Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Tpf Engineering Pvt. Ltd & Anr. vs Union Of India, Ministry Of Road ...
2022 Latest Caselaw 1905 Del

Citation : 2022 Latest Caselaw 1905 Del
Judgement Date : 17 June, 2022

Delhi High Court
M/S Tpf Engineering Pvt. Ltd & Anr. vs Union Of India, Ministry Of Road ... on 17 June, 2022
                          $~44
                          *    IN THE HIGH COURT OF DELHI AT NEW DELHI

                          %                                        Date of Decision: 17th June, 2022

                          +      O.M.P.(I) (COMM.) 198/2022 & I.A. 9728-29/2022

                                 M/S TPF ENGINEERING PVT. LTD & ANR.       ..... Petitioners
                                               Through: Ms. Kanika Agnihotri, Advocate with
                                               Ms. Yashodhara Gupta, Ms. Snehal, Mr. Ankit
                                               Khera and Mr. Rohan Anand, Advocates.

                                                       versus
                                 UNION OF INDIA, MINISTRY OF ROAD
                                 TRANSPORT AND HIGHWAYS & ORS.          ..... Respondents

Through: Mr. Bhagvan Swarup Shukla, Central Government Standing Counsel with Ms. Kamaldeep and Mr. Sarvan Kumar, Advocates.

CORAM:

HON'BLE MS. JUSTICE JYOTI SINGH

JYOTI SINGH, J (ORAL)

1. This is a petition under Section 9 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the '1996 Act'), filed by the Petitioners praying for an interim order staying the operation of t h e im pugned n otice dated 30.04.2022 issued by Respondents No.1 & 2 (hereinafter referred to as the 'Respondents') seeking to terminate the Consultancy Agreement with the Petitioners.

2. The disputes between the parties emanate from the Contract Agreement dated 14.06.2017 executed between the Petitioners as 'Authority's Engineer' and the Respondents for the Work of Replacement of Superstructure of Existing Four-Lane Mahatma Gan dhi Set u over Gan ga

Signature Not Verified

Signing Date:21.06.2022 22:56:25 River in NH-19, Patna, Bihar, from 212.72 KM to 218.295 KM on Engineering, Procurement and Construction Mode.

3. Learned counsel appearing on behalf of the Petitioners challenging the impugned notice and seeking stay of its operation, raises several contentions, inter alia: (a) Respondents have issued stagewise completion cert ificate t o the Petitioners on being satisfied with the services rendered by them; (b) t h e action is malafide being initiated at the fag en d of t h e con tract wh en t he tenure of the contract has entered the phase of maintenance and the 60 months long contract was to be concluded in the next 17 days;

(c) conjoint reading of Clauses 2.8 and 2.9 of the Agreement establishes beyond certitude that the Petitioners were to be afforded an opportunity of remedying any defects/defaults, if any, prior t o n otice of su spension an d only on failure to remedy, a notice of termination of 60 days could be issu ed which has not happened in the present case since n o n otice of su spension was issued and no opportunity was given to remedy a purported failure;

(d) the report rendered by the Petitioners has been duly accepted by the Respondents; and (e) Completion Certificates dated 30.09.2020 and 16.03.2022 have been issued in favour of the Petitioners expressing satisfaction qua their work.

4. Lastly and emphatically, it was urged by the learned counsel that Clause 2.9.6 of the Consultancy Agreement provides that if either party disputes whether an event specified in paragraphs (a) t o (e) of Clau se GC 2.9.1 or 2.9.2 has occurred, such party may within 45 days aft er receipt of termination notice refer the matter to arbitration and this contract shall not be terminated on account of such event except in accordance with the t erms of any resulting arbitral award.

Signature Not Verified

Signing Date:21.06.2022 22:56:25

5. Relying on an order dated 29.04.2021, passed by a Co-ordinate Bench of this Court in Egis India Consulting Engineers Private Limited v. Pawan Hans Limited, in OMP(I)(COMM.) 148/2021 wherein, reliance was placed on an earlier order dated 22.10.2018 in M/s Eptisa Servicios De Ingeniera S.L. v. National Highways and Infrastructure Development Corporation Limited, in OMP(I)(COMM.) 371/2018, it is argued that based on a sim ilar clause in the Agreements before the said Courts, interim orders st aying t he operation of the impugned termination notices have been granted. It is submitted that the Agreement in the present case contains Clause 2.9.6 which contemplates resolution of disputes pertaining to termination of Agreement through arbitration and the Petitioners have invoked the arbitration clause within the stipulated period albeit on the 45th day.

6. Mr. Shukla, on the other hand, opposes the grant of interim relief on the ground that the Agreement in question is a determ inable con tract. Th e effect of breach of a contract by a party seeking to specifically en force t he contract under the Indian Law is enshrined in Section 16(c) read with Section 41(e) of the Specific Relief Act, 1963 and the latter provision clearly provides that injunction cannot be granted to prevent the breach of a contract, performance of which cannot be specifically enforced. Reliance is placed on the judgment of a Division Bench of this Court in Rajasthan Breweries Ltd. v. The Stroh Brewery Company, 2000 SCC OnLine Del 481.

7. It is further submitted that the impugned notice terminates the contract of the Petitioners and the Petitioners are no longer working on t he sit e an d thus even otherwise no interim order can be granted in t heir favour at t his stage, which fact is disputed by the learned counsel for t h e Petitioners by

Signature Not Verified

Signing Date:21.06.2022 22:56:25 filing an affidavit dated 17.06.2022 stating therein t hat t he Pet itioners are working on the site as on date and photographs to that effect have been annexed to the affidavit.

8. I have heard the learned counsel for the parties.

9. Issue notice.

10. Mr. Bhagvan Swarup Shukla, learned Central Government St anding Counsel accepts notice on behalf of Respondents No.1 & 2.

11. Let reply be filed within two weeks from today.

12. Rejoinder, if any, be filed before the next date of hearing.

13. Issue notice to Respondent No.3, through all permissible modes, returnable on 14.07.2022 before the Roster Bench.

14. There is no dispute on the proposition of law put forth by the learned counsel for the Respondents with respect to the provisions of t h e Specific Relief Act relied upon and ordinarily, this Court would not stay the operation of a termination notice under Section 9 of the 1996 Act which, n o doubt, would amount to directing a mandatory in junction. However, t his Court is persuaded to interdict the termination on the basis of Clause 2.9.6 of the Agreement which reads as follows:-

"2.9.6 Disputes about Events of Termination If either Party disputes whether an event specified in paragraphs (a) through (e) of Clause GC 2.9.1 or in Clause GC 2.9.2 hereof has occurred, such Party may, within forty-five (45) days after receipt of notice of termination from the other Party, refer the matter to arbitration pursuant to Clause GC 8 hereof, and this Contract shall not be terminated on account of such event except in accordance with the terms of any resulting arbitral award."

Signature Not Verified

Signing Date:21.06.2022 22:56:25

15. In this context, I may refer to an order passed by the Co-ordinate Bench in Egis India Consulting Engineers Private Limited (supra), wh ere a similar clause was under consideration and a petit ion u nder Sect ion 9 of the 1996 Act was filed seeking an interim order st aying t he t ermination. Interpreting Clause 2.9.6 GCC and relying on the order in M/s Eptisa Servicios De Ingeniera S.L. (supra), the Court observed t hat if on e reads Clause 2.9.6 carefully, it appears prima facie that issuance of a t erm ination notice does not ipso facto result in termination of the contractual relationship and if within 45 days of receipt of the notice, contractor refers the m atter t o arbitration, the contract shall not be terminated except in accordance wit h resulting in arbitral award and the parties have t hus crafted a prot ocol for termination of the contract. After so observing, the Court stayed the operation of the termination notice. Relevant paras are as under:-

"10. Mr. Nakul Dewan, learned senior counsel for the petitioner, has placed reliance on the judgment of a coordinate Bench of this court in Eptisa Servicios De Ingeniera S.L v. National Highways & Infrastructure Development Corp. Ltd. That, too, was a case in which interim stay of operation of an order of termination of the contract was sought on the ground that Clause 2.9.1 (a) of the GCC, in that case, which required providing a mandatory cure period to the contractor before terminating the contract, was not complied with. It was sought to be contended, by the respondent, before the Bench, that in a proceeding under Section 9 of the 1996 Act, an order of termination which had already taken effect could not be stayed. This court, nevertheless, held that the termination was, prima facie, violative of Clause 2.9.1(a) of the GCC (in that case), and, on that ground, granted stay of operation of the termination order, pending resolution of the dispute by arbitration.

11. Ordinarily, this court would not, in exercise of its jurisdiction under Section 9 of the 1996 Act, stay termination

Signature Not Verified

Signing Date:21.06.2022 22:56:25 which has already taken place, as that would amount to granting of a mandatory interlocutory injunction, directing the restoration of status quo ante. There can be no gainsaying that the order dated 13th April, 2021 does, in unequivocal terms, terminate the contract between the petitioner and the respondent.

12. Having said that, if one reads Clause 2.9.6 of the GCC carefully, it appears, prima facie, that issuance of a notice of termination does not ipso facto result in termination of the contractual relationship between the parties. The clause specifically provides that, if, within 45 days of receipt of notice of termination, the contractor refers the matter to arbitration, the contract "shall not be terminated on account of such event except in accordance with the terms of any resulting arbitral award". The parties have, therefore, ad idem, crafted a protocol in which, even after a notice of termination of the contract is issued, if the contractor refers the matter to arbitration, the termination of the contract would not take effect and would remain subject to the arbitral award which would come to be passed.

13. While, therefore, I am not entirely in agreement with Mr. Dewan's argument that the decision in Eptisa Servicios covers the present case, there is substance in Mr. Dewan's contention that even after a notice of termination has been issued by the respondent, the contract would not stand terminated, if the petitioner seeks resolution of the disputes by arbitration. In this case, the notice of termination was issued on 13th April, 2021. The petitioner, on 27th April, 2021, disputed the validity of the letter of the termination order of the decisions to terminate the contract and also sought reference of the disputes to arbitration. Prima facie, therefore, it would appear that, in such circumstances, Clause 2.9.6 of the GCC, would apply and, pending resolution of the dispute in arbitration and subject to the result of the arbitral award, the contract would continue to subsist.

                                 xxx            xxx        xxx



Signature Not Verified

Signing Date:21.06.2022
22:56:25

17. Till the next date of hearing, there shall be ad interim stay on operation of the impugned termination notice dated 13th 18. Subject to completion of pleadings, list for disposal on 20 April, 2021. The respondent shall stand restrained from acting on the basis of the said notice, including, inter alia, by way of invocation of the bank guarantees furnished by the petitioner."

16. In the present case, the impugned notice of termination is dated 30.04.2022 and the Petitioners have disputed the validity of t h e said n otice on several grounds and have invoked the arbitration agreement wit hin 45 days as envisaged in Clause 2.9.6, extracted above.

17. In view of the provisions of Clause 2.9.6 as well as the orders passed by the two Co-ordinate Benches of this Court as aforementioned, it is directed that till the next date of hearing, there shall be a stay on the operation of the impugned notice dated 30.04.2022.

JYOTI SINGH, J (VACATION JUDGE) JUNE 17, 2022/rk

Signature Not Verified

Signing Date:21.06.2022 22:56:25

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter