M/S Sudhir Power Projects Ltd vs M/S Unipower Projects Pvt. Ltd. on 30 March, 2022
                                      $~4
                                      *     IN THE HIGH COURT OF DELHI AT NEW DELHI
                                      %                          Judgment delivered on: 30th March, 2022

                                      +     ARB.P. 1199/2021
                                      M/S SUDHIR POWER PROJECTS LTD                         ..... Petitioner
                                                                 versus

                                      M/S UNIPOWER PROJECTS PVT. LTD.                       ..... Respondent
                                      Advocates who appeared in this case:
                                      For the Appellants: Mr. Manish Kumar, Mr. Piyush Kaushik, Mr. Nakul Jain
                                                          and Ms. Hyyat Ahluwalia, Advocates

                                      For the Respondent: Mr. Gurpreet Singh Sachdeva, Advocate

                                      CORAM:-
                                      HON'BLE MR. JUSTICE SANJEEV SACHDEVA

                                                                   JUDGMENT

SANJEEV SACHDEVA, J

1. Petitioner seeks appointment of an Arbitrator under Section 11(5) of the Arbitration & Conciliation Act, 1996.

2. It is contended that the parties had entered into an agreement and a work order was placed on the respondent dated 11.06.2021 which contains an arbitration clause.

3. The Arbitration Clause 19 reads as under: -

Digitally Signed Signature Not Verified By:JUSTICE SANJEEV Digital Signed By:KUNAL SACHDEVA MAGGU Signing Date:30.03.2022 Signing Date:31.03.2022 12:06:22 21:39 This file is digitally signed by PS to HMJ Sanjeev Sachdeva.

"19. Dispute Resolution / Arbitration & jurisdiction: Any dispute or difference whatsoever arising betweenthe parties out of or relating to the construction, meaning, scope operation or effect of this contract or the validity or the breach thereof shall be settled by arbitration in accordance with Arbitration and Conciliation Act, 1996 and the award made in pursuance thereof shall be binding on the parties. The dispute shall bereferred to the arbitration of Sole Arbitrator to be appointed by CMD/MD of SPPL, whereas Seat and venue of the arbitration shall be New Delhi/Gurugram and the proceedings shall be undertaken in English."

4. Learned counsel for the petitioner submits that the registered office of both petitioner as well as respondent is in Delhi and accordingly petitioner has exercised the option to approach the Courts at Delhi.

5. Learned counsel for the petitioner submits that earlier a Purchase Order was sent by email dated 11.06.2021 and all the terms and conditions were contained in the Purchase Order and Respondents were requested to accept the same. However, the Respondent by their email dated 12.06.2021 raised certain issues with regard to the terms of payment.

6. Subsequently a revised Purchase Order was sent on 17.06.2021 revising the terms of payment. Clause 19 of both the Purchase Orders

Digitally Signed Signature Not Verified By:JUSTICE SANJEEV Digital Signed By:KUNAL SACHDEVA MAGGU Signing Date:30.03.2022 Signing Date:31.03.2022 12:06:22 21:39 This file is digitally signed by PS to HMJ Sanjeev Sachdeva.

remained the same. It is stated that by e-mail dated 17.06.2021, respondent accepted the Purchase Order with the terms mentioned therein.

7. Only objection raised by the respondent in these proceedings to the appointment of an Arbitrator is that is there is no written agreement between the parties. The email by which the Purchase Order and the terms therein have been accepted are not denied.

8. Learned counsel for the respondent further submits that the purchase of order referred to by the petitioner is merely a work order and not a purchase order.

9. Perusal of the Purchase Order dated 11.06.2021 shows that the same bears a heading "work order/contract". The email with which the same has been sent mentions the same as a Purchase Order. However, nothing really turns on the description of the document as the said document contains several terms and conditions and one of the terms being clause 19 containing the Arbitration Clause extracted hereinabove.

10. Further the petitioner has also placed on record the communication dated 13.09.2021 sent by the respondent acknowledging the work order dated 11.06.2021 referred to herein above.




                                                                                            Digitally Signed
Signature Not Verified                                                                      By:JUSTICE SANJEEV
Digital Signed By:KUNAL                                                                     SACHDEVA
MAGGU                                                                                       Signing Date:30.03.2022
Signing Date:31.03.2022 12:06:22                                                            21:39
This file is digitally signed by PS
to HMJ Sanjeev Sachdeva.

11. Section 7 of the Arbitration and Conciliation Act, 1996, inter- alia, stipulates that an arbitration agreement is in writing, if it is contained in exchange of letters, italics telegrams or other means of telecommunications including communication through electronic means.

12. The very fact that petitioner had sent a Purchase Order contacting the terms and conditions of the contract requesting the respondent to accept the same and the said email and Purchase Order is admittedly received by the respondent and respondent by their email have not only acknowledged the receipt but specifically stated that they accept the PO along with its terms.

13. Said exchange of correspondence clearly satisfies the requirement of a written agreement between the parties as envisaged in Section 7 (4) (b) of the Arbitration Act. None of the emails or the communication placed on record by the petitioner are denied by the respondent.

14. In view of the above, this petition is allowed.

15. The disputes are referred to the Delhi International ArbitrationCentre (DIAC), which would appoint an arbitrator to arbitrate the disputes. The arbitration shall take place under the aegis of the DIAC in accordance with its rules and regulations.




                                                                                               Digitally Signed
Signature Not Verified                                                                         By:JUSTICE SANJEEV
Digital Signed By:KUNAL                                                                        SACHDEVA
MAGGU                                                                                          Signing Date:30.03.2022
Signing Date:31.03.2022 12:06:22                                                               21:39
This file is digitally signed by PS
to HMJ Sanjeev Sachdeva.

16. The arbitrator would be entitled to charge fees in accordance with the schedule of fee stipulated by the DIAC.

17. The arbitrator shall furnish the requisite disclosure under section 12(2) of the Arbitration and Conciliation Act, 1996 within one week of entering reference.

18. The petition is disposed of in the above terms.

SANJEEV SACHDEVA, J MARCH 30, 2022 'rs'

Digitally Signed Signature Not Verified By:JUSTICE SANJEEV Digital Signed By:KUNAL SACHDEVA MAGGU Signing Date:30.03.2022 Signing Date:31.03.2022 12:06:22 21:39 This file is digitally signed by PS to HMJ Sanjeev Sachdeva.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter