in the Act.
                                Relying on Section 34(2)(b)(ii) of the Act. The Arbitral Award has
                                been passed against the public policy and hence setting aside of
                                the Arbitral Award is warranted.
                                (ii)    The Appellant/Railways had calculated the penalty as per
                                Clause 11 of the Contract, for delayed delivery which was
                                conveyed to the Respondent/Claimant by letters dated 05.12.2011
                                and 22.02.2012. The letters, however, were not responded to.
                                Hence, these amounts were rightly deducted and recovered as
                                liquidated      damages     from     outstanding      payments       of
                                Respondents/Claimants.
                                (iii)   Time was the essence of the Contract between the parties.
                                The     delivery   dates    were     not    adhered     to   by     the
                                Respondent/Claimant and time extension was granted thrice to the
                                Respondent/Claimant. Thus, the Appellant/Railways was well
                                within its rights to impose penalty on the Respondent/Claimant
                                and waiver of the liquidated damages clause was not possible as
                                was agreed to by the Respondent/Claimant in the Supplementary
                                Agreement.
                                (iv)    It was further contended that it was not possible in the

                          FAO (COMM) 140/2022                                                Page 7 of 26
Signature Not Verified
Digitally Signed
By:YASHPAL GROVER
Signing Date:13.10.2023
01:50:42
                                 present case to prove actual loss and that the findings in this regard
                                of the Sole Arbitrator which were affirmed by the learned District
                                Judge were wrong.
                                (v)    It was contended that the learned District Judge did not
                                appreciate the meaning of Force Majeure Clause as provided in the
                                Contract. The Sole Arbitrator incorrectly interpreted the Force
                                Majeure Clause as it appears in the Contract, and the District
                                Judge affirmed this interpretation as shortage of cement, power
                                cuts and ban on digging in the Aravalli Hills did not fall within the
                                meaning and ambit of the Force Majeure clause.
                                (vi)   No document was produced before the Sole Arbitrator,
                                evidencing the power cuts. In any event, the bidders were advised
                                in the tender document to take into account regular power cuts
                                while quoting for tenders. Thus, the Force Majeure clause did not
                                apply to the contract.
                                (vii) The copy of Arbitral Award was received by the
                                Appellant/Railways on 28.03.2019, the Petition under Section 34
                                of the Act was filed on 12.07.2019 in a delay of 11 days.
                                Sufficient reasons for the delay were furnished in the Application
                                for condonation of delay, despite which its Application was
                                rejected.
                          8.    The Appeal was listed for admission before this Court. Since there
                          was no appearance on behalf of the Respondent/Claimant despite service,
                          this Court proceeded to hear this matter.
                          ANALYSIS:
                          9.    We have heard the Learned Counsel for the Appellant/Railways and

                          FAO (COMM) 140/2022                                               Page 8 of 26
Signature Not Verified
Digitally Signed
By:YASHPAL GROVER
Signing Date:13.10.2023
01:50:42
                           have perused the record as produced before us.
                          9.1   The record reveals that after an examination of evidence placed by the
                          parties before it, the Sole Arbitrator reached the following conclusions:
                                (i)     Delay in supply was largely due to delay in supply of
                                cement, by the Appellant/Railways supplier i.e., M/s. Ambuja
                                Cements who were the only approved supplier by the
                                Appellant/Railways for this purpose. There was no alternative
                                source nominated for the procurement of the cement. The
                                Respondent/Claimant      sent   several   communications     to    the
                                Appellant/Railways including 09.03.2010, 22.07.2010, 11.10.2011
                                and 18.06.2012 in this regard, informing Appellant/Railways of
                                the shortage of the cement, and other (unforeseeable) events that
                                had occurred during the term of the Contract. However, these
                                communications were not dealt with by the Appellant/Railways
                                and instead communications imposing and calculating penalty for
                                delay were sent.
                                (ii)    The issue of delayed payment of Respondent/Claimant bills
                                was also accepted by the Sole Arbitrator as the chart of delayed
                                payments filed by the Respondent/Claimant with its Statement of
                                Claim was not disputed by the Appellant/Railways apart from
                                "bare denial" by the Appellant/Railways. No record was placed by
                                the Appellant/Railways to show that they made timely payments
                                to the Respondent/Claimant.
                                (iii)   It was held by the Sole Arbitrator that coupled with the
                                delay in supply for cement, there were power cuts in Haryana and
                                Himachal Pradesh, and the State Government banned the mining

                          FAO (COMM) 140/2022                                               Page 9 of 26
Signature Not Verified
Digitally Signed
By:YASHPAL GROVER
Signing Date:13.10.2023
01:50:42
                                     in the Aravalli Hills. Further, that the Commonwealth Games,
                                    2010 disturbed the transportation of the Respondent/Claimant.
                                    These events would qualify as Force Majeure conditions in the
                                    Contract as the Respondent/Claimant could not have reasonably
                                    foreseen these factors.
                          9.2       The Respondent/Claimant raised several contentions in support of the
                          Arbitral Award during the proceedings before the District Judge including:
                                    (i)     The delay was attributable to the Appellant/Railways and its
                                    nominated cement company and due reasons beyond the control of
                                    the Respondent/Claimants.
                                    (ii)    There was no equal bargaining power between the
                                    Respondent/Claimant and the Appellant/Railways and the
                                    Supplementary Agreement which provided for extension of
                                    delivery period up to 31.12.2012 with imposition of liquidated
                                    damages was executed under coercion and duress and could not be
                                    said to be binding on the Respondent/Claimant.
                                    (iii)   The Sole Arbitrator had examined the evidence and cogent
                                    and plausible reasons have been given by the Sole Arbitrator for
                                    allowing some claims of the Respondent/Claimant and disallowing
                                    the counter-claims of the Appellant/Railways which cannot be
                                    interfered with in a Petition under Section 34 of the Act.
                                    (iv)    The Arbitral Award has been passed in terms of the
                                    principles enunciated in Ssangyong Engineering & Construction
                                    Co. Ltd. vs. National Highways Authority of India (NHAI)1, that


                          1
                              2019 SCC OnLine SC 677


                          FAO (COMM) 140/2022                                                    Page 10 of 26
Signature Not Verified
Digitally Signed
By:YASHPAL GROVER
Signing Date:13.10.2023
01:50:42
                                 a Court in a Petition under Section 34 of the Act while
                                adjudicating an Arbitral Award on the test of "public policy" is
                                not an appellate Court and does not sit in appeal over the Arbitral
                                Award of an Arbitral Tribunal by re-assessing or re-appreciating
                                the evidence and therefore, if the view taken by the Arbitral
                                Tribunal is a possible one, it does not merit any interference.
                                (v)      Lastly, it was contended that the Application for
                                condonation of delay depicts gross negligence and deliberate
                                inaction on the part of the concerned officers of the
                                Appellant/Railways and their Counsels and the delay in filing the
                                Petition cannot be mechanically condoned and hence, the Petition
                                under Section 34 of the Act was time barred as well.
                          9.3   The Appellant/Railways raised the contentions as have been raised by
                          them before this Court, which have pithily been set forth hereinabove in
                          paragraph 7.
                          10    It was, therefore, held by the Sole Arbitrator that since the delay was
                          occasioned by circumstances which could not have reasonably been foreseen
                          by the Respondent/Claimant including on account of the nominated
                          companies of Appellant/Railways and Force Majeure events, hence the
                          deductions were not justified.
                          10.1 The Counter Claim(s) of the Appellant/ Railways were rejected by the
                          Sole Arbitrator in view of his finding that the action of the
                          Appellant/Railways of imposing and recovering penalty and liquidated
                          damages was unwarranted.
                          10.2 The Sole Arbitrator awarded the following amounts to the
                          Respondent/Claimant:

                          FAO (COMM) 140/2022                                               Page 11 of 26
Signature Not Verified
Digitally Signed
By:YASHPAL GROVER
Signing Date:13.10.2023
01:50:42
                                 (i)     Refund of Rs.7,77,553.35/- towards deduction/amounts
                                withheld with interest @ 9% per annum from the date of recovery
                                till payment in favour of Respondent/Claimant payable by
                                Appellant/Railways;
                                (ii)    Quashing    of    deduction    of     Rs.12,75,387.13/-     by
                                Appellant/Railways holding Appellant/Railways is not entitled to
                                recover it from Respondent/Claimant;
                                (iii)   Refund of Rs.25,10,835/- levied/recovered as liquidated
                                damages to be reimbursed to Respondent/Claimant with interest
                                @ 9% per annum from the date of recovery till payment by
                                Appellant/Railways;
                                (iv)    Rs.18,63,527.66/- towards unpaid Price Variation Clause (in
                                short PVC) as per the formula in the contract with interest @ 9%
                                per annum till payment, payable by Appellant/Railways to
                                Respondent/Claimant;
                                (v)     It was also directed by the Sole Arbitrator, that the Awarded
                                sum under the Arbitral Award was payable within 45 days of
                                Arbitral Award failing which 10% interest, compounded per
                                month       was      payable      by        Appellant/Railways      to
                                Respondent/Claimant from date of Arbitral Award till date of
                                payment.
                          11.   The District Judge examined the findings of the Sole Arbitrator as
                          well as the Arbitral Award. Relying on the reasoning and on the settled law,
                          the District Judge found that the reasoning of the Sole Arbitrator to be
                          logical and that all material and evidence was taken note of.
                          11.1 The Impugned Order found no infirmity in the Arbitral Award and

                          FAO (COMM) 140/2022                                               Page 12 of 26
Signature Not Verified
Digitally Signed
By:YASHPAL GROVER
Signing Date:13.10.2023
01:50:42
                           held that delay in supply of the sleepers as per the terms of the Contract, if
                          any, was attributable to Appellant/Railways on non-supply of an alternate
                          source of procurement of cement. It was also held that the delay did not
                          occur due to any failure of Respondent/Claimant but had taken place due to
                          the factors beyond the control of Respondent/Claimant and therefore, the
                          same would qualify as a Force Majeure event. Additionally, it was also held
                          that the Application for condonation of delay did not provide for sufficient
                          reasons to condone the delay in filing the Petition under Section 34 of the
                          Act.
                          12.    Paragraph 6.3 of the Arbitral Award has found that the reasons for
                          delay were attributable to the Appellant/Railways as well as on account of
                          factors beyond their control as the Respondent/Claimant could not have
                          reasonably foreseen these events. The Force Majeure clause was also held to
                          be applicable in the Arbitral Award.
                          12.1 The Sole Arbitrator holding that the Respondent/Claimant had not
                          committed any breach of the Contract awarded the amounts deducted by the
                          Appellant/Railways as liquidated damages and payments retained and
                          withheld to the Respondent/Claimants along with interest thereon.
                          12.2 The Counter-claims of the Appellant/Railways were essentially to
                          retain payments claimed in Claims (i) and (ii) of the Respondent/Claimants
                          and for arbitral fee. The Sole Arbitrator rejected these Counter claims.
                          12.3 The findings of the Sole Arbitrator were not interfered with by the
                          District Judge in the Impugned Order, including the finding on the
                          applicability of the Force Majeure Clause.
                          CONCLUSIONS:
                          13.    The foundation of a Contract for supply of Railway sleepers has to be

                          FAO (COMM) 140/2022                                               Page 13 of 26
Signature Not Verified
Digitally Signed
By:YASHPAL GROVER
Signing Date:13.10.2023
01:50:42
                           the procurement of the raw materials which include cement, steel, sand,
                          aggregate, wires, inserts etc. The Contract between the parties specifically
                          provided that raw materials required for the performance of the Contract
                          were to be obtained only from the nominated suppliers as below:
                                       "4. Raw Material, Machinery and Plant:

                                               The responsibility for procurement or all raw materials,
                                       machinery and plants required for the manufacture of goods shall
                                       rest entirely with the supplier.
                                       4.1    Cement shall be procured by the contractor from the
                                       nominated primary/secondary source and as per the rate, terms
                                       and conditions fixed by the purchaser with cement suppliers. The
                                       contractor should always maintain a reserve buffer stock of cement
                                       adequate for at-least 2 months sleeper production:
                                       4.2     HTS Wires shall be procured .from the firms who are
                                       approved for manufacture of HTS Wire by Bureau of Indian
                                       Standards and possess a current valid BIS License for manufacture
                                       of the particular type of wire i.e. 3 x 3 mm strand, 7/7.5 mm plain
                                       wire or 9.5 mm dia strand as the case may be.
                                       4.3     SGCI Inserts shall be procured from the firms who are
                                       approved by RDSO for the manufacture of SGCI inserts and whose
                                       approval is current and valid. SGCI Inserts can also be procured
                                       from ISO certified firms as per guidelines issued vide RDSO's
                                       letter No.QA/CT/INSP/CI/Policy dated 25.08.2008.
                                       4.4  Aggregates shall be procured by the contractor from the
                                       RDSO approved sources."
                                                                                      [Emphasis is ours]
                          13.1 Within a couple of months of the Contract being entered to, the
                          Respondent/Claimant       started     addressing      communications         to    the
                          Appellant/Railways that the cement supply company is not supplying the
                          cement in time, and from February 2010 for several months, the required
                          quantity was not provided to them. The alternate supply as approved by the
                          Appellant/Railways was also not provided to the Respondent/Claimant, this
                          position remained unchanged throughout the term of the Contract.


                          FAO (COMM) 140/2022                                                     Page 14 of 26
Signature Not Verified
Digitally Signed
By:YASHPAL GROVER
Signing Date:13.10.2023
01:50:42
                           13.2 The record shows that several communications were sent to the
                          Appellant/Railways       by    the     Respondent/Claimant   detailing    out    its
                          contentions. The Arbitral Award however states that none of these
                          communications were responded to.
                          13.3 The other contention raised by the Appellant/Railways that the
                          Supplementary Agreement executed between the parties was ignored by the
                          Sole Arbitrator is incorrect. Paragraph 7.1.4 of the Arbitral Award refers to
                          the Supplementary Agreement. The Sole Arbitrator reached a conclusion
                          that      the    Supplementary       Agreement   was   entered    into   by     the
                          Respondent/Claimant           under     duress   and    without     which       the
                          Respondent/Claimant was refusing to extend the delivery period. Placing
                          reliance on the NTPC vs. Reshmi Construction2, the Sole Arbitrator has
                          held the Supplementary Agreement, based on an examination of the
                          evidence, was not executed under free consent and hence cannot be relied
                          upon.
                          13.4 The Appellant/Railways contended that it was practically not possible
                          to assess the actual damage caused to the Appellant/Railways, and the
                          deductions made by the Appellant/Railways on account of liquidated
                          damages were in terms of the Contract/Supplementary Agreement. The Sole
                          Arbitrator in Paragraph 7.1.6 of the Arbitral Award, however, has held that
                          Clause 11 of the Contract is penal in nature and that the Appellant/Railways
                          has failed to establish that the amounts claimed by it are a pre-estimate of
                          the damages it will suffer and sustained the damages claimed.
                          13.5 We find no perversity in these findings of the Sole Arbitrator.


                          2
                              AIR 2004 SC 1330


                          FAO (COMM) 140/2022                                                  Page 15 of 26
Signature Not Verified
Digitally Signed
By:YASHPAL GROVER
Signing Date:13.10.2023
01:50:42
                           14.   The Appellant/Railways contended that frequent power cuts, ban on
                          digging and the shortage of cement does not fall within the definition of
                          Force Majeure as set forth in the Contract and hence the Arbitral Award
                          suffers from patent illegality.
                          14.1 Clause 17 of the Contract refers to Force Majeure reads as follows:-
                                    "In the event of any unforeseen event directly interfering with the
                                    supply of stores arising during the currency of the contract, such as
                                    war, insurrection, restraint imposed by the Government, act of
                                    legislature or other authority, explosion, accident, acts of public
                                    enemy, acts of God, the contractor shall within a week from the
                                    commencement thereof notify the same in writing to the purchaser
                                    with reasonable evidence thereof.
                                    If the force majeure condition(s) mentioned above be in force for a
                                    period of 90 days or more at any time, the purchaser shall have the
                                    option to terminate the contract on expiry of 90 days of
                                    commencement of such force majeure by giving 14 days notice to the
                                    contractor in writing. In case of such termination, no damages shall
                                    be claimed by either party against the other save and except those
                                    which had accrued under any other clause of this agreement prior to
                                    such termination."
                                                                                     [Emphasis is ours]
                          14.2 A plain reading of this clause shows that an unforeseen event which
                          directly interferes with the supply of sleepers could be a Force Majeure
                          event/condition. It includes restraints imposed by Government or acts of
                          Parliament or other Authorities. The Force Majeure clause is however
                          subject to the Respondent/Claimant notifying the Appellant/Railways within
                          one week from its commencement with reasonable evidence thereof.
                          14.3 This clause also gives the Contractor, i.e. Respondent/Claimant, the
                          option to terminate the Contract, if the event of Force Majeure lasts more
                          than 90 days.
                          14.4 Admittedly,       the    Contract      was     not    terminated       by     the
                          Respondent/Claimant, and it did supply the revised quantities of sleepers


                          FAO (COMM) 140/2022                                                     Page 16 of 26
Signature Not Verified
Digitally Signed
By:YASHPAL GROVER
Signing Date:13.10.2023
01:50:42
                           albeit belatedly, and after extension of time was granted by the
                          Appellant/Railways.
                          14.5 The communications sent by the Respondent/Claimant to the
                          Appellant/Railways although mention power cuts, ban on digging and
                          interference in transportation on account of Commonwealth Games, 2010 as
                          reasons faced for delay in supply, the Respondent/Claimant, did not
                          specifically notify the Appellant/Railways that these events are Force
                          Majeure events.
                          14.6 There is also no discussion in the Arbitral Award of these events
                          being intimated as such to the Appellant/Railways with evidence thereof,
                          which is the pre-requisite for Clause 17 of the Contract.
                          14.7 This aspect has not been discussed in the Impugned Order either.
                          15.    Black‟s Law Dictionary defines Force Majeure as follows:
                                        "In the law of insurance, superior or irresistible force. Such clause
                                        is common in construction contracts to protect the parties in the
                                        event a part of the contract cannot be performed due to causes
                                        which are outside the control of the parties and could not be
                                        avoided by exercise of due care... Typically, such clauses
                                        specifically indicate problems beyond the reasonable control of
                                        the lessee that will excuse performance."
                                                                                      [Emphasis is ours]

                          15.1 The Supreme Court in Energy Watchdog v. Central Electricity
                          Regulatory Commission3, has, while deciding an Appeal against a judgment
                          of the Appellate Tribunal for Electricity, where a claim of a party was not
                          held to be admissible on the grounds of Force Majeure and/or change in law,
                          laid down the principles of impossibility of performance and Force Majeure,
                          to hold that the doctrine of frustration of a contract does not apply where the

                          3
                          (2017) 14 SCC 80


                          FAO (COMM) 140/2022                                                        Page 17 of 26
Signature Not Verified
Digitally Signed
By:YASHPAL GROVER
Signing Date:13.10.2023
01:50:42
                           fundamental basis for the contract remains unaltered :
                                       "34. "Force majeure" is governed by the Contract Act, 1872.
                                       Insofar as it is relatable to an express or implied clause in a
                                       contract, such as the PPAs before us, it is governed by Chapter III
                                       dealing with the contingent contracts, and more particularly,
                                       Section 32 thereof. Insofar as a force majeure event occurs
                                       dehors the contract, it is dealt with by a rule of positive law under
                                       Section 56 of the Contract Act. Sections 32 and 56 are set out
                                       herein:
                                            "32. Enforcement of contracts contingent on an event
                                            happening.--Contingent contracts to do or not to do
                                            anything if an uncertain future event happens, cannot be
                                            enforced by law unless and until that event has
                                            happened.
                                            If the event becomes impossible, such contracts become
                                            void.
                                            ***

56. Agreement to do impossible act.--An agreement to do an act impossible in itself is void.

Contract to do act afterwards becoming impossible or unlawful.--A contract to do an act which, after the contract is made, becomes impossible, or, by reason of some event which the promisor could not prevent, unlawful, becomes void when the act becomes impossible or unlawful.

Compensation for loss through non-performance of act known to be impossible or unlawful.--Where one person has promised to do something which he knew, or, with reasonable diligence, might have known, and which the promisee did not know, to be impossible or unlawful, such promisor must make compensation to such promisee for any loss which such promisee sustains through the non-performance of the promise." ........

36. The law in India has been laid down in the seminal decision of Satyabrata Ghose v. Mugneeram Bangur& Co. [Satyabrata Ghose v. Mugneeram Bangur& Co., 1954 SCR 310 : AIR 1954 SC 44] The second paragraph of Section 56 has been adverted to, and it was stated that this is exhaustive of the law as it stands in India. What was held was that the word "impossible" has not been used in the section in the sense of physical or literal impossibility. The performance of an act may not be literally impossible but it may be impracticable and useless from the point of view of the object and purpose of the parties. If an untoward

Signature Not Verified Digitally Signed By:YASHPAL GROVER Signing Date:13.10.2023 01:50:42 event or change of circumstance totally upsets the very foundation upon which the parties entered their agreement, it can be said that the promisor finds it impossible to do the act which he had promised to do. It was further held that where the Court finds that the contract itself either impliedly or expressly contains a term, according to which performance would stand discharged under certain circumstances, the dissolution of the contract would take place under the terms of the contract itself and such cases would be dealt with under Section 32 of the Act. If, however, frustration is to take place dehors the contract, it will be governed by Section 56.

15.2 It was further held in the Energy Watchdog case that merely because the performance of a Contract becomes onerous, on account of unforeseen events, it is not frustrated.

37. In Alopi Parshad & Sons Ltd. v. Union of India [Alopi Parshad & Sons Ltd. v. Union of India, (1960) 2 SCR 793 : AIR 1960 SC 588] , this Court, after setting out Section 56 of the Contract Act, held that the Act does not enable a party to a contract to ignore the express covenants thereof and to claim payment of consideration, for performance of the contract at rates different from the stipulated rates, on a vague plea of equity. Parties to an executable contract are often faced, in the course of carrying it out, with a turn of events which they did not at all anticipate, for example, a wholly abnormal rise or fall in prices which is an unexpected obstacle to execution. This does not in itself get rid of the bargain they have made. It is only when a consideration of the terms of the contract, in the light of the circumstances existing when it was made, showed that they never agreed to be bound in a fundamentally different situation which had unexpectedly emerged, that the contract ceases to bind. It was further held that the performance of a contract is never discharged merely because it may become onerous to one of the parties.

38. Similarly, in Naihati Jute Mills Ltd. v. Khyaliram Jagannath [Naihati Jute Mills Ltd. v. Khyaliram Jagannath, (1968) 1 SCR 821 : AIR 1968 SC 522] , this Court went into the English law on frustration in some detail, and then cited the celebrated judgment of Satyabrata Ghose v. Mugneeram Bangur & Co. [Satyabrata Ghose v. Mugneeram Bangur & Co., 1954 SCR 310 : AIR 1954 SC 44] Ultimately, this Court concluded that a contract is not frustrated merely because the circumstances in which it was made are altered. The courts have no general power to absolve a

Signature Not Verified Digitally Signed By:YASHPAL GROVER Signing Date:13.10.2023 01:50:42 party from the performance of its part of the contract merely because its performance has become onerous on account of an unforeseen turn of events.

39. It has also been held that applying the doctrine of frustration must always be within narrow limits. In an instructive English judgment, namely, Tsakiroglou & Co. Ltd. v. Noblee Thorl GmbH [Tsakiroglou & Co. Ltd. v. Noblee Thorl GmbH, 1962 AC 93 : (1961) 2 WLR 633 : (1961) 2 All ER 179 (HL)] , despite the closure of the Suez Canal, and despite the fact that the customary route for shipping the goods was only through the Suez Canal, it was held that the contract of sale of groundnuts in that case was not frustrated, even though it would have to be performed by an alternative mode of performance which was much more expensive, namely, that the ship would now have to go around the Cape of Good Hope, which is three times the distance from Hamburg to Port Sudan. The freight for such journey was also double. Despite this, the House of Lords held that even though the contract had become more onerous to perform, it was not fundamentally altered. Where performance is otherwise possible, it is clear that a mere rise in freight price would not allow one of the parties to say that the contract was discharged by impossibility of performance.

40. This view of the law has been echoed in Chitty on Contracts, 31st Edn. In Para 14-151 a rise in cost or expense has been stated not to frustrate a contract. Similarly, in Treitel on Frustration and Force Majeure, 3rd Edn., the learned author has opined, at Para 12-034, that the cases provide many illustrations of the principle that a force majeure clause will not normally be construed to apply where the contract provides for an alternative mode of performance. It is clear that a more onerous method of performance by itself would not amount to a frustrating event. The same learned author also states that a mere rise in price rendering the contract more expensive to perform does not constitute frustration. (See Para 15-158.)"

[Emphasis is ours]

15.3 The Sole Arbitrator held that the power cuts in Haryana and Himachal Pradesh, the State Government ban of digging in the Aravalli Hills and the Commonwealth Games, disturbing transportation would constitute a Force Majeure condition under Clause 17 of the Contract. 15.4 As discussed earlier, the Respondent/Claimant did not terminate the Contract on account of Force Majeure, but delayed performance thereof.

Signature Not Verified Digitally Signed By:YASHPAL GROVER Signing Date:13.10.2023 01:50:42 The Sole Arbitrator has concluded that the delay in performance was not on account of any failure of the Respondent/Claimant but due to factors beyond the control of the Respondent/Claimant.

15.5 While we agree that these events could not have reasonably been predicted by the Respondent/Claimant, and would have made performance on time difficult, we are unable to agree on the interpretation of the Force Majeure clause given by the Sole Arbitrator, that power cuts, State Government ban on digging and the disturbance in transportation, would qualify as Force Majeure events.

15.6 Force Majeure as defined in Clause 17 of the Contract states war, insurrection and acts of governmental authorities. These would not include power cuts or shortage of materials on account of Commonwealth Games 2010 or ban on digging in the Aravalli hills. 15.7 In any event, power cuts could not be a cause for frustration of the Contract as the tender document executed between the parties admittedly sets forth that regular power cuts were to be taken into account by bidders, i.e., the Respondent/Claimant herein. The ban on digging in Haryana was imposed much prior to the date of the Contract4. Further, as discussed above, the steps of intimation to the Appellant/Railways within a week, of the occurrence of a Force Majeure event with evidence thereof, was not followed by the Respondent/Claimant.

16. In exercise of powers under Section 37 of the Act, the scope of interference of the Courts is narrow. The law is no longer res integra. Where the Arbitrator has assessed the evidence and material placed before him while considering the objections to the Award, the Court does not sit as a

See: M.C. Mehta v. Union of India, (2009) 6 SCC 142; judgment dated 08.05.2009.

Signature Not Verified Digitally Signed By:YASHPAL GROVER Signing Date:13.10.2023 01:50:42 Court of Appeal or re-appreciate and re-assess the evidence. Unless there is a patent illegality or perversity, interference by the Court is not warranted. Merely because another view is possible, the Court will not interdict the Award. The Courts should only interfere if such Award "portrays perversity unpardonable" under Section 34 of the Act. Reference is made to the Supreme Court‟s decision in the Dyna Technologies Pvt. Ltd. v. Crompton Greaves Ltd.5 16.1 Mere erroneous interpretation of a clause by a Sole Arbitrator does not call for an interference of the Award on the ground of patent illegality. The interpretation should be as such which goes to the root of the matter. 16.2 The Courts are required to show restraint while examining Arbitral Awards which have examined the evidence and documents placed before it and have interpreted the Contract in a reasonable manner, lest such interference defeats the very object of the Act. 16.3 The Supreme Court in Delhi Airport Metro Express (P) Ltd. v. DMRC6, has held that the Arbitral Tribunal holds the final authority in both facts and law and contravention of law not linked to public policy is beyond the scope of judicial interference under "patent illegality".:

"28. This Court has in several other judgments interpreted Section 34 of the 1996 Act to stress on the restraint to be shown by Courts while examining the validity of the arbitral awards. The limited grounds available to Courts for annulment of arbitral awards are well known to legally trained minds. However, the difficulty arises in applying the well-established principles for interference to the facts of each case that come up before the Courts. There is a disturbing tendency of Courts setting aside arbitral awards, after dissecting and reassessing factual aspects of the cases to come to a conclusion that the award needs intervention and thereafter,

2019 SCC Online SC 1656

(2022) 1 SCC 131

Signature Not Verified Digitally Signed By:YASHPAL GROVER Signing Date:13.10.2023 01:50:42 dubbing the award to be vitiated by either perversity or patent illegality, apart from the other grounds available for annulment of the award. This approach would lead to corrosion of the object of the 1996 Act and the endeavours made to preserve this object, which is minimal judicial interference with arbitral awards. That apart, several judicial pronouncements of this Court would become a dead letter if arbitral awards are set aside by categorising them as perverse or patently illegal without appreciating the contours of the said expressions.

29.Patent illegality should be illegality which goes to the root of the matter. In other words, every error of law committed by the Arbitral Tribunal would not fall within the expression "patent illegality". Likewise, erroneous application of law cannot be categorised as patent illegality. In addition, contravention of law not linked to public policy or public interest is beyond the scope of the expression "patent illegality". What is prohibited is for Courts to reappreciate evidence to conclude that the award suffers from patent illegality appearing on the face of the award, as Courts do not sit in appeal against the arbitral award. The permissible grounds for interference with a domestic award under Section 34(2-A) on the ground of patent illegality is when the arbitrator takes a view which is not even a possible one, or interprets a clause in the contract in such a manner which no fair-minded or reasonable person would, or if the arbitrator commits an error of jurisdiction by wandering outside the contract and dealing with matters not allotted to them. An arbitral award stating no reasons for its findings would make itself susceptible to challenge on this account. The conclusions of the arbitrator which are based on no evidence or have been arrived at by ignoring vital evidence are perverse and can be set aside on the ground of patent illegality. Also, consideration of documents which are not supplied to the other party is a facet of perversity falling within the expression "patent illegality"."

[Emphasis is ours]

16.4 Interpretation of a contract is a matter for an Arbitrator to determine.

Even if such interpretation gives rise to an erroneous application of law, the Courts will generally not interfere, unless the error is palpably perverse or illegal and goes to the root of the matter. It is therefore to be seen whether the interpretation of the Force Majeure clause is such that a fair minded or reasonable person could conclude as well, or if the interpretation by the Sole

Signature Not Verified Digitally Signed By:YASHPAL GROVER Signing Date:13.10.2023 01:50:42 Arbitrator is patently illegal.

17. The Arbitral Award has interpreted the Contract and its provisions including Force Majeure and has correctly found that the delay and the defaults were on account of the Appellant/Railways. The Sole Arbitrator has thus held that deductions made by the Respondent/Claimants on account of penalty, liquidated damages and non-grant of price escalation were unjustified. The claim of loss of profits of the Respondent/Claimants was rejected as not proved, since no evidence was lead by the Appellant/Railways. The Counter-claims of Appellant/Railways were based on the Claims. Since Claims (i) and (ii) of the Respondent/Claimants were allowed, Counter-claims (i) and (ii) were automatically rejected. Thus, Counter-claim (iii) of the Respondent/Claimants being costs was also rejected.

17.1 The interpretation given by the Sole Arbitrator and the conclusions reached are a reasonable and fair interpretation of the Contract, based on the evidence produced and thus would not fall in the scope of patent illegality as has been interpreted by the Courts.

17.2 The Sole Arbitrator and the District Judge have wrongly interpreted that the Force Majeure Clause. However, this interpretation at best this could be an erroneous interpretation of the clause, which would not qualify as patent illegality. This interpretation also does not go to the root of the matter as in the opinion of this Court, the final conclusions reached by the Sole Arbitrator are not erroneous.

18. The Appeal is accordingly dismissed and CM APPL.41855/2022 is also dismissed. There shall, however, be no Orders as to costs. CM APPL. 41856/2022[Application seeking condonation of delay]

Signature Not Verified Digitally Signed By:YASHPAL GROVER Signing Date:13.10.2023 01:50:42

19. This is an Application seeking condonation of delay filed by the Appellant/Railway seeking condonation of delay of 65 days in filing of the present Appeal. The reasons as set forth in the Application is that the delay was caused due to time taken in departmental procedures obtaining legal opinions from Railway Advocates and other legal advisors and Ministry of Legal Affairs, Law and Justice and Ministry of Railways. 19.1 Reliance has been placed by the Appellant on the Judgment of the Supreme Court in the In Re suo moto W.P.(C) 3/20207, to submit that for the purposes of limitation, the period up to 28.02.2022 has been excluded by the Supreme Court and a 90-day extension is granted from 01.03.2022 for limitation, which would expire on 29.05.2022.

20. An Appeal under Section 37 of the Act must be filed within a period of 60 days in terms of the provisions of Section 13(1A) of the Commercial Courts, Commercial Division and Commercial Appellate Division of High Courts Act, 2015 [hereinafter referred to as "Commercial Courts Act"]. 20.1 The record shows that the present Appeal was filed on 19.09.2022. Thus, even the 90 days extension period as provided by the Supreme Court in the In Re Suo Moto case has been breached by the Appellant/Railways. 20.2 Learned Counsel for the Appellant/Railways contends that the delay in filing of the present Appeal, neither unintentional nor willful but due to the reasons as set forth in the present Application. Reliance is placed on a tabular chart filed by the Appellant/Railways setting forth the movement of the „file‟ between various governmental bodies during the period from 07.02.2022 and 29.06.2022.

21. The Supreme Court in the case of State of Maharashtra v. Borse

(2022) 3 SCC 117

Signature Not Verified Digitally Signed By:YASHPAL GROVER Signing Date:13.10.2023 01:50:42 Bros. Engineers & Contractors (P) Ltd.8and Basawaraj V. Land Acquisition Officer9, held that condonation of delay in filing an Appeal under Section 37 of the Act, beyond the period provided in the Act, may be granted only upon „sufficient cause‟ shown by the party.

22. The Supreme Court in State of M.P. v. Bherulal10, while relying on the judgment of the Supreme Court in Postmaster General and Others. Vs. Living Media India Limited and Another11has categorically held that the law of limitation binds everybody including the Government and there is no separate statute of limitation provided for governmental Appeals. The Postmaster General case further states that delay cannot be mechanically condoned, in the absence of plausible and acceptable explanation, merely because the Government or a wing of the Government is a party.

23. However, in view of the fact that the Appeal has been dismissed, there is no requirement to adjudicate the present Application. Hence, the Application is closed.

TARA VITASTA GANJU, J (JUDGE)

RAJIV SHAKDHER, J (JUDGE)

OCTOBER 11, 2023 SA/ ha

(2021) 6 SCC 460

(2013) 14 SCC 81

(2020) 10 SCC 654

(2012) 3 SCC 563

Signature Not Verified Digitally Signed By:YASHPAL GROVER Signing Date:13.10.2023 01:50:42

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter