Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

National Highways Authority Of ... vs M/S Uem-Essar Joint Venture
2022 Latest Caselaw 817 Del

Citation : 2022 Latest Caselaw 817 Del
Judgement Date : 22 March, 2022

Delhi High Court
National Highways Authority Of ... vs M/S Uem-Essar Joint Venture on 22 March, 2022
                                IN THE HIGH COURT OF DELHI AT NEW DELHI

                          %                               Judgment delivered on: 22.03.2022
                          +        O.M.P. (COMM) 18/2021, & I.A. Nos. 655/2021 & 659/2021

                          NATIONAL HIGHWAYS AUTHORITY
                          OF INDIA                                                 ..... Petitioner
                                                           versus
                          M/S UEM - ESSAR JOINT VENTURE                          ..... Respondent
                          Advocates who appeared in this case:
                          For the Petitioner        : Mr Manish K. Bishnoi, Ms Pallavi Singha
                                                    : and Mr Anish Chawla, Advocates.

                          For the Respondent        : Mr Vivek Chib, Senior Advocate with Mr
                                                    : Asif Ahmed, Mr Prateek Dhanda and
                                                    : Ms Unnati Jhunjhunwala, Advocates.
                          CORAM
                          HON'BLE MR JUSTICE VIBHU BAKHRU
                                                       JUDGMENT

VIBHU BAKHRU, J

1. The National Highway Authority of India (hereinafter 'NHAI') has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter 'the A&C Act') impugning an arbitral award dated 01.09.2020 (hereinafter 'the impugned award') passed by an Arbitral Tribunal comprising of three members [Justice (Retd.) Iqbal Ahmed Ansari, Shri A.B. Desai, Chief Engineer and Justice (Retd.) C.K. Thakkar as the Presiding Arbitrator].

2. The impugned award was rendered in the context of disputes that had arisen between the parties in connection with the Agreement dated 16.01.2002. The principal dispute between the parties was

Signature Not Verified Digitally Signed

Signing Date:22.03.2022 regarding the respondent's claim for payment of a sum of ₹4,95,02,980/- for the works executed by it and certified by the Engineer appointed by NHAI. The majority of the Arbitrators [Shri A.B. Desai and Justice (Retd.) C.K. Thakkar] allowed the aforesaid claim, in favour of the respondent. The said learned Arbitrators also awarded interest in favour of the petitioner; however, there is a difference of opinion as to the date from which the said interest would run. Justice (Retd.) Iqbal Ahmed Ansari entered a dissenting opinion.

3. NHAI has assailed the impugned award (by majority) on the ground that it is vitiated by patent illegality on the face of the award. According to NHAI, the claims raised by the respondent were barred by limitation. Thus, neither the principal claim for payment of the work done nor the claim for interest on the said amount, could be entertained.

4. Briefly stated, the facts necessary to address the aforesaid controversy, are as under:-

4.1 On 18.09.2001, NHAI had invited tenders for execution of the work relating to "Western Transport Corridor, Tumkur- Haveri Section of NH4 - Rehabilitation and upgrading of Sira-Chitrdurga Section (Km. 122.3 to Km. 189) in the State of Karnataka - Package 2" (hereinafter 'the Project'), on the terms and conditions stipulated thereon.

4.2 The respondent had submitted its bid and the contract for executing the Project works for a consideration of ₹253,24,41,361/- was awarded to the respondent in terms of the Letter of Acceptance dated

Signature Not Verified Digitally Signed

Signing Date:22.03.2022 28.11.2001 (hereinafter the 'LoA'). Thereafter, on 16.01.2002, the parties entered into a formal agreement (hereinafter 'the Contract').

4.3 In terms of the Contract, the execution of the works was to commence on or before 01.03.2002 and completed within a period of thirty months from the commencement date. Thus, the entire works were required to be completed on or before 31.08.2004. The execution of the works was delayed and the respondent sought Extension of Time (hereinafter 'EOT') for completion of the works on successive occasions, which were approved by NHAI.

4.4 There is some controversy regarding the approvals of the EOT. According to NHAI, it had agreed to EOT on four occasions (that is, till the 4th EOT) but had not approved the subsequent three requests for EOT (that are, requests for the 5th, 6th and 7th EOT).

4.5 NHAI claims that the said works could not be completed within the stipulated period of time due to delay on the part of the respondent; the said works were completed by 26.03.2008. Thereafter, the Engineer (appointed by NHAI) issued the Taking Over Certificate (hereinafter 'TOC'). And, on 11.01.2011, the Engineer issued the Defect Liability Certificate (hereinafter 'DLC') with effect from 31.01.2010.

4.6 Pursuant to the issuance of the DLC, on 22.04.2011, the respondent submitted a Draft Final Statement, in accordance with Clause 60.11 of the Conditions of Particular Application (hereinafter the 'COPA'). The Engineer certified an aggregate payment of ₹4,95,02,980/- for the work done against certain items but rejected the

Signature Not Verified Digitally Signed

Signing Date:22.03.2022 Draft Final Statement in regard to the other payments. The respondent submitted further information to the Engineer in support of its claim for the amounts that were rejected by the Engineer, however, the Engineer did not accept the same.

4.7 It is stated that in view of the above, the Final Statement could not be prepared. In respect of the payment certified by the Engineer for an aggregate amount of ₹4,95,02,890/-, the respondent accepted the same. The said certification issued by the Engineer on 10.01.2012 was considered as an Interim Payment Certificate (IPC no. 66).

4.8 The petitioner referred the disputes regarding the claims that were not accepted by the Engineer to the Dispute Adjudication Board (hereinafter 'DAB'). The DAB rendered its decision. The respondent did not accept the decision of the DAB and those disputes were referred to arbitration. Thereafter, on 06.08.2012, an arbitral tribunal was constituted to adjudicate the said disputes. This Court is informed that the arbitral proceedings have culminated into awards, which is the subject matter of challenge by NHAI in another proceeding.

4.9 The payments, as certified by the Engineer under IPC no. 66 dated 10.01.2012, were not paid (the payment certificate accepted and certified by the Engineer. By various communications, the respondent requested NHAI to pay the outstanding amount as certified by the Engineer. However, the respondent claims that NHAI did not make the payments due.

Signature Not Verified Digitally Signed

Signing Date:22.03.2022 4.10 Certain letters were written by the Project Director, NHAI, which indicate that some of the Non-BOQ Variation Orders required the approval of the Competent Authority. And, the payments certified by the Engineer were withheld for want of the said approvals.

4.11 The respondent states that it sent letters dated 29.01.2013, 21.03.2013 and 30.05.2013 requesting NHAI to make the payments as certified by the Engineer under IPC no. 66.

4.12 Since NHAI failed to make the payments, the respondent invoked the Disputes Resolution Mechanism Clause by a letter dated 23.09.2013 and communicated its intention to refer the disputes to the DAB, in terms of Clause 67.1 of the COPA.

4.13 Thereafter, the respondent issued a letter dated 21.04.2015 referring the disputes to the DAB. The DAB rendered its decision on 03.08.2015 accepting the respondent's claim for payment of ₹4,95,02,890/- as certified under IPC no. 66. However, the DAB did not accept the respondent's claim for interest in entirety and allowed interest only up to 03.08.2015.

4.14 Both the parties were dissatisfied with the decision of the DAB. NHAI issued a notice dated 20.08.2015 expressing its dissatisfaction with the decision of the DAB and the intention to refer the disputes to arbitration. The respondent also issued a letter dated 27.08.2015 expressing its dissatisfaction with the DAB's decision to limit the interest till 03.08.2015 and regarding certain other issues. However, it

Signature Not Verified Digitally Signed

Signing Date:22.03.2022 accepted the DAB's decision insofar as its claim for payment of the amounts certified under IPC no. 66.

4.15 Thereafter, by a letter dated 30.08.2017, the respondent invoked the Arbitration Agreement and sought reference of the disputes to arbitration.

4.16 On 30.04.2018, the respondent filed its Statement of Claims. The claims made by the respondent in the Statement of Claims are tabulated below:

                                CLAIM             PARTICULARS                    AMOUNT

                                Claim No.1        Payment against certified IPC ₹4,95,02,980
                                                  no. 66
                                Claim No.2        Payment of interest at the rate ₹5,49,05,164/-
                                                  of      12%       per   annum
                                                  compounded monthly, in
                                                  terms of Clause 63.8 of the
                                                  COPA from the date of IPC
                                                  till the date of payment



4.17 NHAI filed its Statement of Defence contesting the claims made by the respondent, inter alia, on the ground that the same were barred under the Limitation Act, 1963. In addition, NHAI also raised counter claims of ₹25.32 crores towards liquidated damages for delay in execution of the works and sought a set off of the said amount. It also raised a counter-claim for interest: pendente lite interest calculated on the awarded amount at the rate of 24% per annum and future interest calculated on the awarded amount at the rate of 18% per annum.

Signature Not Verified Digitally Signed

Signing Date:22.03.2022 Reasons and Conclusion

5. Mr Bishnoi, learned counsel appearing for NHAI, confined the challenge to the impugned award to the extent that it rejects NHAI's contention that the claims were barred by limitation. He submitted that since the Majority Arbitrators had not concurred on awarding interest from the date of IPC no. 66 till 30.08.2017, there was no award for the same and NHAI was not required to challenge the award of interest.

6. Since NHAI does not press its challenge to award of interest, this Court is refraining from making any objection in regard to award of interest. The only question that is required to be examined by this Court is whether the impugned award is vitiated by patent illegality as the Arbitral Tribunal (by majority) has accepted that the respondent's claim was within the period of limitation.

7. Mr Bishnoi earnestly contended that the cause of action for claiming the amount of ₹4,95,02,980/- (the payment as certified by the Engineer under IPC no.66) had arisen when the work was completed. He submitted that since the works were completed way back on 26.03.2008 - the date on which the TOC was issued by the Engineer - the period of limitation had expired on 25.03.2011. He submitted that if the date of the DLC is considered as the date of cause of action, the period of limitation would expire on 10.01.2014 (that is, three years from the date of DLC dated 11.01.2011). He submitted that in any event, the amount claimed by the respondent was certified by the Engineer on 10.01.2012 and therefore, at the latest, the period of limitation expired on 09.01.2015.

Signature Not Verified Digitally Signed

Signing Date:22.03.2022

8. The Arbitral Tribunal had considered the aforesaid issue and the learned Arbitrator (Shri A.B. Desai) had rejected the said contention. The learned Arbitrator had found that NHAI had not disputed the amounts certified by the Engineer under IPC no. 66 and therefore, there was no reason for the respondent to immediately invoke the Disputes Resolution Mechanism. The learned Arbitrator also noted that in terms of Clause 60.8 of the COPA, NHAI was obliged to make the payments under any Interim Payment Certificate within a period of thirty days of the monthly statement being submitted to the Engineer for certification. In the event of failure to make the payment within the stipulated period, NHAI was liable to pay interest on the amount certified under the Interim Payment Certificate from the date on which such payments are due.

9. The Arbitral Tribunal held that the cause of action for the dispute did not arise immediately on completion of the works on 26.03.2008, as on that date no dispute had arisen. The Arbitral Tribunal noted that the Contract stipulated a mechanism for resolution of the disputes and in terms of Clause 67.1 of COPA, any dispute in the first instance is required to be referred to the DAB. Clearly, no such dispute had arisen on the date of completion of the works or on the date of the TOC. In terms of Clause 60.11 of the COPA, the Draft Final Statement was required to be submitted within a period of fifty-six days after issuance of the DLC.

10. The dispute in the present case had arisen on account of non- payment of certain payments included in the Draft Final Statement as

Signature Not Verified Digitally Signed

Signing Date:22.03.2022 certified by the Engineer. Thus, the question of seeking a reference of any dispute prior to that date, did not arise.

11. Clearly, there is no infirmity with this reasoning of the Arbitral Tribunal. The contention that the respondent was required to make a claim within a period of three years from the date of completion of the works on 26.03.2008 or the DLC dated 11.01.2011, is unmerited considering that IPC no. 66 was issued by the Engineer on 10.01.2012.

12. The dispute arises in respect of non-payment of the amount as certified by the Engineer on 10.01.2012. There is no dispute that the letter dated 10.01.2012 issued by the Engineer certifying some of the amounts claimed under the Draft Final Statement submitted by the respondent constituted an Interim Payment Certificate (IPC no. 66). The Final Statement could not be prepared in view of the disputes regarding the claims included in the Draft Final Statement, which were not certified by the Engineer. It is important to note that the Final Statement had not been prepared till the filing of the Statement of Claims by the respondent.

13. Since the dispute relates to non-payment of the amounts certified under the IPC, the period of limitation could not commence prior to 10.01.2012.

14. The Arbitral Tribunal had noted that in terms of the Contract, it was not open for NHAI to completely disregard the Interim Payment Certificate. NHAI was either required to pay the same or dispute the same. In the present case, the Arbitral Tribunal found that NHAI had

Signature Not Verified Digitally Signed

Signing Date:22.03.2022 not disputed IPC no.66. On the contrary, the Project Director had, in fact, acknowledged that the payment was due. There were two letters issued by the Project Director - letters dated 30.05.2012 and 14.08.2012

- copies of which the respondent claims, were received by email. In its letter dated 30.05.2012, the Project Director had, inter alia, stated as under: -

"Some Non-BOQ variation orders have to be got approved by the Competent Authority. The Final Bill of the Contractor has been checked and final net payment to the Contractor works out to ₹4,95,02,980/-, but the payment is kept pending for want of approval for the above."

15. The Arbitral Tribunal (by majority) had construed the said letter as a clear acknowledgement. The learned Arbitrator had noted that while the liability to pay ₹4,95,02,980/- was not disputed, the same had been withheld for want of approval regarding non-BOQ Variation Orders. Since, it was acknowledged that the payments were due but were awaiting approvals, it was clearly not necessary for the respondents to initiate any immediate action. The Arbitral Tribunal was of the view that the respondent could not be expected to immediately invoke the Disputes Resolution Mechanism and that the period of limitation stood extended. This Court finds no infirmity with the said view.

16. The question as to interpretation of the said communication clearly falls within the jurisdiction of the Arbitral Tribunal and this Court finds no infirmity with the manner in which the said communications have been interpreted. Since, the certified payments

Signature Not Verified Digitally Signed

Signing Date:22.03.2022 were not made despite sending various letters (that are, letters dated 29.01.2013, 21.03.2013 and 30.05.2013), the respondent invoked the Disputes Resolution Mechanism and by a letter dated 21.04.2015, sought reference of the disputes to the DAB. This was in conformity with the Disputes Resolution Mechanism, as agreed between the parties in terms of Clause 67 of the COPA.

17. It is important to note that the DAB accepted the respondent's claim for the amount certified under IPC no. 66 (₹4,95,02,980/-) in its decision dated 03.08.2015. At that stage, NHAI issued a 'Notice of Dissatisfaction' dated 20.08.2015 and expressed its intention to refer the disputes to arbitration in terms of Clause 67.4 of the COPA.

18. However, NHAI did not take steps to refer the disputes to arbitration. In the circumstances, the respondent invoked the Arbitration Clause. In the given facts, the decision of the Arbitral Tribunal holding that the respondent's claim was not barred by limitation cannot, by any stretch, be stated to be patently illegal or one that vitiates the impugned award under Section 34(2A) of the A&C Act.

19. The petition is unmerited and is, accordingly, dismissed. The pending applications are also disposed of.

VIBHU BAKHRU, J MARCH 22, 2022 pkv/v

Signature Not Verified Digitally Signed

Signing Date:22.03.2022

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter