Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

National Highway Authority Of ... vs Continental Engineering ...
2022 Latest Caselaw 2411 Del

Citation : 2022 Latest Caselaw 2411 Del
Judgement Date : 6 October, 2022

Delhi High Court
National Highway Authority Of ... vs Continental Engineering ... on 6 October, 2022
                  $~24
                  *    IN THE HIGH COURT OF DELHI AT NEW DELHI

                                                   Date of Decision: 06th October, 2022

                  +        O.M.P. (COMM) 426/2018 & I.A. 13900/2018

                           NATIONAL HIGHWAY AUTHORITY OF INDIA
                                                                 ..... Petitioner
                                        Through: Ms. Nivedita Nair and Ms.
                                                 Asha Gopalan Nair, Advocates.

                                                   versus

                           CONTINENTAL ENGINEERING

                           CORPORATION (CEC)                         ..... Respondent
                                        Through:        Dr. Amit George, Mr. Kunal
                                                        Kher, Mr. Amol Acharya and
                                                        Mr.   Rayadurgam       Bharat,
                                                        Advocates.

                  CORAM:
                  HON'BLE MR. JUSTICE PRATEEK JALAN

                  PRATEEK JALAN, J. (ORAL)

%

1. The present petition under Section 34 of the Arbitration and Conciliation Act, 1996, [hereinafter, "the Act"] is directed against an arbitral award dated 08.06.2018 by which a three member tribunal adjudicated disputes arising out of a contract dated 20.02.2007 for work of "Rehabilitation and upgrading of existing 2-lane road to 4- lane divided carriageway configuration from km 293.400 to km 336.000 Hyderabad-Bangalore section of NH-7 in the State of Andhra

Signature Not Verified Digitally signed By:SHITU NAGPAL Signing Date:10.10.2022

Pradesh on North-South Corridor, Contract Package No. /ADB-II/C- 12" [hereinafter, "the Contract"].

2. The challenge of the petitioner - National Highways Authority of India [hereinafter, "NHAI"] is restricted to two claims which were awarded by the Tribunal against it:

a. Claim No.1: Payment of 150 mm thick embankment quantity under Bill of Quantities [hereinafter, "BOQ"] item No. 2.04.

b. Claim No. 3: Non-payment of BOQ item No. 5.15 for providing and laying M-15 grade concrete in pipe bedding.

3. Ms. Nivedita Nair, learned counsel for the NHAI, submits that the award on both these claims is contrary to the terms of the Contract, as the activities for which the award has been made were already covered under other items of the BOQ.

4. As far as claim No. 1 is concerned, Ms. Nair contends that, since the respondent has already been paid for "clearing and grubbing" under BOQ item No. 1.01, the grant of the claim for embankment under BOQ item No. 2.04 was not permissible. According to NHAI, "clearing and grubbing" activity includes backfilling, and grant of both items of the BOQ amounts to double recovery on the part of the respondent.

5. As far as claim No. 3 is concerned, the principal submission of Ms. Nair is that no amount was liable to be awarded under BOQ item No. 5.15 as the work to be done was covered under BOQ item No. 5.14. She draws my attention to two items of the BOQ [at page 424 of the petitioner's documents] which are listed as follows:-

Signature Not Verified Digitally signed By:SHITU NAGPAL Signing Date:10.10.2022

Item Description Unit Estimated Unit Rate (Rs.) Amount Rs. No.

                                                            Quantity     in        In words (in figures)
                                                                         figures

                  5.14      Providing laying
                            and jointing RCC
                            NP-4 Pipe (as per
                            IS:458-2002) for
                            culverts including
                            testing complete
                            as per drawings
                            and      Technical
                            Specifications
                            Section 2900

                                 a) Dia          1000 m     1491         6100/-    Six      9095100/-
                                    mm                                             thousand
                                                                                   one
                                                                                   hundred
                                                                                   only

                                 b) Dia          1200 m     1389         8410/-    Eight    11681490/-
                                    mm                                             thousand
                                                                                   four
                                                                                   hundred
                                                                                   ten only

                  5.15      Providing     and cum           2054         2440/-    Two      5011760/-
                            laying M 15 grade                                      thousand
                            concrete in pipe                                       four
                            bedding as per                                         hundred
                            drawing       and                                      fourty
                            Technical

Signature Not Verified
Digitally signed By:SHITU
NAGPAL
Signing Date:10.10.2022

                             Specifications                                         only
                            Section 2900


6. According to Ms. Nair, by an amendment to the technical specifications, the following provision was incorporated in Clause 2911 of the amended technical specifications: -

"Clause 2911 Rate

The first paragraph under this Sub Clause shall be read as :

The Contract unit rate for the pipes shall include the cost of pipes including loading, unloading, hauling, storing, laying in position, jointing and cement concrete bedding below the pipe complete and all incidental costs to complete the work as per these specifications."

7. Ms. Nair submits that the award of the respondent's claim under BOQ item No. 5.15 separately by the arbitral tribunal is directly in the teeth of Clause 2911 of the amended technical specifications which provides that the contract unit rate of the pipes shall inter alia, include the cement concrete bedding below the pipe.

8. Dr. Amit George, learned counsel for the respondent, at the very outset, submits that the aforesaid grounds of challenge are not available in the present case as the respondent is an entity incorporated in Taiwan, and the award under challenge is thus rendered in an Signature Not Verified Digitally signed By:SHITU NAGPAL Signing Date:10.10.2022

"international commercial arbitration", within the meaning of Section 2(1)(f) of the Act. In such a case, Dr. George submits that the grounds of challenge are limited to those specified in Section 34(2) of the Act, and the ground of patent illegality provided in Section 34(2A)1 would not be available to the NHAI. In support of this contention, Dr. George cites a judgment of a Coordinate Bench of this Court between the same parties in National Highways Authority of India vs. Continental Engineering Corporation (CEC)2.

9. Without prejudice to the aforesaid contention, Dr. George submits that the conclusion of the arbitral tribunal on claim No. 1 is based entirely on the evidence and does not warrant interference under any ground specified in Section 34 of the Act. He draws my attention to paragraphs 1.21 and 1.22 of the award which read as follows: -

"1.21 During 7th hearing held on 12.12.2017, the respondent clarified that as per records, the measurements of the embankment carried out under BOQ item No. 2.04 have been taken by the Engineer from OGL obtained after the 'clearing and grubbing' operation and that the deduction of 150mm thickness was made from the measurements of 1st layer of embankment executed above OGL and that no excavation was carried out after 'clearing and grubbing' operation.

1.22 On the basis unassailable evidence in paras above, it is held that the 1st layer is a part of the embankment constructed under BOQ item No. 2.04, as neither excavation upto a maximum depth of 150 mm after 'clearing and grubbing' was

Inserted by the Arbitration and Conciliation (Amendment) Act, 2015 [w.e.f. 23.10.2015].

Judgment dated 13.04.2022 in O.M.P.(COMM) 422/2019.

Signature Not Verified Digitally signed By:SHITU NAGPAL Signing Date:10.10.2022

required to be done under item No. 1.01 (there being no instruction of Engineer on record to do so) nor was it done as admitted by the respondent in 7th hearing) and as a consequence no back filling was involved. Accordingly, it is held that entire work done is the embankment above OGL ·for which· the claimant is entitled to be paid under BOQ item No. 2.04 without making any deduction. Thus the claim is held as tenable."3

Additionally, Dr. George cites the judgment of the Division Bench of this Court in National Highways Authority of India vs. Hindustan Construction Company Ltd.4 wherein a claim on a similar ground was upheld by the Division Bench.

10. On claim No. 3, Dr. George submits that the arguments raised by the NHAI before this Court have been duly considered in paragraphs 3.30 and 3.31 of the award which read as follows: -

"3.30 The respondent while framing the Contract/BOQ and inviting bids sought for separate rates for items BOQ 5.14 & 5.15. The unit and quantities for both these items are different. The claimant submitted separate rates for BOQ items 5.14 & 5.15 and the respondent accepted the same and thus the Contract Agreement was concluded. Thus, both BOQ item 5.14 & 5.15 are clear in terms of quantity as well as rates.

3.31 Supplementary Technical Specifications Clause 2910 & Clause 2911 at page 240 of Contract Agreement are conflicting. In Clause 2910, it is laid down, that, cement concrete bedding shall be measured separately, meaning

Emphasis supplied.

2012 SCC OnLine Del 5832 [paragraphs 13 and 14].

Signature Not Verified Digitally signed By:SHITU NAGPAL Signing Date:10.10.2022

thereby that, if it is so, then it is meant for payment purposes only & there cannot be any other purpose for this measurement."

11. He submits that items 5.14 and 5.15 of BOQ are distinct and the rates quoted by the bidders in each case is also distinct. He relies upon the Division Bench judgment of this Court in National Highways Authority of India vs. M/s Lanco Infractech Ltd.5 to submit that the arbitral tribunal has correctly held that any ambiguity in the contractual terms must be resolved against the draftsman.

12. In rejoinder, Ms. Nair distinguishes the Division Bench judgment in Hindustan Construction Company Ltd.6, on the ground that in the said judgment it was found that no backfilling was carried out as a part of "clearing and grubbing" activity. She contends that, on the contrary, backfilling was an important component of the activity to be carried out in the present case. Although it has been submitted by Ms. Nair that this issue is pending before the Supreme Court in a batch of petitions, including a challenge to the judgment of the Division Bench in Hindustan Construction Company Ltd., it is not suggested that the judgment has been stayed by the Supreme Court.

13. Having heard learned counsel for the parties, I am of the view that no ground for interference with the impugned award is made out. At the outset, it is not disputed that the present award is rendered in an international commercial arbitration, within the meaning of Section 2(1)(f) of the Act. The ground of patent illegality provided in Section

Judgment dated 07.03.2014 in FAO(OS) 34/2006.

Supra (note 4).

Signature Not Verified Digitally signed By:SHITU NAGPAL Signing Date:10.10.2022

34(2A) is, therefore, not available to the NHAI, and interference can only be justified if the case falls within the grounds specified in Section 34(2). Of those grounds, Ms. Nair only contended that the award is in conflict with the public policy of India, as provided in Section 34(2)(b)(ii) of the Act.

14. The width of the public policy ground is clarified in the two explanations to Section 34(2), which read as follows: -

"34. Application for setting aside arbitral award:

xxxx xxxx xxxx (2) An arbitral award may be set aside by the Court only if--

xxxx xxxx xxxx [Explanation 1.--For the avoidance of any doubt, it is clarified that an award is in conflict with the public policy of India, only if,-- (i) the making of the award was induced or affected by fraud or corruption or was in violation of section 75 or section 81; or

(ii) it is in contravention with the fundamental policy of Indian law; or

(iii) it is in conflict with the most basic notions of morality or justice.

Explanation 2.--For the avoidance of doubt, the test as to whether there is a contravention with the fundamental policy of Indian law shall not entail a review on the merits of the dispute.]7

Emphasis supplied.

Signature Not Verified Digitally signed By:SHITU NAGPAL Signing Date:10.10.2022

15. The Supreme Court has considered the question in several judgments, including its judgment in Ssangyong Engineering Construction & Co Ltd. vs. National Highways Authority of India (NHAI)8. Relying upon Associate Builders vs. DDA9, the Court has explained that the expression "public policy of India", is now restricted to the fundamental policy of Indian law, as understood in paragraphs 18 and 27 of Associate Builders, or to basic notions of justice or morality as understood in paragraphs 36 to 39 of Associate Builders.

16. The Court concluded as follows: -

"76. However, when it comes to the public policy of India, argument based upon "most basic notions of justice", it is clear that this ground can be attracted only in very exceptional circumstances when the conscience of the Court is shocked by infraction of fundamental notions or principles of justice.

***** ***** ***** However, we repeat that this ground is available only in very exceptional circumstances, such as the fact situation in the present case. Under no circumstance can any court interfere with an arbitral award on the ground that justice has not been done in the opinion of the Court. That would be an entry into the merits of the dispute which, as we have seen, is contrary to the ethos of Section 34 of the 1996 Act, as has been noted earlier in this judgment."10

17. The relevant extracts of Associate Builders11, referred to in Ssangyong, are set out below:-

(2019) 15 SCC 131.

(2015) 3 SCC 49.

Emphasis supplied.

Supra (note 9).

Signature Not Verified Digitally signed By:SHITU NAGPAL Signing Date:10.10.2022

"18. In Renusagar Power Co. Ltd. v. General Electric Co.12, the Supreme Court construed Section 7(1)(b)(ii) of the Foreign Awards (Recognition and Enforcement) Act, 1961:

"7. Conditions for enforcement of foreign awards.-- (1) A foreign award may not be enforced under this Act--

***

(b) if the Court dealing with the case is satisfied that--

***

(ii) the enforcement of the award will be contrary to the public policy."

In construing the expression "public policy" in the context of a foreign award, the Court held that an award contrary to

(i) The fundamental policy of Indian law,

(ii) The interest of India,

(iii) Justice or morality, would be set aside on the ground that it would be contrary to the public policy of India. It went on further to hold that a contravention of the provisions of the Foreign Exchange Regulation Act would be contrary to the public policy of India in that the statute is enacted for the national economic interest to ensure that the nation does not lose foreign exchange which is essential for the economic survival of the nation (see SCC p. 685, para

75). Equally, disregarding orders passed by the superior courts in India could also be a contravention of the fundamental policy of Indian law, but the recovery of compound interest on interest, being contrary to statute only, would not contravene any fundamental policy of Indian law (see SCC pp. 689 & 693, paras 85 & 95).

xxxx xxxx xxxx

1994 Supp (1) SCC 644.

Signature Not Verified Digitally signed By:SHITU NAGPAL Signing Date:10.10.2022

Fundamental Policy of Indian Law

27. Coming to each of the heads contained in Saw Pipes judgment13, we will first deal with the head "fundamental policy of Indian law". It has already been seen from Renusagar14 judgment that violation of the Foreign Exchange Act and disregarding orders of superior courts in India would be regarded as being contrary to the fundamental policy of Indian law. To this it could be added that the binding effect of the judgment of a superior court being disregarded would be equally violative of the fundamental policy of Indian law.

                                           xxxx         xxxx         xxxx
                             Justice

36. The third ground of public policy is, if an award is against justice or morality. These are two different concepts in law. An award can be said to be against justice only when it shocks the conscience of the court. An illustration of this can be given. A claimant is content with restricting his claim, let us say to Rs 30 lakhs in a statement of claim before the arbitrator and at no point does he seek to claim anything more. The arbitral award ultimately awards him Rs 45 lakhs without any acceptable reason or justification. Obviously, this would shock the conscience of the court and the arbitral award would be liable to be set aside on the ground that it is contrary to "justice".

Morality

37. The other ground is of "morality". Just as the expression "public policy" also occurs in Section 23 of the Contract Act, 1872 so does the expression "morality". Two illustrations to the said section are interesting for they explain to us the scope of the expression "morality":

xxxx xxxx xxxx "

Oil and Natural Gas Corporation Ltd. vs. Saw Pipes Ltd. (2003) 5 SCC 705.

Supra (note 12).

Signature Not Verified Digitally signed By:SHITU NAGPAL Signing Date:10.10.2022

18. The challenge to the award does not, in my view, fall within the narrow scope outlined above, either with respect to claim No.1 or with respect to claim No.3.

19. As far as claim No. 1 is concerned, the Division Bench judgment in Hindustan Construction Company Ltd.15 rejected the challenge of NHAI, even on the ground of patent illegality in the award. This case is on the same footing. The distinction sought to be urged by Ms. Nair i.e., with regard to backfilling having been done under BOQ item No. 1.01 is, in my view, unsustainable as the arbitral tribunal, in paragraph 1.22 of the award (extracted above), has come to a conclusion on evidence that no backfilling was involved. Even when the ground of patent illegality is available, findings of the arbitral tribunal on appreciation of evidence are not lightly interfered with, unless shown to be completely perverse or arbitrary. No such ground has been urged in this case.

20. I do not consider it necessary to defer the decision in this case until the Supreme Court has disposed of the appeal from the judgment in Hindustan Construction Company Ltd. The said judgment has not been stayed by the Supreme Court. Further, the scope of interference in the present case is even narrower than the grounds available therein. If such a challenge does not fall within the scope of patent illegality, it would a fortiori fall outside the scope of public policy. There is no element of the award in this respect which shocks the conscience of the Court, as required for the public policy ground to be invoked.

21. As far as claim No.3 is concerned, here also, in paragraphs 3.30

Supra (note 4) [Paragraphs 12 to 14].

Signature Not Verified Digitally signed By:SHITU NAGPAL Signing Date:10.10.2022

and 3.31 cited above, the arbitral tribunal has interpreted the contract to hold that the rates in BOQ item Nos. 5.14 and 5.15 were not overlapping and were to be paid separately. In reaching this conclusion, the tribunal has considered clause 2911 of the amended technical specifications also. As noted by the arbitral tribunal, the BOQ quoting separate public rates under item Nos. 5.14 and 5.15 was duly accepted by the NHAI.

22. The interpretation of the contract by the arbitral tribunal is not open to challenge under Section 34 of the Act even on the ground of patent illegality unless it is found to be an interpretation which no reasonable person could adopt. I do not find the award vitiated by any such interpretation. Further, as noted above, even this ground is not available to NHAI in the case of an international commercial arbitration.

23. On both claims, therefore, I find that NHAI's challenge does not fall within the scope of the public policy challenge under Section 34(2)(b)(ii) of the Act, and in effect requires the Court to undertake a merits review, which is expressly barred by Explanation II to Section 34(2).

24. For the reasons aforesaid, the petition is dismissed.

PRATEEK JALAN, J OCTOBER 6, 2022 'vp'/

Signature Not Verified Digitally signed By:SHITU NAGPAL Signing Date:10.10.2022

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter