Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Ntpc Ltd vs M/S Tata Projects Ltd
2022 Latest Caselaw 657 Del

Citation : 2022 Latest Caselaw 657 Del
Judgement Date : 3 March, 2022

Delhi High Court
Ntpc Ltd vs M/S Tata Projects Ltd on 3 March, 2022
                          $~19
                          *    IN THE HIGH COURT OF DELHI AT NEW DELHI
                          +     FAO(OS) (COMM) 55/2022
                                NTPC LTD                                                ..... Appellant
                                                    Through:     Mr.Adarsh Tripathi with Mr.Ajitesh
                                                                 Garg and Mr.Vikram Singh Baid,
                                                                 Advocates.
                                                    versus

                                M/S TATA PROJECTS LTD                    ..... Respondent
                                              Through: Ms.Smita Bhargava with Mr.Tanuj
                                                       Agarwal and Ms.Pavitra Singh,
                                                       Advocates.
                          %                        Date of Decision: 03rd March, 2022
                          CORAM:
                          HON'BLE MR. JUSTICE MANMOHAN
                          HON'BLE MR. JUSTICE SUDHIR KUMAR JAIN
                                                     JUDGMENT

MANMOHAN, J (Oral):

C.M.No.10815/2022 Exemption allowed, subject to all just exceptions. Accordingly, the application stands disposed of. FAO(OS) (COMM) 55/2022 & C.M.No.10816/2022

1. Present appeal has been filed challenging the judgment dated 08th December, 2021 passed by learned Single Judge in OMP (Comm) No.171 of 2021 whereby the award rendered by learned Arbitral Tribunal was upheld.

2. Learned counsel for Appellant states that the Arbitral Tribunal has grossly erred in not preserving the right of the Appellant to raise its claims for levying liquidated damages subsequently. He states that the learned

Signature Not Verified Digitally Signed By:KRISHNA BHOJ Signing Date:08.03.2022 19:55:23 Single Judge as well as the Arbitral Tribunal failed to consider that the extension given to the Respondent was subject to levy of liquidated damages and the learned Single Judge even failed to note that the Arbitral Tribunal was of the view that the majority of the delay caused in completion of project had been caused by the Respondent. He emphasises that though no claim was raised by the Appellant in the Arbitral Tribunal qua the liquidated damages, yet the Arbitral Tribunal as well as the learned Single Judge concluded that neither party was justified in claiming any compensation/damages on account of prolongation of the work.

3. A perusal of the paper book reveals that the Respondent/claimant had specifically prayed for a declaration that the Respondent/claimant was not entitled to levy any liquidated damages for the delay in completion of the project. In view of the said specific prayer, this Court is of the opinion that it was incumbent upon the Appellant to prove that the delay was caused by the Respondent/claimant and the Arbitral Tribunal was legally bound to give a finding thereon.

4. In any event, upon a perusal of the award as well as the impugned order, it is apparent that the Appellant had sought to attribute delay in completion of the project on account of the certain action/inaction on the part of the Respondent/claimant. Consequently, the Arbitral Tribunal was legally obliged to render a finding on the said aspect.

5. Further, this Court is of the view that the intent of the arbitration proceeding, which is an alternative dispute resolution mechanism, is to give a quietus to the dispute. No party can say that even when the Respondent/claimant is seeking liquidated damages on account of delay and had sought a declaration that the Appellant was not entitled to liquidated

Signature Not Verified Digitally Signed By:KRISHNA BHOJ Signing Date:08.03.2022 19:55:23 damages, yet the Appellant would raise its counter-claim before another Arbitral Tribunal.

6. It is also settled law that once an arbitral award has been confirmed in an application filed under Section 34 of the Act, the Appellate Court must be extremely cautious in disturbing concurrent findings of the fact and law as they are ordinarily not amenable to interference under Section 37 of the Act. (See: M/s. Mangalwar Filling Station v. Indian Oil Corporation Ltd., FAO (COMM) 75/2021 dated 07th July, 20221.)

7. In view of the aforesaid, this Court finds no ground to interfere with the decision passed by the learned Single Judge. Accordingly, the present appeal along with pending application is dismissed.

MANMOHAN, J

SUDHIR KUMAR JAIN, J MARCH 03, 2022 KA

Signature Not Verified Digitally Signed By:KRISHNA BHOJ Signing Date:08.03.2022 19:55:23

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter