Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Navayuga-Van Oord Jv vs Union Of India Through Ministry Of ...
2022 Latest Caselaw 1914 Del

Citation : 2022 Latest Caselaw 1914 Del
Judgement Date : 30 June, 2022

Delhi High Court
M/S Navayuga-Van Oord Jv vs Union Of India Through Ministry Of ... on 30 June, 2022
                          $~1

                          *      IN THE HIGH COURT OF DELHI AT NEW DELHI
                          %                                             Decided on: 30th June, 2022
                          +                      O.M.P.(I) (COMM.) 208/2022


                                 M/S NAVAYUGA-VAN OORD JV                        .....Petitioner
                                         Represented by: Mr. Sandeep Sethi, Sr. Advocate, Mr.
                                                         Saurav Agarwal, Mr. Shantanu
                                                         Agarwal, Mr. Ankit Banati, Mr.
                                                         Harshit Malik, Ms. Shruti Arora, Ms.
                                                         Sruti Chandran, Ms. Anmol Dhindra
                                                         & Mr. Rishi Agarwala, Advocates.
                                              versus

                                 UNION OF INDIA THROUGH MINISTRY OF DEFENCE,
                                 DIRECTOR GENERAL, PROJECT VARSHA
                                                                              ...... Respondent
                                          Represented by: Mr. Harish Vaidyanathan Shankar,
                                                          CGSC, Mr. Srish Kumar Mishra, Mr.
                                                          Sagar Mehlawat & Mr. Alexander
                                                          Mathai Paikaday, Advocates.
                                                          Captain Varun Singh, JAG (Navy).

                          CORAM:
                          HON'BLE MS. JUSTICE NEENA BANSAL KRISHNA

                          NEENA BANSAL KRISHNA, J. (ORAL)

I.A. 9858/2022 (U/S 151 of CPC, 1908 for exemption from filing original/certified and typed/clear copies of the annexures/documents)

1. Allowed, subject to all just exceptions.

2. Application is disposed of.

O.M.P.(I) (COMM.) 208/2022

Signature Not Verified Digitally Signed By:NIRMLA TIWARI

Signing Date:05.07.2022 14:24:17

1. The present petition has been filed under Section 9 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the "A&C Act, 1996") by the petitioner seeking directions for appointment of an independent Agency to collaboratively look into the Report of IIT Madras to work out an effective way forward for completion of work and for restraining the respondents from invoking/encashing the seven Bank Guarantees during the pendency of the Arbitration proceedings. Claim of the Petitioner:

2. The case of the petitioner is stated that a Notice Inviting Tender (hereinafter referred to as the "NIT") was issued on 16th June, 2016 by the respondent for the construction of the Inner and Outer Harbour for "Project Varsha" which is a highly confidential Defence project of national and strategic importance to the Indian Navy, located on the East Coast of India. Because of the highly sensitive nature of the Project, a confidential and limited survey was allowed at the time of the Tender. The designs and drawings were provided with the Tender by the respondent. However, the prospective bidders were allowed to submit their bids for the project comprising of elaborate technical proposals, qualifications and other such documents, based on the documents provided by the respondent after a Confidentiality Undertaking. The petitioner was awarded the Contract through a Letter of Acceptance dated 24th October, 2017 (hereinafter referred to as the "LoA") and consequently, the parties entered into the Contract on 19th December, 2017.

3. The completion period was contemplated as 42 months i.e., till 18 th August, 2021, which stood extended upto 05th March, 2022. The commencement date was notified as 16th February, 2018 by the respondent

Signature Not Verified Digitally Signed By:NIRMLA TIWARI

Signing Date:05.07.2022 14:24:17 vide its Letter dated 15th February, 2018. The Project required extensive investment and mobilization of resources. Accordingly, the Contract envisaged interest bearing advance payments, subject to the Contractor submitting the Bank/Performance Guarantees.

4. The petitioner has asserted that it is a well-known industry practice that marine activities such as dredging are carried out in the „Fair-Weather Season‟ i.e., the period without Monsoon. For the East Coast of India, the Fair-Weather Season generally falls between October and April, post which the Monsoon commences. Due to the delay in the commencement of the works, the petitioner lost the entire First Fair-Weather Season, which had a cascading effect on the completion of the entire project within the given time frame.

5. The petitioner has claimed that irrespective of these difficulties, it remained committed to the Project and made all endeavours to complete the construction activities in time. It began pre-construction surveying works, drafting of plans and method statements, mobilization of construction equipment and manpower, construction of temporary site facilities and off- site arrangements and procurement of temporary and permanent work material. However, as the work progressed for construction activities, it was found that original GFC drawings and designs prepared by the Engineer/respondent were divorced from the prevailing site conditions and therefore, impossible to work. One of the major differences found was in the actual seabed levels. The petitioner raised the issue with the respondent for necessary modification but it refused to entertain any changes in the original design. The petitioner accordingly proceeded with the dredging work.

6. It was observed by the petitioner, over a period of time, that dredged

Signature Not Verified Digitally Signed By:NIRMLA TIWARI

Signing Date:05.07.2022 14:24:17 breakwater profiles executed as per the original designs had filled up with sand and the central mound of the dredged profile had eroded to a large extent, which led to the deformation of the dredged profiles. The petitioner during his work over the period of time realised that the original designs/drawings and time fixed for completion of project were made without adequate consideration of the aspects and hydro-dynamics and siltation during various stages of construction activities to be carried out by the petitioner.

7. In order to find a way forward, the petitioner at its own significant cost engaged IIT Madras (which was consulted by the respondent and its report was the basis of terms in NIT to support the original GFC drawings and designs) and other eminent domestic and International technical experts, namely;

(i) Department of Ocean Engineering, Indian Institute of Technology, Madras (hereinafter referred to as the "IIT Madras";)

(ii) C.D.R. (Coasts, Deltas, and Rivers) International B.V., Netherlands (hereinafter referred to as the "CDR International"), an independent Engineering Consultancy Firm in marine construction and ocean engineering sector; and

(iii) Professor Dr. Van Der Meer, a renowned international expert in the appraisal, design, and testing of break-waters and coastal structures, including seawalls and dikes.

8. From the reports of above-mentioned eminent experts which includes

Signature Not Verified Digitally Signed By:NIRMLA TIWARI

Signing Date:05.07.2022 14:24:17 the report of IIT Madras of December, 2021, it has been found that the Works as notified in the Contract, cannot be executed within the timeline provided in the Contract; thus making the performance of the Contract within the timelines provided in the Contract, as impossible. The realistic timeline for completion of the works as envisaged by the Contract cannot be less than 88 months, which too, is subject to external contingencies such as COVID-19 Pandemic and other unforeseeable, unstable oceanic conditions that can increase the time for completion. However, the report of the IIT Madras has been rejected illegally by the respondent and the Engineer.

9. It is further submitted that the respondent has been choking the petitioner‟s cash flow and restraining its liquidity by illegally withholding/delaying amounts due and payable to the petitioner. In fact, the amounts certified for the petitioner‟s work done since 26th July, 2021, which comes to ₹91,70,35,625/-, have still not been released by the respondent. The petitioner‟s readiness and willingness to perform the Contract can be gathered from the fact that it has already mobilized resources worth more than a thousand crores of rupees, deployed 500 personnel and borne significant expenses in engaging eminent experts to find the solutions to the on-site construction challenges arising out of original GFC drawings/designs. Per contra, the respondent is causing impediments to the petitioner‟s work by choking its cash flow and thereby causing unnecessary delay in the execution of the works.

10. It is submitted that the respondent is in possession of seven Bank Guarantees of the total value ₹6,33,73,84,436/- furnished by the petitioner at the time of commencement of Contract. It is asserted that if the respondent

Signature Not Verified Digitally Signed By:NIRMLA TIWARI

Signing Date:05.07.2022 14:24:17 withholds the amounts due to the petitioner illegally or invokes the Bank Guarantees right at the onset of the dispute, the petitioner shall be completely drained of its cash flow, putting fetters on its ability to execute the work and thereby cause irreparable harm/financial loss.

11. The petitioner by way of present petition under Section 9 of the A&C Act, 1996 has sought the following reliefs:

"(a) Appoint an independent agency to collaboratively look into the report of IIT Madras along with the concerned parties to work out an effective way forward which would enable expeditious completion of the works and restrain the Respondents from taking any coercive steps against the Petitioner;

(b) Restrain the Respondent, its employees, agents, representatives, and its officers from invoking/encashing the following Bank Guarantees during the pendency of the arbitration proceedings:

                                 S.No.                  Bank Guarantee          Amount in
                                                                                  Rupees
                                 i.       No.      75200IGL0001317     dated 292,54,00,000/-
                                          18.11.2017 issued by Union Bank of
                                          India, Industrial Finance Branch,
                                          Somajiguda, Hyderabad 500082
                                 ii.      No. 0999517FGOOO2374 dated 74,16,97,410/-
                                          29.11.2017 issued by State Bank of
                                          India, Corporate Account Group
                                          Branch, Ballard Estate, Mumbai -
                                          400001
                                 iii.     No.      75200IGL0001417     dated 188,82,87,026/-
                                          08.12.2017 issued by Union Bank of
                                          India, Hyderabad.
                                 iv.      No.      75200IGL0011818     dated 32,00,00,000/-
                                          03.11.2018 issued by Union Bank of
                                          India, Hyderabad.
                                 v.       No. 000191 BG0000002 dated 3,70,00,000/-


Signature Not Verified
Digitally Signed
By:NIRMLA TIWARI

Signing Date:05.07.2022
14:24:17
                                           22.02.2019 issued by Bank of
                                          Maharashtra, Hyderabad
                                 vi.      No.      75200IGL0009319     dated 22,50,00,000/-
                                          16.09.2019 issued by Union Bank of
                                          India, Hyderabad.
                                 vii.     No.      75200IGL0003520     dated 20,00,00,000/-
                                          24.07.2020 issued by Union Bank of
                                          India, Hyderabad.

(c) Pass ex-parte, ad-interim, and interim orders in terms of the above prayers."

Submissions on behalf of the Petitioner:

12. Learned Senior Counsel for the petitioner has argued that the NIT for the Contract was issued on 16th November, 2016 but it took almost one year to award the Contract on 24th October, 2017. Even thereafter, the Contract could be commenced only after five months of award i.e., from 16 th February, 2018 and the work was to be completed within 1280 days or 42 months, the date of completion being envisaged in the Contract as 18 th August, 2021. However, on account of prevailing COVID-19 Pandemic situation, the respondent extended the completion date till 28th April, 2022. From the very fact that it took about a year to award the Contract from the date of NIT and that it took another five months to commence the work, shows the complexity of the Contract executed between the parties.

13. It is submitted that certain drawings/designs submitted by the respondent were not in accordance with the ground realities and were found to be inappropriate, which got revealed when the construction work was commenced, which led to delay in expeditious completion of the project. Considering the sensitive nature of the project, the respondent had

Signature Not Verified Digitally Signed By:NIRMLA TIWARI

Signing Date:05.07.2022 14:24:17 considered the report from IIT Madras before floating the NIT but its recommendations which became the basis of terms of NIT, were based on a cursory survey that could be conducted due to the sensitive nature of the project. IIT Madras was therefore engaged by the petitioner which re- examined the drawings and designs in detail and submitted a report in December, 2021 stating that at least 88 months are required for completion of the project. The respondent agreed for extension of time till April, 2024 while in terms of the report of the IIT Madras of December, 2021, the project can be completed only by July, 2025.

14. Learned Senior Counsel for the petitioner has further argued that the Contract itself provides for extension of time for completion of Contract and for delayed damages and, therefore, time is not the essence of Contract and the Respondent cannot terminate the Contract but only claim liquidated damages in case of any delay in the execution of the Contract. The petitioner despite not having been paid his dues in the sum of ₹ 91,70,35,625/- for last six months, has continued to work on site and its 750 workmen and 80 engineers are presently working and its equipment worth more than 1000 crores of rupees is also on the site.

15. The petitioner for the last six months has written regularly by way of seven communications to the respondent seeking extension of the period for completion of work but has failed to receive any response from the respondent. It is argued that there cannot be any termination as time is not the essence of the Contract. It is further argued that the termination is not viable and is also not in national interest as the past conduct shows that tendering itself would take one year and the Contract in any case, would then not get concluded till April, 2025. Moreover, the costs would increase

Signature Not Verified Digitally Signed By:NIRMLA TIWARI

Signing Date:05.07.2022 14:24:17 threefold. The termination would also result in breaking of the execution of the Contract, which would only result in further delay in completion of the project of national significance. It is, therefore, submitted that the interim protection as sought against invocation of the Bank Guarantees, may be granted to the petitioner.

Arguments by learned Counsel for the Respondent:

16. Mr. Harish Vaidyanathan Shankar, learned Central Government Standing Counsel (CGSC), has asserted that the Contract relates to National Security as it is in respect of construction of Outer Harbour. The petitioner is in complete defiance since the year 2018 and has shown no seriousness for the completion of the work which maybe at the behest of third parties and raises serious concern.

17. It is claimed that the petition under Section 9 of the A&C Act, 1996 is not maintainable. Clause 20 of the Contract deals with Claims, Disputes and Arbitration. It provides that in case of any dispute, the parties may approach Dispute Adjudicatory Board (DAB) and only thereafter, the arbitration may be invoked in terms of Clause 20.6 of the Contract. The petitioner has not followed this procedure and no Certificate of Dissatisfaction has been issued by the DAB, but the petitioner has directly filed the petition under Section 9 of the A&C Act, 1996. The only circumstance in which the petitioner may approach for arbitration directly in terms of Clause 20.8 of the Contract is when DAB is not in existence but so is not the case. The petition under Section 9 of the A&C Act, 1996 is therefore, not maintainable.

18. Learned CGSC for the respondent has further argued that the date of completion of project was April, 2022 and the same has not been extended till date. The Minutes of Meeting dated 22nd November 2021 referred to

Signature Not Verified Digitally Signed By:NIRMLA TIWARI

Signing Date:05.07.2022 14:24:17 by the petitioner, clearly record that while petitioner‟s representative was seeking extension till April, 2024 in view of the report of December, 2021 of IIT Madras, the same was not agreed to by the Engineer representing the respondent. Moreover, the IIT Madras report on which the petitioner has vehemently relied for seeking extension of time for completion of Contract in fact, is not the report of the IIT Madras as an Institution.

19. Learned CGSC for the respondent has referred to its Letter dated 17th April, 2022 vide which the respondent sought clarification from IIT Madras about its Report of December, 2021 which was contradictory to its earlier Report of 2015 giving different timelines for completion of the project. IIT Madras vide its Letter dated 08th March, 2022 has clarified that the Professors of IIT Madras are competent to be engaged independently and to give their independent reports. Its earlier report of 2015 was prepared by the Institution on the basis of proof of check of Project Varsha and the reports were submitted by Professor R. Sundra Vadivelu and Professor Sannasiraj on behalf of IIT Madras which stands by its earlier Report of 2015. The report of December, 2021 has been independently prepared by Professor S. Nallayarasu based on the Data provided by the petitioner. It is, therefore, evident that the report of December, 2021 now being referred and relied upon by the petitioner is a private document prepared by the Professor who was engaged by the petitioner and is not the report of IIT Madras as an Institution as has been projected and vehemently argued. The report has been prepared by Professor S. Nallayarasu in individual capacity and is not binding on the respondent. Moreover, it has been specifically rejected by the respondent vide its Letter dated 08th March, 2022.

Signature Not Verified Digitally Signed By:NIRMLA TIWARI

Signing Date:05.07.2022 14:24:17

20. It is further submitted that from the letter of "Incurrence of additional Cost and Time" dated 28th October, 2021 addressed by the petitioner to the respondent it is evident that CDR International having worldwide expertise in design and Engineering services to give an assessment of technical and practical difficulties in progress of the Works. CDR engaged Prof. Van Der Meer, a world renowned expert and advisor to International projects on Breakwater Construction to validate the assessment Report. Professor S. Nallayarasu of IIT Madras was also asked to validate the report of CDR and the Report of Professor S. Nallayarasu is based on the documents submitted by the petitioner, without visiting to the site. The Report on which such heavy reliance has been placed by the petitioner, therefore is of no assistance to it. It is further argued that the Notice of Correction dated 03rd December, 2021 in terms of Sub-Clause 15.1 of the General Conditions of Contract, and a Notice of Delay Damages dated 03rd March, 2022 has already been served upon the petitioner in terms of Clause 15 of the Contract providing for "Termination by Employer."

21. It is, therefore, stated that the reliefs as sought by the petitioner do not come within the ambit of Section 9 of A&C Act, 1996 and the petition is liable to be dismissed.

22. Submissions heard.

DISCUSSIONS

23. At the outset it may be observed that the contract under consideration relates to the national security and defence. In the decision of Manohar Lal Sharma Vs. Narendra Damodar Dass Modi (2019) 3 SCC 25, the Apex Court highlighted the significance of the contracts pertaining to Defence Services and observed that adequate military strength and capability to

Signature Not Verified Digitally Signed By:NIRMLA TIWARI

Signing Date:05.07.2022 14:24:17 discourage and withstand external aggression and to protect the sovereignty and integrity of India is a matter of utmost concern for the Nation. The empowerment of defence forces with adequate technology and material support is, therefore, a matter of vital importance. The parameters of judicial review of administrative decisions with regard to Award of Tenders and Contracts are confined to the scrutiny of the decision making process on the parameters of unreasonableness and malafide. The Court should not exercise its power of judicial review even if a procedural error is committed to the prejudice of the Tenderer since private interests cannot be protected while exercising such judicial review.

24. In Reliance Airport Developers Pvt. Ltd. vs. Airport Authority of India (2006) 10 SCC 1 it was noted that certain areas of governmental activity, national security being the paradigm, the courts have regarded themselves as incompetent to investigate, beyond an initial decision as to whether the government‟s claim is bonafide. In this kind of non-justifiable area, judicial review is not entirely excluded, but is very limited.

25. In Siemens Public Communications Network Pvt. Ltd. vs. Union of India (2008) 16 SCC 215 the Apex Court emphasized that the triple ground on which the judicial scrutiny is permissible has been consistently held to be illegality, irrationality and procedural impropriety.

26. This Court must be circumspect in entertaining the present petition, considering that this project is of national significance dealing with the national security.

Termination of Contract:

27. The main argument raised on behalf of the petitioner is that disputes have arisen in regard to completion of the project within the given Timeline

Signature Not Verified Digitally Signed By:NIRMLA TIWARI

Signing Date:05.07.2022 14:24:17 which was April, 2022 and Notice of Delay Damages dated 15th February, 2022 has also been served upon the petitioner, but there can be no termination of contract since time was not the essence for performance of the contract and the work is still continuing on the site to which no objection has been taken by the Respondent. The main contention is that the contract itself provides for extension of time and for damages on account of delay which implies that time is not the essence of the Contract. Even if the time given in the Contract i.e. April, 2022 has expired the contract would not ipso facto come to an end, giving an occasion to the respondent to invoke the Bank Guarantee. Therefore, interim protection against invocation of Bank Guarantees has to be given in the given circumstances.

28. This aspect was considered in detail by the Apex Court in its decision in M/s Hind Contractors Vs. State of Maharashtra (1979) 2 SCC 70, and it was held that whether the time is the essence of the Contract would essentially be a question of the intention of the parties to be gathered from the terms of the Contract. Even when the parties have expressly provided that Time is the essence of the Contract, such stipulation would have be read along with the other provisions of the Contract and on construction and interpretation of the terms of the Contract, inference that completion of the work by a particular date was intended to be fundamental, may be excluded. For instance, if the Contract includes clauses providing extension of time in certain contingencies or for payment of fine or penalty for every day or week, the work undertaken remains unfinished on the expiry of the time provided in the contract, such clauses would be construed as rendering ineffective the express provision relating to the time being the essence of the Contract.

Signature Not Verified Digitally Signed By:NIRMLA TIWARI

Signing Date:05.07.2022 14:24:17

29. While learned Senior counsel for the petitioner had placed reliance on the Minutes of Meeting dated 01st December, 2021 in regard to Meeting held between the petitioners and the officers of respondent to claim that the respondent have agreed for the completion of the construction of Outer harbour by April, 2024, but the careful reading of the Minutes clearly reflect that this was the submission made by the petitioner/contractor but was not accepted by the respondents.

30. Significantly, in terms of Clause 15 dealing with Termination by Employer, the Notice of Correction dated 03rd December, 2021, has already been served upon the petitioner and the Notices of Delay Damages dated 3rd March, 2022 has also been served. However, it is fairly conceded that the contract has not been terminated and the petitioner is continuing with the work on the site. Moreover, admittedly a certified amount of ₹91,70,35,625/- is due to the petitioner, but has been withheld by the respondent on the ground that about Eleven Hundred Crores (₹1100,00,00,000/-) are recoverable from the petitioner. In these circumstances, it can be reasonably held that disputes in regard to the Contract have arisen between the parties.

31. It needs to be further examined whether petitioner is entitled to injunction against invocation of Performance Guarantees. The law in regard to injunctions for restraining invocation/ revocation of bank guarantee has been clearly laid down by the Apex Court in U.P. State Sugar Corporation vs. Surmac International Ltd. (1997) 1 SCC 568 wherein the principle was clearly enunciated that on the enforcement of a Bank Guarantee or a Letter of Credit in respect of Bank Guarantee which is sought to be encashed by a

Signature Not Verified Digitally Signed By:NIRMLA TIWARI

Signing Date:05.07.2022 14:24:17 beneficiary, the bank giving such guarantee is bound to honour it as per its terms irrespective of any dispute raised by its customer. It was held that the existence of any dispute between the parties to the Contract is not a ground to restrain the enforcement of Bank Guarantees. The only two exceptions recognized for grant of order of injunction are:

(i) fraud committed in the notice of the bank which would vitiate the very foundation of guarantee; and

(ii) injustice of the kind which would make it impossible for the guarantor to reimburse himself.

32. It was observed that except in these two circumstances, the court should not readily issue injunction to retrain the realization of the Bank Guarantee.

33. The Apex Court in Himadri Chemicals Industries Ltd. vs. Coal Tar Refining Company (2007) 8 SCC 2010 made a reference to the aforementioned judgment and concluded that since the Bank Guarantee or a Letter of Credit is an independent and a separate contract and is absolute in nature, existence of any dispute between the parties to the contract would not be a ground for issuing an order of injunction to restrain enforcement of bank guarantee.

34. The law is absolutely well defined and settled that there can be no injunction against invocation of a Bank Guarantee. However, the distinguishing factor is that admittedly the Performance Guarantees have not been invoked till date by the respondent and the work is still being done at the site by the petitioner. The question is whether the petitioner can be provided with some interim protection.

35. Similar facts as in the present case came up for consideration in

Signature Not Verified Digitally Signed By:NIRMLA TIWARI

Signing Date:05.07.2022 14:24:17 Hindustan Construction Company Ltd. vs. NHPC Ltd. O.M.P. 536 of 2014 decided by this Court on 30th May, 2014; Hindustan Construction Company Ltd. vs. NHPC Ltd. O.M.P. 536 of 2014 decided by this Court on 12th February, 2015; NHPC Ltd. vs. Hindustan Construction Company Ltd. FAO (OS) 131 of 2015 decided by the Division Bench of this Court on 28th May, 2015, wherein it was held consistently that where the bank guarantee has not yet been invoked by the respondent, the directions for prior Notice of certain days before invocation is not violative of the settled law prohibiting any injunction against revocation of bank guarantee. In these cases, it was categorically observed that the factum of notice of invocation of bank guarantee can be of no prejudice to the petitioner, since after giving such notice, it will be open to the respondent to proceed to invoke the bank guarantee subject to the petitioner seeking appropriate remedies. By providing for prior Notice, the respondent was not being injuncted from invoking the Bank Guarantee but merely some time was granted to the petitioner to seek its remedies in case the respondent sought to encash it. CONCLUSION

36. It was conceded on behalf of the respondent that the petitioner is continuing to work on the site even after April, 2022 and no express letter indicating termination of Contract has been served upon the petitioner. An ambivalent situation prevails wherein the respondent though has served Notice of Correction and the Delay Damages Notice, but has yet not served any Notice of termination or has notified the petitioner to stop the work at site after April, 2022. Therefore, as held in the cases of Hindustan Construction Limited (supra) that though invocation of Bank Guarantee cannot be prohibited or injuncted, it is held to be a fit case where the

Signature Not Verified Digitally Signed By:NIRMLA TIWARI

Signing Date:05.07.2022 14:24:17 respondent is directed to give a prior Notice of 15 days expressing his intention to revoke the Bank Guarantee before revocation of Bank Guarantees.

37. The petition under Section 9 of the A&C Act, 1996 is accordingly, disposed of.

I.A. 9857/2022 (U/S 151 of CPC, 1908 for ex-parte ad-interim stay) In view of the order passed above, the present application has become infructuous and stands disposed of, as such.

NEENA BANSAL KRISHNA, J (VACATION JUDGE)

JUNE 30, 2022 S.Sharma

Signature Not Verified Digitally Signed By:NIRMLA TIWARI

Signing Date:05.07.2022 14:24:17

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter