Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

National Highways Authority Of ... vs Irb Pathankot Amritsar Toll Road ...
2022 Latest Caselaw 690 Del

Citation : 2022 Latest Caselaw 690 Del
Judgement Date : 8 March, 2022

Delhi High Court
National Highways Authority Of ... vs Irb Pathankot Amritsar Toll Road ... on 8 March, 2022
*     IN THE HIGH COURT OF DELHI AT NEW DELHI
%                                     Reserved on: February 08, 2022
                                   Pronounced on: March 08, 2022
+     O.M.P. (COMM) 373/2021& I.A. 17100-01/2021 & 663/2022
      NATIONAL HIGHWAYS AUTHORITY OF INDIA
                                           ..... Petitioner
                      Through: Mr. Sudhir Nandrajog,
                               Senior Advocate with
                               Mr. Nikhil Mehta &
                               Mr. Varun Sharma,
                               Advocates

                         Versus

      IRB PATHANKOT AMRITSAR TOLL ROAD LTD.
                                            ..... Respondent
                       Through: Mr. Vikram Nankani &
                                Mr.Saurabh Kirpal, Senior
                                Advocates with Mr. Mahesh
                                Agarwal, Mr. Sameer
                                Rohatgi, Mr. H.P.
                                Chaturvedi, Mr. M.V.
                                Ravindran, Mr. Ashish
                                Batra,Mr. Sarthak Sachdev,
                                Mrs. Terresa R Daulat &
                                Mr. Apoorva Agarwal,
                                Advocates

     CORAM:
     HON'BLE MR. JUSTICE SURESH KUMAR KAIT

                         JUDGMENT

1. The present petition has been filed under the provisions of Section

34 of Arbitration and Conciliation Act, 1996 challenging the arbitral

award dated 13.07.2021 read with order dated 27.07.2021 passed by the

learned arbitral tribunal.

2. In the present petition, it is stated that the Government of India

entrusted the work of development, maintenance and management of

Pathankot to Amritsar Section of National Highways No.15 from km

6.082 to km 108.502 to the petitioner, for which petitioner invited

proposals for design, build, finance, operate and on transfer basis the

above referred Section of NH-15, shortlisted certain bidders including

consortium comprising IRB Infrastructure Ltd. and Modern Road Makers

Pvt. Ltd. with IRB Infrastructure Developers Ltd. as its Lead Member

(henceforth referred to as the "consortium"). After evaluation, petitioner

accepted the bid of the consortium vide its letter of acceptance dated

27.07.2009. Respondent- IRB Pathankot Amritsar Toll Road Ltd., by its

letter dated 21.09.2009 also joined the consortium and thereafter, a

Concession Agreement dated 16.11.2009 was entered between the

parties. In terms of the aforesaid Concession Agreement, the

commencement of the work was to be done on 31.12.2010 and the

completion date was fixed as 910th day from the appointed date i.e.

27.06.2013. However, the work could not be completed within the time

stipulated and time was extended from 05.08.2014 to 25.08.2014 to

15.10.2014 and the parties entered into a further agreement dated

05.11.2014. Though respondent claimed to have completed the work by

18.11.2014, however, vide letter dated 22.11.2014 took the plea that

certain works like boundary pillars, drainage etc. are left, which do not

affect the project work. Therefore, a Provisional Completion Certificate

(PCC) was issued to the respondent on 27.11.2014 to commence

commercial operation and toll collection. After three years of issuance of

Provisional Completion Certificate, vide letter dated 19.06.2017

respondent requested for extension of Concession Period for the period

of 581 days and reiterated the same request on 18.06.2018. On

07.08.2018 respondent invoked arbitration and thereafter, on 19.01.2019,

approached IRC for appointment of Arbitrator. The arbitral tribunal was

constituted comprising of Justice (Retd.) Ajit Prakash Shah as the

Presiding Arbitrator and Shri S.S. Agarwal and Shri Navin Kumar as

Arbitrators.

3. Before the arbitral Tribunal, the respondent/claimant filed the

Statement of Claims and petitioner/respondent filed the Statement of

Defence. Based thereupon, the arbitral tribunal framed the issues and

proceeded for determination thereof. The tribunal proceedings

culminated into Award dated 13.07.2021, wherein the claims raised by

the respondent / claimant were granted with costs. Based upon the

aforesaid averments made in the petition and aggrieved against the said

arbitral award, the present petition under the provisions of Section 34 of

the Arbitration and Conciliation Act, 1996 has been preferred by the

petitioner.

4. Before adverting to the submissions and arguments raised on

behalf of both the sides, it is pertinent to mention the issues which were

subject matter of consideration and decision before the arbitral tribunal.

These issues were framed by the learned arbitral tribunal on 28.01.2020

and have been enumerated in Para-10 of the impugned award and read

as under:-

"1. Whether the Independent Engineer approved Extension of Time of 518 days in terms of provision of Article 14 or the Concession Agreement?

2. Whether the Supplementary Agreement dated 05.11.2014 prohibits claims of the Claimant as consequence of delay damages arising out of the overrun?

3. Whether the compensation sought by the Claimant under Clause 35.2 of the Concession Agreement towards increase in capital cost is attributable to delay

on the part of NHAI in completion of the Project Highway?

4. Whether the Claims are time barred?

5. Whether the Claimant is estopped from making the Claims in view of execution of the supplementary agreement dated 05.11.2014?

6. Interest & Costs?"

5. During the course of hearing, learned senior counsel appearing on

behalf of petitioner submitted that the impugned Award is against the

provisions of the contract, which has been rendered in haste without

appreciating the pleadings and evidence on record. The learned arbitral

tribunal neither considered the objections/ submissions made on behalf

of petitioner nor rejected them and thereby, the impugned Award is

cryptic, non-speaking, patently illegal and in conflict of provisions of law

as well as provisions of Arbitration and Conciliation Act, 1996.

6. With regard to the first issue i.e."whether the Independent

Engineer approved Extension of Time of 518 days in terms of provision

of Article 14 of the Concession Agreement", learned senior counsel for

petitioner submitted that „Extension of Time‟ and „Extension of

Concession Period‟ are all together two different issues. „Extension of

Time‟ means extension of time for construction and „Extension of

Concession Period‟ means extension of toll collection period. It was next

submitted that the learned Tribunal wrongly framed and dealt with the

Issue no. 1, as the claim of the claimant was for the „Extension of

Concession‟ period but the tribunal dealt it as „Extension of Time‟ only

and on this ground alone, the Award in question deserves to be set aside.

Also submitted that the Independent Engineer (IE) vide letter dated

23.09.2015 had recommended extension of time of 518 days without

extension of concession period, however, learned tribunal on the

erroneous assumption recommended the concession period, though in

terms of Article 35 of the Concession Agreement, extension of

concession period can be claimed only if the NHAI is in material default

or breach of the Concession Agreement. Learned senior counsel also

relied upon communication dated 25.10.2012 of the Independent

Engineer to submit that the delays were attributable to respondent only

and so, extension of time to the respondent was refused. It is submitted

by learned senior counsel that the learned arbitral tribunal has

misinterpreted the letters dated 27.05.2013; 12.06.2013; 07.10.2013;

20.12.2013 and 23.03.2015 while assuming that the impediments for

timely completion of the project are attributable to the petitioner-NHAI.

7. With regard to the second issue, "Whether the Supplementary

Agreement dated 05.11.2014 prohibits claims of the Claimant as

consequence of delay damages arising out of time overrun" , learned

senior counsel submitted that the tribunal has erroneously held that the

Supplementary Agreement dated 05.11.2014, was executed by the

respondent/IRB under economic duress and hence, is voidable, whereas

Shri Navin Kumar, learned Arbitrator has taken a different view that the

respondent has failed to establish the existence of any coercion for

issuance of the undertaking dated 13.10.2014 or 05.11.2014. It is also

submitted that the tribunal has wrongly held that the Supplementary

Agreement was not drafted or prepared by the respondent/ IRB but was

by the petitioner/NHAI, whereas the stamp paper for the Supplementary

Agreement has been purchased in the name of respondent and typed

thereon and it cannot be presumed that the stamp paper was in the

possession of the petitioner, who got it prepared. Therefore, this finding

returned by the Tribunal that the Supplementary Agreement is voidable

is patently wrong and is liable to be set aside.

8. Learned senior counsel next submitted that the finding returned by

the tribunal that the Supplementary Agreement was signed under duress

cannot be accepted, as the Shri Navin Kumar, learned Arbitrator has

taken a contrary view and it is established from the fact that safety audit

report was submitted only on 18.10.2014, which is a pre-requisite for

grant of PCOD and thereafter, on 21. 10.2014, the project was inspected

and on the next day i.e. 22.10.2014, petitioner approved the issuance of

PCOD i.e. much prior to the execution of the Supplementary Agreement.

Therefore, the issue of duress is an after-thought portrayed by the

respondent.

9. On the aspect of delay in raising the claim regarding duress,

learned senior counsel for petitioner submitted that the tribunal has erred

in holding that there was no delay on the part of respondent, whereas

Shri Navin Kumar, learned Arbitrator has observed that the

Supplementary Agreement was signed on 05.11.2014 whereas

respondent/ IRB raised the dispute under Article 44 of Concession

Agreement on 18.06.2018 and the Testimony of CW-1, makes it clear

that the respondent did not raise any protest almost for a period of four

years against the alleged duress from the date of the signing of the

Supplementary Agreement .

10. Learned senior counsel for the petitioner submitted that the finding

returned by the arbitral tribunal that the Supplementary Agreement does

not in any way prevent the claimant from making the claims, is patently

wrong as the learned tribunal has misinterpreted construction period

between the appointed date of 31.12.2010 and Schedule date of

completion of 27.06.2013, whereas it should have been calculated from

the appointed date of 31.12.2010 to the commercial operation date i.e.

27.11.2014 and therefore, in view of Supplementary Agreement dated

05.11.2014, the claim of respondent deserves to be rejected.

11. It was also contended by learned senior counsel for the petitioner

that as per the Clause- b of Supplementary Agreement dated 05.11.2014,

it was agreed by respondent that it shall not raise any claim whatsoever

in this Concession Agreement i.e. idling of resources (Manpower and

machinery), increase in cost of material, delay in construction of

highway, etc.

12. On the third issue "Whether the compensation sought by the

Claimant under Clause 35.2 of the Concession Agreement towards

increase in capital cost is attributable to delay on the part of NHAI in

completion of the Project Highways", learned senior counsel submitted

that the learned arbitral tribunal has held that the delay has occurred due

to reasons solely attributable to the petitioner and that the respondent has

claimed Rs.159.54 Crores and Rs.92.71 Crores towards extra expenditure

and increase in capital cost due to time over run / delayed construction

for the period 27.06.2013 to 27.11.2014, however, in the audited

accounts of the respondent, there is no mention of the above said amount

and even otherwise, the learned tribunal has erred in granting damages/

compensation when petitioner had extended the concession period

equivalent to the construction delay, as the respondent was able to earn

the toll for the same period which was originally available to it.

13. Learned senior counsel for petitioner further submitted that the

tribunal erred in holding that the costs shall be solely borne by the

petitioner, which is contrary to the contract entered between the parties,

according to which costs were to be equally borne between the parties.

Also submitted that the learned tribunal erred in granting the interest

from the period starting from 27.11.2014, whereas the claims were

quantified by the respondent only on 18.09.2018 and 15.05.2019.

14. On issue No.5 i.e. "whether the Claimant is estopped from

making the Claims in view of execution of the supplementary agreement

dated 05.11.2014", learned senior counsel for petitioner submitted that

the finding of tribunal that the Supplementary Agreement was signed by

the respondent under duress and so, question of estoppel does not arise,

is patently wrong as respondent had voluntarily entered into

Supplementary Agreement dated 05.11.2014, which was duly acted upon

by the petitioner and in lieu of same, Provisional Completion Certificate

and Final Completion Certificate effective from 27.11.2014 were duly

issued to the respondent. Also submitted that it is after four years of

execution of Supplementary Agreement dated 05.11.2014, the

respondent/ claimant on 24.09.2018 for the first time has alleged that the

"no claim undertaking" was given under duress. It was submitted that at

the time of entering into the Supplementary Agreement, the respondent

had defaulted on timely completion of project, hence it was not economic

duress but it was economic for the respondent to enter into the said

agreement, which is a legally binding Agreement and a valid contract

and in this view, the tribunal ought not have granted claim of respondent.

15. Learned senior counsel for petitioner emphatically submitted had

the Supplementary Agreement not been entered into between the parties,

the petitioner would have terminated the Concession Agreement and

levied damages on the respondent for delays and breaches on its part,

whereas by virtue of Supplementary Agreement, both the sides had given

up their claims against each other. It was submitted that if at this stage

the Supplementary Agreement is rescinded declaring it to be under

duress, the benefits derived there-under by the respondent have to be

returned and petitioner‟s rights have to be restored, which were not

claimed before the learned arbitral tribunal, such like, petitioner‟s right to

terminate the Concession Agreement under Article 32 would have to be

revived retrospectively; the entire toll collected by the respondent would

become unauthorized; the petitioner would become entitled to damages

for non-completion of project within the scheduled time and for several

material breaches etc. from the respondent.

16. On the issue "whether the claims raised by the petitioner were

time barred", learned senior counsel submitted that the arbitral tribunal

has failed to appreciate that the claims of respondent were highly barred

by time, as the respondent itself has claimed before the tribunal that the

limitation period started when the IE determined the Extension of Time

i.e.11.12.2015, whereas the Extension of Time for the first time was

determined on 22.12.2014 and second time on 23.03.2015 and thereby,

cause of action accrued on 22.12.2014, whereas the claims were raised

after lapse of four years on 18.06.2018 and arbitration was invoked vide

letter dated 07.08.2018. It was also submitted that vide letter dated

18.06.2018, the respondent had invoked conciliation on the point of

Extension of Concession Period only and no claim for compensation was

raised and therefore, the finding of tribunal that the claims are not time

barred is patently illegal.

17. To the contrary, learned senior counsel appearing on behalf of the

respondent submitted that the impugned award in question is a detailed

well-reasoned Award and finding of one of the Arbitrators on the issue of

economic duress does not affect the conclusion thereof. It was submitted

that the findings returned in the impugned Award are based on

construction and/or interpretation of the Concession Agreement, duly

supported by material on record including the Statement of Accounts and

the oral evidence of the Chartered Accountant and Auditor and it does

not at all suffers from patent illegality or perversity.

18. Learned senior counsel for respondent submitted that the

Concession Agreement dated 16.11.2009 was executed between

petitioner/NHAI and respondent where-under petitioner was obliged to

provide to Concessionaire a valid license and hindrance free vacant Right

of Way to the entire Site of the Project within 90 days from the appointed

date i.e. 31.12.2010, failing which it was liable to pay damages to

respondent. As per Article 12.4 read with Article10.3 construction of the

Project Highway was to be completed by 910 th day from the appointed

date i.e. the Scheduled Four Lanning Date of 27.06.2013 and if the

respondent failed to complete the project milestones within 90 days from

the date fixed for such milestone, it was liable to pay damages to the

petitioner/NHAI. However, if delay was due to default by petitioner/

NHAI or force majeure, then respondent was entitled to grant of

extension of time determined by the Independent Engineer and

accordingly all timelines would get extended.

19. Learned senior counsel for respondent next submitted that as per

Article 27 read with Article 15 of the Concession Agreement, respondent

was entitled to commence collection of Fee /Toll from the date of

completion certificate issued by the Independent Engineer under Article

14 thereof for the entire Concession Period of 20 years from appointed

date. The concession agreement in Article 35.02 further stipulated that if

petitioner/ NHAI was in material default or breach of the Concession

Agreement, it shall be liable to pay compensation of all direct costs,

including interest payments on Debt O&M Expenses, any increase in

capital costs on account of inflation and all other costs. In addition,

Clause 35.03 stipulated that in the event such material default by NHAI

as in Article 35.2 causes delay in achieving COD, NHAI shall, in

addition to payment of compensation under Article 35.2, extend the

Concession Period to the extent of delay in COD.

20. Learned senior counsel submitted that the arbitral tribunal has

rightly held that due to reasons solely attributable to the petitioner, there

was delay in completion of construction of the Project. It was contended

that despite recommendation of the Independent Engineer for Extension

of Time of 518 days, petitioner unreasonably withheld the approval

contrary to the provisions of Concession Agreement till issuance of

provisional completion certificate and consequently, there was delay in

COD and respondent could not commence collection of fee/ toll.

21. Learned counsel for respondent submitted that on issue No.1, the

learned arbitral tribunal has held that respondent is entitled to "Extension

of Time" of 518 days from the scheduled completion date of 27.06.2013

on account of delays solely attributable to NHAI, which were supported

by detailed, catalogued reasons, particularly letters dated 7.10.2013 &

20.12.2013 of the Independent Engineer, who confirmed the delays and

hindrances due to non-availability of hindrance free work site and also

upon failure of petitioner to execute relevant agreements with Railways;

deposit mandatory planning and estimation charges on time, which

petitioner has not been able to rebut before the learned arbitral tribunal.

22. With regard to issue No.2 & 5, learned senior counsel for

respondent submitted that respondent has been able to prove before the

arbitral tribunal that the supplementary agreement was signed under

economic duress, which is one sided agreement drafted by the NHAI

with the condition to issue the Provisional Completion Certificate.

Respondent has also been able to prove that obtaining of Provisional

Completion Certificate was necessary for respondent to collect the toll/

fee and to pay off the debts of lenders. Learned senior counsel submitted

that the arbitral tribunal has rightly rendered the Supplementary

Agreement void. Learned counsel submitted that cumulative reading of

Article 35.2 &35.3 shows that once default by NHAI is established, it

must extend the Concession Period proportionately to the period of

delay. It was strenuously submitted that the claims of respondent are not

at all barred by limitation. It was also submitted that the scope of review

of arbitral award by this Court under the provisions of Section 34 of the

Act, is very limited. Learned senior counsel placed reliance upon a recent

decision of Hon‟ble Supreme Court in Delhi Airport Metro Express Pvt.

Ltd. Vs. Delhi Metro Rail Corporation Ltd. 2021 SCC OnLine SC 695

in support of above submissions.

23. The rival contentions urged on behalf of both the sides were

extensively heard and material placed on record as well as decisions cited

have been carefully perused.

24. Pertinently, Section 34 of the Act provides for setting aside of the

arbitral award on very limited grounds, which have been enumerated in

sub-Section (2) and (3) of Section 34 of the Act. Further, in catena of

decisions, the Hon‟ble Supreme Court has laid down the parameters to be

followed while considering the petitions under the aforesaid provisions

of law.

25. In a recent decision in National Highways No. 45E and 220

National Highways Authority of India Vs. M. Hakeem, 2021 SCC

OnLine SC 473 the Hon‟ble Supreme Court has held that under Section

34 of the Arbitration and Conciliation Act, 1996, Courts cannot modify

or vary an arbitral award. It has been further held that "given the very

limited judicial interference on extremely limited grounds not dealing

with the merits of the award, the "limited remedy" under Section 34 is

coterminous with the "limited right" namely, either to set aside an

award or remand the matter under the circumstances mentioned in

Section 34 of the Arbitration Act, 1996."

26. Applying the afore-noted ratio of law laid down by the Hon‟ble

Supreme Court and keeping in mind that this Court cannot in depth

scrutinize the arbitral award and has only a limited scope to interfere, this

Court has analysed the arbitral award to find out whether the claims

raised in the present petition are valid and liable to be sustained or

dismissed.

27. In the impugned award, the arbitral tribunal has noted that for

executing the Project on a DBFOT basis, a Concession Agreement was

signed between the parties on 16.11.2009 for a Concession Period of 20

years from appointed date i.e. 31.12.2010. The cost of the project was

Rs.705 crores, its length was 102.420 km. and the date scheduled for

completion of the project was 27.06.2013 and the project award

parameter was the grant of Rs. 126.90 crores. The aforesaid Concession

Agreement was amended vide a Supplementary Agreement dated

05.09.2013, whereby the arbitration clause was amended. Subsequently.

another Supplementary Agreement was signed between the parties on

05.11.2014, which according to claimant/ respondent was signed under

duress.

28. The learned tribunal has noted the claim of claimant/ respondent

that the project commenced from the appointed date i.e. 31.12.2010 and

the completion of the project was to be done by 27.06.2013, which was

delayed on account of reasons exclusively attributable to the petitioner

herein. The claimant/respondent had raised claims for Extension of Time

for 518 days, damages and for extension of concession period. Thus,

according to the impugned award, the claims raised by the claimant/

respondent before the arbitral tribunal were:-

i. Claim No.1, Extension of Concession Period: Since the Project

had been delayed due to the Respondent's breach of reciprocal

promises and obligations, the Claimant could not achieve a timely

COD. The overall effect of the delay was 518 days, as certified by

the Independent Engineer, and this greatly distorted and delayed

the Claimant's collection of revenue. Thus, it was not necessary to

prove who caused the breach and to what extent, given that the

Claimant was denied of its rightful period of commercial operation

for collection of revenue. Thus, the Claimant was claiming for the

extension of the Concession Period in order to secure appropriate

and adequate relief.

ii. Claim No. 2, Compensation under Article 35.2 for delay: Article

35.2 obliged the Respondent to reimburse the Claimant for any

extra expenditure incurred by the latter in case of a time overrun,

including expenditure for overheads and other specified, relevant

expenditure. Thus, the Claimant was claiming "an amount of Rs.

159.541 crores" under this clause, by relying on the annexed

detailed certified and audited expenditure as per the authorized

auditors.

iii. Claim No. 3, Compensation under Article 35.2 on account of

inflation: Article 35.2 also provides for compensation for "any

increase in capital costs on account of inflation and all other

costs" to be paid to account for escalation and other costs. The

Claimant calculated the same to be Rs.92.71 crores and submitted

its claim.

iv. Claim No. 4, Cost of Arbitration: The Claimant sought liberty to

submit a cost compilation under Section 31 A of the Arbitration

and Conciliation Act, 1996 towards closure of arbitration

proceedings.

29. The arbitral tribunal has also elaboratively noted the objection of

the petitioner/ respondent that the claimant had signed the Supplementary

Agreement dated 05.11.2014 with eyes wide open, where-under it had

agreed to not raise any claim whatsoever for idling of resources, increase

in cost of material, delay in highway construction etc. and also not to

seek an extension of the Concession Period.

30. The tribunal has also noted that the claimant/respondent had acted

upon the Supplementary Agreement and received the PCC/PCOD and

was also permitted an Extension of Time up to that period without levy

of penalty. Thus, the claimant/respondent had received benefits and

advantages by virtue of the Supplementary Agreement.

31. To determine the claims of claimant/ respondent, the arbitral

tribunal had framed six issues, which have already been noted by this

Court in Para-3 above.

32. (i) With regard to the first and fifth issue, the tribunal has noted

that the claimant/ respondent had commenced the work on 31.12.2010

and the date for completion of the project was scheduled as 27.06.2013.

Under Article 12.4.2 of the Concession Agreement if

claimant/respondent failed to achieve Project Milestone III within 90

days from 10.10.2012, it was liable to pay damages to the authority.

However, claimant/ respondent achieved the Project Milestone III on

31.12.2012 i.e. within the limitation period.

(ii) The tribunal has further noted that thereafter, claimant/ respondent

vide letter dated 27.05.2013, sought Extension of Time of 369 days from

Independent Engineer, detailing various impediments that were

attributable to the respondent, who vide letter dated 07.10.2013 granted

interim extension of 264 days clarifying that such 253 days Extension of

Time overlapped with the Extension of Time of 90 days assessed by it on

account of the hindrances at the site and thereby, shifted the project

completion date to 18.03.2014. The aforesaid proposal of Independent

Engineer vide letter dated 07.10.2013 was returned by the petitioner

herein, in response to which vide letter dated 20.12.2013 the Independent

Engineer once again reiterated its earlier recommendation for grant of

264 days interim Extension of Time. On 18.02.2014 i.e. more than six

months after the scheduled completion date, the Commissioner of

Railway Safety sanction was received and the mandatory planning and

estimation charges in respect thereof were deposited on 19.04.2014 and

the permission for launching girders was granted after clearance was

obtained from the Court on 01.08.2014. Thus, the delay of 400 days from

the scheduled date of completion i.e. 27.06.2013 till 01.08.2014 was

attributable only to the petitioner/NHAI. Thereafter, claimant/respondent

signed an undertaking on 14.10.2014 and the Supplementary Agreement

on 05.11.2014 and the Independent Engineer on 21.11.2014 sought

issuance of PCOD and after necessary approval on 27.11.2014 by the

Independent Engineer as well as petitioner herein, the toll collection at

the Highway began from 28.11.2014.

(iii) The impugned Award notes that the Independent Engineer vide

letter dated 23.03.2015 written to the petitioner/NHAI had clarified that

the claimant/ respondent had achieved Milestone- I before the scheduled

completion date, which was authenticated by the Statutory Auditor; and

had achieved Milestones- II and III within 90 days of the scheduled

completion date, as per Article 12.4.2 and reiterated that the claimant/

respondent was entitled to Extension of Time of 518 days.

(iv) On the first issue, the Tribunal held as under:-

"In view of the above factual narration, the following three conclusions emerge. First, the IE was the sole competent authority under the contract to determine the issue of EOT. Second, the IE's findings that the Claimant achieved Project Milestones I, II, and III within 90 days, as per Article 12.4.2 of the CA has gone unrebutted, except making references to the previous observations of the IE. In any event, the Respondent failed to demonstrate any error or flaw in this finding of the IE. Third, the IE's finding that the Claimant is entitled to an EOT of 518 days (400 + 87+ 31 days) from the scheduled completion date of 27.06.2013 has not been rebutted by the Respondent or shown to be to erroneous, even during their cross-examination. The time taken by the Respondent to receive the CRS approval for the 5 ROBs had admittedly been "abnormally delayed", resulting in an EOT of 400 days (till 01.08.2014) which subsumed other delays. The Respondent had also failed to provide any explanation on delay of 87 days (after receiving the Court's order dt. 01.08.2014 for completing the balance works on the ROB) and 31

days (for the period after 30.10.2014 since hindrance-free land was still not made available by NHAI to the Claimant, till the issuance of the PCC on 27.11.2014. Thus, the Claimant is entitled to EOT of 518 days with effect from the scheduled completion date of 27.06.2013 till the date of issuance of PCCIPCOD, i.e. 27.11.2014. Hence, the finding on Issue No. 1 stands concluded and the AT finds in favour of the Claimant that the IE has approved the EOT for 518 days as per Article 14 of the CA."

33. On the afore-noted first issue, this Court finds that vide letter dated

03.09.2012 the claimant/ respondent had requested the Director/NHAI to

handover the land required to enable it to complete the project on the

scheduled completion date. A perusal of communication dated

23.03.2015 of the Independent Engineer to the Project Director, NHAI

(Page-930 of documents) clearly shows that the reasons for grant of

Extension of Time wherein it is noted that under Event-1, hindrances at

the site had hampered the work of the concessionaire, which could be

removed from the main carriageway in June, 2014 and there was a delay

of 54 days in doing so. It is also noted that under Event-2, there was

delay caused for tree cutting permission and delay of 73 days was

attributable to it. Further, under Event-5, there was delay in shifting of

existing Irrigation Distributary and therefore, concessionaire was entitled

to extension of 90 days‟ time. Under Event- 6, extension of time of 13

days has been recommended for delay in possession of land due to

different court cases. The Independent Engineer under Event-7 has

recommended extension of time of 487 days due to delay in seeking CRS

approval. In all, the Independent Engineer has recommended delay of

518 days. In the opinion of this Court, the arbitral tribunal has rightly

noted that the Independent Engineer was the sole competent authority

under the contract to determine the Extension of Time and since

petitioner has rightly achieved Milestones I, II and III within the time

prescribed as per Article 12.4.2 of the Concession Agreement, the

Extension of Time of 518 days, for the reasons solely attributable to the

petitioner/NHAI, and has rightly recommended Extension of Time of

518 days and thereby holding issue No.1 in favour of the claimant.

34. With regard to second issue as to whether Supplementary

Agreement dated 05.11.2014 prohibits claims of claimants or not, the

learned arbitral tribunal has noted that in terms of Article 14.3.1, the

Independent Engineer was not required to take prior approval of

petitioner-NHAI before issuing PCC/PCOD and, therefore, Independent

Engineer‟s letter dated 13.10.2014 seeking the respondent's approval is

contrary thereto and claimant/respondent signing an undertaking on the

same date waiving its rights under the contract and reliance placed

thereupon by the Project Director of NHAI relying to seek approval from

NHAI on 14.10.2014, provided an important background to consider that

the same was signed under duress. It is also noted that the failure to

receive a PCC/PCOD, prevented the claimant/ respondent from levying

toll and thereby had serious economic implications and also it was under

pressure to repay the principal and interest to the banks.

(i) The Tribunal, therefore, held that only after respondent/Claimant

had signed the Supplementary Agreement on 05.11.2014, the

petitioner/respondent finalized the issuance of PCOD, which was

approved by the Executive Committee of NHAI on 27.11.2014 and

issued on the same date. The Tribunal has also held that petitioner/NHAI

had set up the signing of Supplementary Agreement as a pre-condition

for the issuance of PCC/PCOD.

(ii) With regard to plea of petitioner/NHAI that the Supplementary

Agreement dated 05.11.2014 was drafted by the claimant/ respondent,

the tribunal has opined that the stamp paper was purchased on

14.10.2014, which bears the name of claimant/respondent as the first

party and name of second party is blank. The Tribunal has also relied

upon noting of Mr. M.K. Jain, General Manager of NHAI vide (Tech)-

P&H dated 05.11.2014 addressed to CGM (T) BSS recording that "a

draft Supplementary Agreement to be signed with the concessionaire is

placed for perusal please" to arrive at the finding that the Supplementary

Agreement was drafted and signed on the same date and it was the

petitioner/NHAI herein who had drafted the same.

35. This Court has also gone through the Supplementary Agreement

dated 05.11.2014, the relevant portion of which has caught the eyes of

this Court, is highlighted as under:-

      "THE PARTIES         HEREIN      HAVE     AGREED       TO    THE
      FOLLOWING:

      (a)      Both the parties amicably agree, for issuance of

Provisional Completion Certificate the work of Design, Engineering, Finance, Construction, Operation and Maintenance of Pathankot to Amritsar Section of NH-15 from Km. 108+502 in the State of Punjab subject to completion of certain balance items as decided by Authority in its Executive Committee Meeting held on 22.10.2014.

(b) Concessionaire amicably agree that he will not raise any claims whatsoever in this Concession Agreement i.e. idling of resources (manpower and machinery), increase in cost of materials, delay in construction of highway, etc. The Concessionaire amicably agrees that he will not seek any extension in Concession Period: however, the Concessionaire shall retain his right for extension of the Concession Period on account of any

valid factor arising after the actual construction of the highway/ project as per provisions of the Concession Agreement.

(c) The concessionaire also claimed that he should be given EOT for construction period without levy of penalty as delay was attributable to both the parties. It was amicably settled that the issue of grant of EOT for construction period shall be dealt separately.

(d) Concssionaire amicably agrees that it shall not raise any claim whatsoever, in any form other than for any Change of Scopes already principally approved by NHAI. A fair decision by NHAI, as per provisions of the CA, on the variations/ Change of Scopes will be acceptable to the concessionaire.

(e) The Concessionaire amicably agrees to complete the balance works mentioned in punch list, as per Concession Agreement."

36. An undertaking from the claimant/respondent, as mentioned in

Clause- (a) and (b) highlighted above, has been given and after

furnishing thereof, the petitioner finalised issuance of PCC, which was

issued on 27.11.2014. This Court finds that the learned arbitral tribunal

has taken detailed note of the facts and circumstances in which the

Supplementary Agreement dated 05.11.2014 was executed and this Court

is in harmony to the said view of the arbitral tribunal.

37. On the aspect whether respondent herein had a right to claim for

the losses attributable to it, the stand of petitioner/NHAI before the

arbitral tribunal was that in the light of Supplementary Agreement dated

05.11.2014, the claimant/ respondent had waived off its right, however,

this Court finds that the Independent Engineer in letter dated 13.01.2015

had significantly stated that the claimant / respondent had achieved all

the milestones within the time framed and limitation period, as

prescribed under Article 12.4.2 and also recommended Extension of

Time, due to various delays attributable to the petitioner. Therefore, the

tribunal has rightly held that it cannot be accepted that claimant /

respondent will voluntarily give up valuable claims for compensation and

extension of Concession Period on account of petitioner‟s default without

any reciprocal consideration. The tribunal had therefore rightly held that

claimant/ respondent was in a precarious financial condition and that

without signing the Supplementary Agreement, the respondent would not

have issued the PCC/PCOD and it would not have been able to

operationalise the Project Highway and start collecting toll fees. It was

also rightly held that the Supplementary Agreement dated 05.11.2014

was signed by the claimant/ respondent under duress and is, therefore,

rendered voidable. Also, in view of Clause (C) of the Supplementary

Agreement the issue of Extension of Time is to be decided separately,

which makes it further clear that the claimant/ respondent had not given

up its claim for Extension of Time for construction and claim

compensation for the delay caused at the hands of petitioner/ NHAI.

38. With regard to issue No.5 „on estoppels", the tribunal has rightly

held that petitioner/NHAI did not provide any evidence of estoppels nor

any of the witness substantiated and also that once it has been held that

the Supplementary Agreement was signed under duress by

claimant/respondent, the question of estoppels does not arises.

39. On the aspect of claimant/respondent having raised the issue

belatedly on 24.09.2018 i.e. after 04 years of signing the Supplementary

Agreement, the arbitral tribunal has noted that the claimant had prayed

for issuance of a completion certificate on 03.05.2017, followed by a

letter dated 19.06.2017 seeking compensation for the delay of 518 days

under Article 35.2 and 35.3 of the concessionaire agreement. The

aforesaid letter dated 19.06.2017 to the NHAI was after 30 month of the

Supplementary Agreement and the claimant/respondent got the

Completion Certificate only on 25.08.2017. The tribunal has further

observed as under:-

"125. While evaluating this argument, the AT must take into account the threat of termination under Article 12.4.3 of the CA, since the delay in issuance of PCOD was more than the period of 270 days mentioned in Article 12.4.3 and the Respondent had not accepted that the delay was due to reasons solely attributable to it or due to a force majeure. In fact, even the Supplementary Agreement expressly left the question of EQT during the construction period open, thus leaving the threat of termination hanging on the Claimant. In this context, the

IE's letter dated 13.01.2015 further recommending an interim EOT up till the issuance of the PCC dt. 27.11.2014 is revealing of the Respondent's intentions, since it highlighted that:

"5. It is pertinent to point out that the Authority has been insisting for imposing of Damages on the Concessionaire for delay in completing the works on the stretches made available to the concessionaire free of any obstruction. However, the Milestones as per the CA have been achieved. As such, no damages are leviable on the Concessionaire" (emphasis supplied).

In the same letter, the IE also specifically references Article 12.4.3 of the CA noting that the Project Milestones I, II, and III had been achieved, but the Scheduled Project Completion Date as per Schedule G had not been achieved. The IE subsequently recommended the interim EOT till 27.11.2014."

40. The tribunal has also taken note of the fact that despite issuance of

full Completion Certificate on 25.08.2017, the issue of Extension of

Time was not settled and the claimant/respondent vide letters dated

18.06.2018; 28.06.2018 and 07.08.2018 raised the disputes and sought

conciliation and it is only after petitioner/NHAI failed to reply to the

same, the claimant/respondent invoked arbitration vide letter dated

07.08.2018. The aforesaid reasoning makes it abundantly clear that the

arbitral tribunal has rightly held that there was no delay on the part of the

Claimant in raising the claim of economic duress pursuant to

Supplementary Agreement dated 05.11.2014 and that claims are not

barred by limitation.

41. With regard to third issue whether the compensation sought by the

Claimant under Article 35.2 of the CA towards increase in capital cost is

attributable to the delay caused by the NHAI in completing the Project

Highway, the petitioner/NHAI has averred that the arbitral tribunal has

erroneously held that the delay has occurred for the reasons solely

attributable to the petitioner and therefore, compensation claimed by the

claimant/ respondent towards extra expenditure and increase in capital

cost due to time over run / delayed construction for the period

27.06.2013 to 27.11.2014 is liable to be rejected. Petitioner has also

claimed that once petitioner had extended the concession period

equivalent to the construction delay and the respondent was able to earn

the toll, there was no question of grant of compensation by the arbitral

tribunal. To the contrary, stand of claimant/respondent is that in terms of

Article 35.2 of the Concessionaire Agreement, if petitioner/ NHAI was in

default or breach thereof, it shall be liable to pay all direct costs,

including interest payments on Debt O&M Expenses, any increase in

capital costs on account of inflation and all other costs. Article 35.3

further stipulates that if the delays are caused and proved in terms of

Article 35.2, the petitioner/NHAI shall extend the concession period to

the extent of delay in COD.

42. It is pertinent to mention here that the Independent Engineer vide

its letter dated 07.10.2013 and 23.03.2015 had approved Extension of

Time for 518 days. In the said letter also stated that the claimant/

respondent had reached the Milestones within the contractual limitation

period. In addition, the Statutory Auditor certified the expenses for the

period 27.06.2013 till 27.11.2014 and based thereupon the tribunal was

right in holding that the incremental additional cost incurred by the

claimant/respondent as interest and fixed overhead costs on account of

the respondent‟s 518 days delay was Rs.159.451 crores. The tribunal

further added the direct cost in respect of labour, salary (PMC), Site

establishment costs, Plants & Machinery hire charges etc. to the tune of

Rs.92.71 crores thereto and held that compensation of Rs. 159.541 crores

+ Rs. 92.71 crores = Rs. 252.251 to be paid by the petitioner/NHAI to the

claimant/respondent. The concession period was also extended for 518

days for the delays attributable to the respondent.

43. In view of the above, finding that the arbitral award is based upon

the evidence and material placed on record, it cannot be held to be

perverse or erroneous and so is not required to be interfered with by this

Court.

44. With aforesaid observations, the present petition is dismissed.

(SURESH KUMAR KAIT) JUDGE March 08, 2022 r

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter