Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Gail( India) Limited vs Armtech (India) Limited
2022 Latest Caselaw 1961 Del

Citation : 2022 Latest Caselaw 1961 Del
Judgement Date : 4 July, 2022

Delhi High Court
Gail( India) Limited vs Armtech (India) Limited on 4 July, 2022
                               IN THE HIGH COURT OF DELHI AT NEW DELHI

                          %                                      Judgment delivered on: 04 July, 2022
                          +      O.M.P. (COMM) 20/2020

                          ARMTECH (INDIA) LIMITED                                  ..... Petitioner
                                                                 versus
                          GAIL (INDIA) LIMITED                                     ..... Respondent


                          Advocates who appeared in this case:
                          For the Petitioner            : Mr. Rajesh Gupta & Mr. Harpreet Singh,
                                                         Advs.
                          For the Respondent           : Mr. Vikas Mehta & Mr. Apoorv Khator,
                                                         Advs.

                                                                 AND

                          +      O.M.P. (COMM) 33/2020 and IA No. 779/2020

                          GAIL (INDIA) LIMITED                                     ..... Petitioner
                                                                 versus
                          ARMTECH (INDIA) LIMITED                                  ..... Respondent
                          Advocates who appeared in this case:
                          For the Petitioner            : Mr. Vikas Mehta & Mr. Apoorv Khator,
                                                          Advs.
                          For the Respondent           : Mr. Rajesh Gupta & Mr. Harpreet Singh,
                                                         Advs.

                          CORAM
                          HON'BLE MR JUSTICE VIBHU BAKHRU

                                                           JUDGMENT

Signature Not Verified Digitally Signed

Signing Date:04.07.2022 VIBHU BAKHRU, J

1. The aforesaid petitions are cross petitions under Section 34 of the Arbitration & Conciliation Act, 1996 (hereafter the 'A&C Act') impugning the Arbitral Award dated 24.09.2019 (hereafter the 'impugned award') rendered by an Arbitral Tribunal constituted of Justice (Retd.) V.K. Gupta as the Sole Arbitrator (hereafter the 'Arbitral Tribunal').

2. The impugned award was rendered in the context of the disputes that have arisen between the parties in connection with an Agreement dated 01.05.2012, whereby Armtech (India) Limited [petitioner in OMP(COMM) No.20/2020 - hereafter referred to as 'Armtech'] had agreed to execute the works relating to the "External Development and External Services for 100 Type B and 20 Type D Houses at Gain Gaon, Dibiyapur, Auraiya, Uttar Pradesh".

3. GAIL (India) Limited [petitioner in OMP(COMM) No.33/2020

- hereafter referred to as 'GAIL'], is a Government of India undertaking, inter alia, engaged in the business of distribution of natural gas, liquid hydrocarbons, LPG, manufacturing of petrochemicals etc. One of GAIL's manufacturing unit is located at Gail Gaon, Dibiyapur, District Auraiya, Uttar Pradesh.

                          4.     GAIL        issued       a      tender   [bearing     Tender          No.
                          GAIL/PA11/35611/3300043656/SKG                  (E-bid     No.8000003712]

inviting bids for executing the works of external development and external services for 100 Type B and 20 Type D houses at Gail Gaon.

Signature Not Verified Digitally Signed

Signing Date:04.07.2022

5. Pursuant to the aforesaid tender, Armtech submitted its bid. Armtech was declared as the successful bidder and accordingly GAIL issued a Fax of Acceptance (FOA) dated 01.02.2012. In terms of the FOA, the estimated value of the Contract was fixed at ₹17,47,91,942.51/-. The works in question were to be executed within a period of fifteen months commencing from the seventh day of the issuance of the FOA dated 01.02.2012.

6. On 03.02.2012, GAIL handed over the site in question to Armtech. Thereafter, on 28.03.2012, GAIL issued a Letter of Acceptance (LOA) awarding the Contract for executing the works in question to Armtech. The LOA issued by GAIL also included the Schedule of Rates and the description of the works to be performed by Armtech. Thereafter, on 01.05.2012, the parties entered into a formal agreement (hereafter 'the Contract').

7. In terms of the Contract entered into between the parties, Armtech furnished a Bank Guarantee dated 28.04.2012 for a sum of ₹1,74,79,200/-. The stipulated date for completion of the works was 07.05.2013. However, execution of the works was delayed.

8. Armtech sent a letter dated 25.04.2013 to GAIL seeking extension of nine months' time for completion of the works in question. This request of Armtech was acceded to and by a letter dated 06.05.2013, GAIL provisionally extended the time for completion of the Contract till 06.06.2013. Similarly, further extensions were sought by Armtech and the same were granted by

Signature Not Verified Digitally Signed

Signing Date:04.07.2022 GAIL from time to time. GAIL granted the last extension by its letter dated 19.12.2015 extending the terms of the Contract upto 20.02.2016.

9. Since the work was not completed by Armtech within the extended period granted by GAIL, that is, upto 20.02.2016, GAIL issued a Show Cause Notice dated 03.03.2016 alleging that Armtech had failed to complete the works despite several opportunities. It further put Armtech to notice that if the balance work was not completed within fifteen days from the date of issue of the Show Cause Notice dated 03.03.2016, the Contract entered into between the parties would be terminated by GAIL and the balance work would be carried out at Armtech's risk and costs. Armtech responded by a letter dated 04.03.2016 assuring GAIL that it would complete the balance works. Armtech also expressed its opposition to GAIL's contention that the balance work would be executed at the risk and cost of Armtech.

10. On 27.04.2016, GAIL issued a Full and Final Notice to Armtech, inter alia, stating that the balance work would be executed at the risk and costs of Armtech in terms of the Contract.

11. Armtech issued a letter dated 06.08.2016, whereby it submitted its Action Plan for completing the remaining works. However, since Armtech had failed to execute the balance work within the stipulated period, GAIL invoked the two Bank Guarantees aggregating a sum of ₹1,99,79,200/- [Bank Guarantee No.1509ILG000814 dated 13.03.2014 for a sum of ₹25,00,000/- and Bank Guarantee No.

Signature Not Verified Digitally Signed

Signing Date:04.07.2022 1509ILG002012 dated 28.04.2012 for a sum of ₹1,74,79,200/-]. Thereafter, GAIL issued a letter dated 21.10.2016 terminating the Contract entered into between the parties in terms of Clause 29.1(a) of the General Conditions of Contract (GCC).

12. GAIL awarded the balance unexecuted work to other contractors viz. M/s Awasthi Traders, M/s Yes Engineering and M/s. Asiatic Electrical & Switchgear Pvt. Ltd.

13. In view of the disputes between the parties, Armtech invoked the Arbitration Agreement and sought reference of the disputes to arbitration.

14. The tabular statement indicating the claims raised by Armtech in its Statement of Claims is set out below:

                                "S.    Claims                    Particulars                     Amount
                                No.
                                 1. CLAIM NO.1       Claim on account of RA Bill No. 37       1,00,56,330.25/-
                                 2. CLAIM NO.2       Claim on account of bank                 2,00,00,000/-
                                                     guarantees      extra    contractually
                                                     encashed
                                3.     CLAIM NO.3    Claim on account of pending              79,17,534/-
                                                     retention money
                                4.     CLAIM NO.4    Claim on account of incorrectly          79,17,534/-
                                                     imposed penalty
                                5.     CLAIM NO.5    Claim on account of amount held up       5,00,000/-
                                                     against electrical panel
                                6.     CLAIM NO.6    Claim on account of tools and plants     2,76,59,609/-
                                                     detained at site
                                7.     CLAIM NO.7    Claim on account of delay and its        1,35,60,500/-
                                                     consequences
                                8.     CLAIM NO.8    Claim on account of admitted             80,46,734/-
                                                     outstanding      balance     as    on
                                                     31.03.2016
                                9.     CLAIM NO.9    Claim on account of interest from        Based on actual
                                                     date of accrual upto date of payment     calculation
                                                     @18% per annum



Signature Not Verified
Digitally Signed

Signing Date:04.07.2022
                                 10.    CLAIM NO.10   Claim on account of costs                 5,00,000/-
                                11.                  TOTAL                                     9,61,58,241.25"


15. GAIL also raised certain counter-claims. The tabular statement indicating the said counter-claims is set out below:

                                "S.      Counter                  Particulars                     Amount
                                No.       Claims
                                 1.      Counter     Price reduction on account of non- 87,39,597/-
                                        Claim No.1   performance of claimant as per
                                                     clause 27 GCC
                                2.       Counter     Claim on account of pending house 2,15,394/-

Claim No.2 rent, electricity and water charges of house no.1348, Nehru Kunj, GAIL Gaon.

3. Counter A. Claim on account of balance road 12,70,404.69/-

Claim No.3 work executed through another contractor including checklist jobs.

B. Claim on account of balance earth-

9,54,976.88/-

work executed through another contractor including checklist jobs.

C. Claim on account of balance 2,82,695/-

electrical work in sub-station constructed.

4. Counter Claim on account of site office at 12,21,000/-

Claim No.4 pump house, temporary sheds, labour hutments etc. within GAIL Gaon premises TOTAL 1,26,84,067.57"

16. The Arbitral Tribunal delivered the impugned award on 24.09.2019. The Arbitral Tribunal held that both the parties were responsible for the delay in execution of the Contract to some extent but after a certain stage, the delay in execution of the works was entirely for reasons attributable to Armtech. The Arbitral Tribunal also held that GAIL had no option but to terminate the Contract in

Signature Not Verified Digitally Signed

Signing Date:04.07.2022 question. Notwithstanding the said findings, the Arbitral Tribunal partly allowed some of the claims made by Armtech and rejected all counter-claims raised by GAIL. A tabular statement indicating the claims allowed by the Arbitral Tribunal is set out below:

                                 "S.       Claims                       Particulars
                                 No.
                                  1.     Claim No.2     Allowed to the extent of Rs.1,74,79,200.00/
                                  2.     Claim No.3     Allowed to the extent of Rs.30,00,000.00/
                                  3.     Claim No.4     Allowed to the extent of Rs.73,55,229.00/
                                  4.     Claim No.5     Allowed to the extent of Rs.5,19,809.00/"


17. GAIL is aggrieved by the impugned award to a limited extent. It does not impugn the impugned award rendered by Arbitral Tribunal in respect of Armtech's Claim No.2. It has confined its challenge to the impugned award to the extent that the Arbitral Tribunal has partly allowed Armtech's Claim Nos.3 and 5 and dismissed its counter- claims.

18. Armtech has assailed the impugned award to the extent that Arbitral Tribunal has rejected its Claim Nos.1 and 8 and further confined the interest awarded from the date of the submission of claim and not from the date of cause of action.

19. Given the nature of the allegations made before this Court, this Court considers it apposite to consider the respective challenge of the parties claim wise.

GAIL's Challenge to the Impugned Award [O.M.P.(COMM.) 33/2020]

Re: Claim No.3

Signature Not Verified Digitally Signed

Signing Date:04.07.2022

20. Armtech claimed that GAIL had deducted an amount equal to 5% of the value of the electrical material supplied by it and retained the same. It contended that the total value of the electrical material supplied was ₹6,17,00,447/- and against the said amount, GAIL withheld a sum of ₹30,85,022/- towards retention money. Armtech claimed that it is entitled to a sum of ₹30,00,000/-. GAIL disputed the said claim of Armtech and it contended that it had not deducted any amount from the running bills. GAIL claimed that extensions were granted subject to imposition of Price Reduction Schedule (PRS) in terms of Clause 27 of the GCC. The Arbitral Tribunal found that in terms of Clause 15A(iv)(ii)(d) of the Contract, 5% of the value of the electrical material was to be withheld towards retention money. The same was to be released after completion of the works. The Arbitral Tribunal accepted GAIL's contention that it had withheld a sum of ₹30,82,002/- in terms of the said clause. However, since Armtech's claim was limited to a sum of ₹30,00,000/-, the Arbitral Tribunal awarded the same.

21. Mr. Mehta, learned counsel appearing for GAIL contends that GAIL had not withheld any amount except on account of PRS. The Arbitral Tribunal has accepted Armtech's claim towards imposition of PRS, which was in the nature of liquidated damages (Claim No.4), and had awarded an amount of ₹73,55,229/- against Claim No.4. Thus, the amount retained by GAIL on account of PRS has been separately awarded in favour of Armtech. Therefore, the impugned award against Claim no.3 amounted to awarding the same claim twice over.

Signature Not Verified Digitally Signed

Signing Date:04.07.2022

22. Mr. Gupta, learned counsel appearing for Armtech disputed the said contention. He stated that the amount of ₹30,00,000/- had been withheld separately from the bills relating to supply of electrical items. This dispute is clearly a factual dispute. The Arbitral Tribunal is a final adjudicator of questions of fact and such findings of the Arbitral Tribunal cannot be interfered with in these proceedings. However, this Court finds that the Arbitral Tribunal has not considered the issue whether in fact any amount has been withheld by GAIL against payments for electrical items. This Court had also asked the learned counsels for the parties to establish from the records whether in fact any amount had been withheld from the bills of electrical items. None of the counsels for the parties has been able to clearly establish whether any amount had been withheld. It appears that the Arbitral Tribunal has proceeded solely on the basis that Clause 15A of the Contract in question provided that 5% of the value of electrical items would be withheld towards retention money. A decision on this dispute would require reconciliation of the accounts. However, the impugned award does not indicate that any such exercise was conducted and if so whether the Arbitral Tribunal was satisfied that an amount of ₹30,85,022/- was, in fact, withheld by GAIL towards retention money. According to GAIL, it had withheld certain amounts, however, the same was solely on account of PRS. GAIL claims that in all it had retained a sum of ₹73,55,026/- towards PRS which was separately awarded in favour of Armtech.

Signature Not Verified Digitally Signed

Signing Date:04.07.2022

23. Since the issue whether, in fact, an amount of ₹30,00,000/- is included in the sum of ₹73,55,026/-, which has been awarded in favour of Armtech has not been decided by the Arbitral Tribunal, this Court is of the view that the impugned award against Claim No.3 is liable to be set aside.

Re: Claim No.4 and Counter-Claim No.1

24. Armtech's Claim No.4 and GAIL's Counter-Claim No.1 are connected as they relate to levy of PRS. In terms of Clause 27 of the GCC as applicable, the Contract Price is liable to be reduced by half percent for every week on delay in completing the Contract, subject to maximum of 5% of the total Contract price. According to GAIL, the execution of the Contract was delayed by forty months. GAIL states that Armtech is responsible for the said delay, therefore, a sum of ₹87,39,597/- towards 5% of the Contract value of ₹17,47,91,942/- is liable to be deducted from the amount payable to Armtech. GAIL stated that an amount of ₹48,60,138/- was withheld towards PRS till payment of the 36th RA bill. In addition, GAIL had also encashed the Bank Guarantee for a sum of ₹25,00,000/- which it stated was against PRS. Thus, admittedly GAIL had recovered a sum of ₹73,60,138/- against levy of PRS. Therefore, GAIL claimed a further sum of ₹13,79,459/- (₹87,39,597/- less ₹73,60,138/-) towards PRS (Counter- Claim No.1). Armtech claimed that it was not liable to pay PRS as it was not responsible for the delay in executing the works. Armtech claims that the same was either for reasons beyond its control and / or attributable to GAIL. Thus, it claimed refund of the amount withheld

Signature Not Verified Digitally Signed

Signing Date:04.07.2022 by GAIL. The Arbitral Tribunal held that GAIL was not entitled to levy PRS and therefore, awarded a sum of ₹73,60,138/- in favour of Armtech.

25. Mr. Mehta, learned counsel appearing for GAIL contended that the issue whether GAIL was liable to impose PRS is based entirely on the question as to which party had delayed the execution of the Contract. He submitted that although the Arbitral Tribunal had found that Armtech was responsible for the delay, however, despite the said finding, the Arbitral Tribunal held GAIL was not entitled to recover PRS. He submitted that the Arbitral Tribunal's conclusion is inconsistent with the findings and therefore, the impugned award is liable to be set aside.

26. Mr. Gupta, learned counsel appearing for Armtech countered the aforesaid submissions. He submitted that there is no inconsistency in the impugned award. He further submitted that the findings of the Arbitral Tribunal must be read in the correct perspective. He submitted that the Arbitral Tribunal had found that GAIL was responsible for the initial delay dated May, 2014 and Armtech was held to be responsible for the delay thereafter. The Arbitral Tribunal had found that GAIL was not responsible for the delay after a particular point of time. Therefore, the Arbitral Tribunal had balanced the impugned award and had rejected GAIL's claim for liquidated damages.

Signature Not Verified Digitally Signed

Signing Date:04.07.2022

27. The Arbitral Tribunal had examined the question of delay and recorded its findings at the outset. The said findings were repeated verbatim while discussing the other claims. The relevant passage recording the Arbitral Tribunal's finding with respect to which party was responsible for the delay is set out below:

"........I shall determine the issue of delay first and then proceed to determine if the termination of the contract was validly done.

a) Determining the Responsibility of Delay: Both the parties admit to the fact that there was delay in the execution of the work and that time extensions, even if these were provisional, were granted by the respondent to the claimant. The dispute however, remains as to which of the two parties is responsible for the delay and the apportionment of the delay, if possible.

Both the parties have drawn my attention to the various minutes of meetings dated 21.05.2012, 06.07.2012, 11.09.2012 and 06.10.2012 (Annexure R-6 (colly)) wherein there are certain shortfalls on part of both the parties. The shortfalls are of the nature which would delay the execution of work and therefore it appears that the delay in the execution of work was partially on account of both the parties. The respondent relied upon letter dated 19.06.2015 alleging that the claimant had in fact admitted to the validity of the levy of PRS by the respondent. However, a scrutiny of the said letter reveals that the claimant did not at any point of time agree to the levy of PRS but simply requested the respondent to affect the recovery from the final bill. There is no concession given

Signature Not Verified Digitally Signed

Signing Date:04.07.2022 to the respondent on the merits of levy of PRS. The respondent has also not been able to explain the reason why the decision on the external earth was given to the claimant as late as in May 2014. It weighs very heavily on my mind that the work to be executed under the contract is about the external development of the township, which relies critically on the earth work. In fact, without adequate earth being available, it is impossible to complete the work. I have also observed that the work claimed to have been done on the risk and cost of the claimant by the respondent majorly consists of earth work and road work. Both of these activities require earth work. During the cross examination, RWI has admitted that the source of earth was ultimately communicated by the respondent to the claimant and the same was about 10 kms away from the site of work. Therefore the averment of the claimant about inadequacy of the available earth leading to delay appears plausible and acceptable.

The respondent has strongly relied on letter dated 27.04.2016(Annexure R-17) which it claims was the final notice issued by it to the claimant. A bare perusal of this document would reveal that it did set timeline for rectification and therefore, succeeds to qualify as a valid show cause notice. Ultimately, the respondent terminated the contract of the claimant on 21.10.2016 (Annexure R-20). However, the same was objected to by the claimant on 24.10.2016 while pointing out the various flaws on part of the respondent.

The respondent has shown adequate record to demonstrate that the delay was mainly on part of the claimant. Actually; the Claimant can be said to be

Signature Not Verified Digitally Signed

Signing Date:04.07.2022 responsible for the delay in its entirety after a particular period of time and for that period of time, the Respondent cannot be held responsible at all for causing the delay. For the major part, therefore I hold the Claimant responsible for the delay which took place in the execution of the contract work and ultimately resulted in the contact being terminated.

b) Validity of Termination of the Contract: It is an undisputed fact that the contract has been terminated by the respondent and as a consequence thereof, the respondent has now raised some counterclaims against the claimant as well. It is the contention of the claimant that the termination of the contract has been wrongly done and thus the respondent could not have acted against it, leading to the balance work being done on the risk and cost of the claimant.

The primary reason for the termination of the contract, as averred by the respondent was that the work was being delayed by the claimant.

However, the claimant has alleged that the decision, drawings, payments etc. were pending as a result of which the work under the contract could not be completed and the respondent took advantage of this and terminated the contract. I do not agree. In my considered opinion, under the circumstances, the Respondent had no option but to terminate the contract because it had become clear that the Claimant was not in any position to complete the work."

28. It is clear from the above that the Arbitral Tribunal had found that both the parties were responsible for the delay to some extent. It also appears that the Arbitral Tribunal had held GAIL responsible for the delay in rendering a decision regarding external earth. Admittedly,

Signature Not Verified Digitally Signed

Signing Date:04.07.2022 sand mining had been proscribed in the State of Uttar Pradesh and therefore, either sand for earth filling was required to be procured from outside the State or in the alternative earth filling work was to be performed by other types of soil. The decision regarding the site from where earth could be excavated was therefore, vital for execution of the works. The Arbitral Tribunal had found that there was delay on the part of GAIL in taking the said decision, which was communicated in May, 2014. However, there were other reasons as well, which had also contributed in the delay in completion of the project. The Arbitral Tribunal had accepted Armtech's contention that the delay was largely attributable to the inadequacy of the available earth. But it has also returned a finding that Armtech was "responsible for the delay in its entirety after a particular period of time".

29. The Arbitral Tribunal had further emphasized that for the major part, Armtech was responsible for the delay in execution of the work. Notwithstanding the aforesaid, the Arbitral Tribunal had accepted Armtech's claim that GAIL was not entitled to levy PRS. A perusal of the impugned award indicates that Arbitral Tribunal had referred to various decisions and its reasons for allowing Armtech's claim and disallowing GAIL's, can be discerned from the discussion regarding the said decisions.

30. The Arbitral Tribunal has referred to the decision in NCT of Delhi v. R.K. Construction Company: (2003) 1 ALR 465 (Delhi) and on the strength of the said decision had held that liquidated damages have been wrongly levied as there was no notice indicating the

Signature Not Verified Digitally Signed

Signing Date:04.07.2022 timelines for such levy. Further the Arbitral Tribunal had referred to the decision in the case of B.W.L. Ltd. V. MTNL: (2000) 2 ALR 190 (Delhi) and had observed that PRS had not been validly levied as there was no specific order levying the PRS. The Arbitral Tribunal had also referred to Beebcon Engineers Pvt. Ltd v. Bharat Heavy Electricals Ltd.: (2006) 1 ALR 194 (Delhi) and had concluded that since both the parties are responsible for the delay in execution of the work, liquidated damages ought not to have been levied. In addition to the above, the Arbitral Tribunal had also referred to Indian Oil Corporation v. Llyod Steel Industrial Limited: (2007) 4 ALR 84 (Delhi) and observed that GAIL had failed to demonstrate any tangible legal loss on account of delay and therefore, levy of liquidated damages was illegal. The Arbitral Tribunal had also referred to the decision in Bipromasz Bipron Trading SA vs. Bharat Electronics Limited: (2012) 3 ALR 1 SC and held that levy of liquidated damages is illegal and no order indicating the same has been issued by GAIL.

31. It is clear from the impugned award that the Arbitral Tribunal's decision to reject the levy of PRS is not premised solely on the basis of which party is responsible for the delay but other considerations as well. Admittedly, no specific timelines have been specified after the lapse of which liquidated damages were levied. According to GAIL, Armtech was responsible for the entire delay of forty months. This contention has been rejected by the Arbitral Tribunal. The Arbitral Tribunal also found that GAIL was responsible for a part of the delay on account of the belated decision regarding external earth work. It

Signature Not Verified Digitally Signed

Signing Date:04.07.2022 was also Armtech's contention that substantial delays have been caused as it was required to source earth from a distance of ten kms. The Arbitral Tribunal found merit in the said contention.

32. The decision of the Arbitral Tribunal that GAIL was required to demonstrate the legal loss or injury suffered by it and had failed to do so is erroneous. The Contract related to works for extending facilities to employees of GAIL and is doubtful whether GAIL was required to provide any tangible measure for such losses. However, at the same time, it also does not appear that GAIL had taken any unequivocal stand that it was not possible to prove actual loss and the liquidated damages were a genuine pre estimate of the loss suffered by it.

33. At this stage, it is necessary to recall that this Court is not required to examine the impugned award as the first appellate court sitting in appeal over the decision of the Arbitral Tribunal. The scope of challenge under Section 34 of the A&C Act is limited. This Court is unable to accept that the conclusion of the Arbitral Tribunal is perverse and vitiates the impugned award on the ground of patent illegality.

34. The Arbitral Tribunal has wide discretion in deciding the disputes. Clearly some of the reasons provided by the Arbitral Tribunal in support of its conclusion are plausible reasons. Therefore, this Court is of the view that given the standards of examination under Section 34 of the A&C Act, no interference is called for with the decision of the Arbitral Tribunal.

Signature Not Verified Digitally Signed

Signing Date:04.07.2022 Re: Claim No.5

35. The Arbitral Tribunal awarded a sum of ₹5,19,809/- in favour of Armtech and it found that GAIL had withheld the said amount from the amounts due against supply of HT electrical panel. Admittedly, the value of the said HT electrical panel was ₹35,19,809/- and GAIL had paid an amount of ₹30,00,000/-. Undisputedly, GAIL was liable to pay the balance amount of ₹5,19,809/-. GAIL claimed that in terms of the understanding between the parties, the said payment was to be made directly to the vendor (M/s Asiatic Electrical and Switchgear Pvt. Ltd.) who had supplied the said HT electrical panel.

36. There is no dispute that GAIL had issued the letter of comfort to the vendor in question confirming that it would pay the amount. GAIL had thereafter paid a sum of ₹30,00,000/- to the said vendor. The dispute is confined to the balance amount of ₹5,19,809/-. GAIL claimed that it had retained an amount of ₹5,24,113/- and had remitted the same to the vendor on 20.11.2017. Armtech had disputed that GAIL had paid any further amount to the vendor in question against the supply of HT electrical panel. The Arbitral Tribunal found that GAIL had failed to establish that it had paid any part of the withheld amount to the vendor against the supply of electrical panel. The fact that GAIL had made any further payments to the vendor in question, failed to persuade the Arbitral Tribunal that it had paid the withheld amount of ₹5,24,113/- as GAIL had other transactions with the said vendor and there is no material to establish that the amount of

Signature Not Verified Digitally Signed

Signing Date:04.07.2022 ₹5,24,113/- had been paid by GAIL against the supply of electrical panel.

37. GAIL has assailed the said finding as, ex facie, erroneous. Mr. Mehta, learned counsel appearing for GAIL has been unable to point out any material and / or document on record indicating that GAIL had made payment for supply of electrical panel to the vendor in question. Merely showing certain remittances would in the facts and circumstances of the case not be dispositive of the question whether GAIL had made any further payments in respect of supply of HT electrical panel.

38. Mr. Mehta also contended that the Arbitral Tribunal had erred in not appreciating that in any event Armtech was not entitled to any payment against supply of electrical panel as the said payments were required to be made directly to the vendor (M/s Asiatic Electrical and Switchgear Pvt. Ltd.). The said contention is unpersuasive. The vendor had supplied the electrical panel at the instance of Armtech. Armtech would be liable to pay the consideration for the HT electrical panel notwithstanding GAIL had issued a letter of comfort. GAIL was also unable to show any invoice raised by the vendor against GAIL in respect of supply of the HT electrical panel in question. Therefore, the contention that GAIL was not liable to pay any amount to Armtech against supply of HT electrical panel is unpersuasive. This Court finds no ground to interfere with the decision of the Arbitral Tribunal to award a sum of ₹5,19,809/- in favour of Armtech. The Arbitral Tribunal awarded the said amount as claimed by Armtech

Signature Not Verified Digitally Signed

Signing Date:04.07.2022 notwithstanding the fact that GAIL had claimed that the balance withheld amount was marginally higher - ₹5,24,113/-.

GAIL's Counter-Claim No.2

39. GAIL had claimed a sum of ₹2,15,394/- towards house rent, electricity and water charges for the premises bearing House No.1348, Nehru Kunj, Gail Gaon occupied by Armtech. The said premises was allotted to Armtech as residential accommodation to facilitate the execution of the work. Armtech had paid an amount of ₹1,44,752.44/- for the period upto 30.06.2017. GAIL claimed that an amount of ₹1,88,265/- was payable upto the said date and in addition, Armtech was also liable to pay house rent at the rate of ₹9,043/- per month with effect from 01.07.2017 till 30.09.2017. The Arbitral Tribunal found that Armtech was not at site and the possession of the entire premises was under control of GAIL. Thus, it held that there was no impediment for GAIL to take over the premises in question. In the circumstances, the Arbitral Tribunal rejected GAIL's claim.

40. Mr. Mehta, learned counsel appearing for GAIL contended that Arbitral Tribunal has erred in rejecting the claim made by GAIL as it was established that certain materials and tools belonging to Armtech were lying at site. Armtech had also made a claim in this regard. He further submitted that the finding that Armtech was not occupying any part of the area is, therefore, erroneous.

41. This Court is unable to accept that the decision of the Arbitral Tribunal is perverse or, ex facie, erroneous. According to GAIL,

Signature Not Verified Digitally Signed

Signing Date:04.07.2022 Armtech had abandoned the work in December, 2015. There is no dispute that GAIL was in control of the overall security of the area. In view of the above, the decision of the Arbitral Tribunal warrants no interference in these proceedings.

Re: GAIL's Counter-Claim Nos.3(a), 3(b) and 3(c)

42. GAIL had raised a counter-claim in respect of the amounts incurred by it for execution of the remaining works. GAIL claims that it had incurred an amount of ₹60,29,720.34/- for execution of the remaining road work. The contract for the same was awarded to M/s Awasthi Traders. In terms of the Contract between the parties, GAIL was liable to pay a sum of ₹54,76,743.70/- to Armtech for the said works. GAIL claimed the differential between the two amounts - that is, between ₹60,29,720.34/- and ₹54,76,743.70/- - and in addition claims a further markup of 10% as overhead expenditure. GAIL computed the amount against execution of the works at ₹11,55,948.68/-. Similarly, GAIL claimed an amount of ₹1,14,456.01/- towards completion of pending checklist for road works. Thus, in aggregate GAIL claimed an amount of ₹12,70,404.69/- for execution of the balance road works through another contractor viz. M/s Awasthi Traders. Similarly, GAIL also claimed a sum of ₹9,54,976.88/- for pending earth work along with cost incurred for the checklist jobs and ₹2,82,695/- for execution of certain electrical works.

Signature Not Verified Digitally Signed

Signing Date:04.07.2022

43. The Arbitral Tribunal rejected the aforesaid claim as it found that GAIL had not prepared the Final Bill. The Arbitral Tribunal concluded that since the Final Bill had not been prepared, it was difficult to understand as to how GAIL had computed the balance quantities. Further, the Arbitral Tribunal also found that no evidence was brought on record at the appropriate time to reflect that the amount as claimed had, in fact, been paid.

44. Mr. Mehta, learned counsel appearing for GAIL contended that in terms of the Contract between the parties, GAIL was entitled to recover the additional amount incurred for executing the remaining work at the risk and costs of Armtech. He contended that since the Arbitral Tribunal had found that the termination of the Contract was valid, the necessary consequences - which included GAIL's right to have the balance work executed at the risk and costs of Armtech - followed.

45. The aforesaid contention is not persuasive. The Arbitral Tribunal has not rejected GAIL's claim on the ground that it was not entitled to get the remaining works executed at the risk and costs of Armtech; it has rejected GAIL's claim on the ground that GAIL had failed to substantiate the quantification of its claim. The Arbitral Tribunal held that since GAIL had not prepared the Final Bill, it was difficult to compute the additional quantity of work that was required to be executed. The Arbitral Tribunal faulted GAIL for not establishing its claim. This Court finds no ground to interfere with the decision of the Arbitral Tribunal to reject GAIL's counter-claim

Signature Not Verified Digitally Signed

Signing Date:04.07.2022 against amounts incurred by it for getting the balance work executed at the risk and costs of Armtech.

Re: GAIL's Counter-Claim No.4

46. GAIL had claimed a sum of ₹1,21,000/- from Armtech for occupying certain area within the Gail Gaon premises. GAIL claimed that Armtech had occupied approximately 15000 sq.ft. area for providing labour hutments, temporary sheds and site office. GAIL claimed that since it was deprived of utilizing the said area, Armtech was responsible to compensate GAIL for the same. GAIL quantified its claim at ₹1,00,000/- per month from the date of termination of the Contract till handing over of possession (that is, from 21.10.2016 till 20.09.2017). In addition, GAIL claimed an amount of ₹1,21,000/- for occupation of pump house building at the rate of ₹11,000/- per month for the aforesaid period.

47. The Arbitral Tribunal found that Armtech was no longer at site and since the entire area was under the overall security of GAIL, there was no impediment for GAIL to use the said area.

48. This Court does not find the aforesaid reasoning to be implausible or one that no reasonable person could possibly accept. The decision of the Arbitral Tribunal is not impeachable as none of the grounds set out in Section 34 of the A&C Act are established.

49. In view of the above, this Court finds no merit in GAIL's petition and the same is liable to be dismissed.

Signature Not Verified Digitally Signed

Signing Date:04.07.2022 Armtech's challenge to the impugned award [O.M.P.(COMM.) 20/2020]

50. Armtech's challenge to the impugned award is confined to rejection of its Claim No.1 and Claim No.8. Armtech has also challenged the decision of the Arbitral Tribunal to award interest from the date of claim and not from the date on which cause of action has arisen.

Re: Armtech's Claim No.1

51. Armtech had claimed that it was entitled to a sum of ₹1,00,05,633.25/- being the amount invoiced under RA Bill No.37. GAIL had not paid any amount against the aforesaid bill for the work done upto the 36th RA bill. Armtech claimed that there was no dispute that it had executed the works beyond the works as invoiced under the 36th RA bill and was entitled to be paid for the same. It claimed that about 85% of the total work was executed upto the 36th RA bill (amounting to ₹14,71,04,580/-). The work of ₹1,76,87,362/- remained, out of which Armtech had executed works for a sum of ₹1,00,05,623.25/-. GAIL had disputed the said bill and claimed that the same was fictitious. GAIL stated that it had not received the 37th RA bill at the material time. GAIL claimed that it had received the 37th RA bill along with a letter dated 22.01.2017 forwarding therewith the letter dated 01.10.2016. The Arbitral Tribunal had examined the rival contentions and concluded that Armtech had failed to establish the work executed as claimed.

Signature Not Verified Digitally Signed

Signing Date:04.07.2022

52. Admittedly, the works were neither executed nor measured. GAIL's claim for risks and costs was also denied by the Arbitral Tribunal on the same ground. Admittedly, GAIL had issued a notice calling upon Armtech to participate in joint measurements. GAIL states that despite receipt of the notice, Armtech had not come forward for the measurements. Armtech on the other hand claimed that its representative was prevented by the security personnel. Admittedly, there is no material on record to clearly establish the works executed by Armtech after the 36th RA bill.

53. Mr. Gupta, learned counsel appearing for Armtech contended that there was enough material on record for the Arbitral Tribunal to make a reasonable assessment of the work done. He submitted that the Arbitral Tribunal "ought to have applied rational guess work which was arithmetically possible". He submitted that since 85% of the works were executed, there is no dispute that works valued at approximately ₹1,76,87,362/- remained to be executed. Since GAIL claims to have got the work valued at ₹83,99,885/- executed through other agencies, it is apparent that Armtech would have executed the work amounting to approximately ₹1,00,00,000/-.

54. The onus to establish that it had executed the works as claimed rested on Armtech. Armtech could have discharged the said onus by producing primary documents. However, Armtech appears to have relied predominantly on the 37th RA bill. As noted above, GAIL had disputed receipt of the said bill at the material time and further contended that the abstract of the work done was manipulated. In the

Signature Not Verified Digitally Signed

Signing Date:04.07.2022 given circumstances, the decision of the Arbitral Tribunal to reject Armtech's claim on the ground that it had failed to establish the same cannot be interfered with. The said finding has been returned by the Arbitral Tribunal after evaluation of the material and evidence on record. It is well settled that an Arbitral Tribunal is the final adjudicator on the quantity and quality of evidence. This Court finds no ground to interfere with this decision in these proceedings.

Re: Armtech's Claim No.8

55. Armtech claimed an amount of ₹80,46,734/- from GAIL. Armtech had premised the said claim on the basis of a letter of confirmation dated 09.04.2016 whereby GAIL had confirmed the outstanding balance as on 31.03.2016. Armtech claimed that the said amount was due and payable to it but GAIL had withheld the same without any reason.

56. GAIL disputed the said claim on the ground that the letter relied upon did not reflect the amounts due and payable to Armtech. GAIL claimed that the said letter reflected the amounts recorded in its books in anticipation of pending works in relation to various projects.

57. The Arbitral Tribunal rejected Armtech's claim as it found that GAIL explanation was reasonable.

58. Mr. Gupta, learned counsel appearing for Armtech contended that GAIL's stand is, ex facie, erroneous as there was no other project against which any amount was due and payable. Further there was no

Signature Not Verified Digitally Signed

Signing Date:04.07.2022 possible reason as to why any amount would be reflected as due and payable for the work which was yet to be completed.

59. It is possible that certain amounts may be payable to Armtech. But this Court is not persuaded to accept that any interference with the impugned award is warranted in these proceedings. This is because, if any amount was indeed due and payable by GAIL, the onus to establish the same rested on Armtech. Armtech could possibly establish the same by producing primary documents including bills raised and payments received. However, Armtech had premised its claim entirely on GAIL's letter dated 09.04.2016. The decision of the Arbitral Tribunal turned solely on the basis of its evaluation and appreciation of that piece of evidence. The contents of the said letter were disputed and Armtech did not produce any other material - which ought to have been in its control - to establish the amount payable. As noted above, the Arbitral Tribunal is the final adjudicator of the quantity and quality of evidence. This Court is unable to find that the decision of the Arbitral Tribunal is perverse or fall fouls of the standards as set out in Section 34(2)(b)(ii) and Section 34(2A) of the A&C Act.

Re: Armtech's Claim for Interest

60. The Arbitral Tribunal has awarded interest at the rate of 9% per annum from the date of commencement of the arbitration proceedings till actual realization of the awarded amount. Armtech claims that interest ought to have been awarded from the date of the cause of action and there is no reason for denial of such interest.

Signature Not Verified Digitally Signed

Signing Date:04.07.2022

61. It is well settled that the Arbitral Tribunal has wide discretion in awarding interest. The pre-reference award is also subject to substantive law. It does not appear that Armtech had set up a case for award of interest under the Interest Act, 1978.

62. In view of the above, the decision of the Arbitral Tribunal to not award interest for the period prior to invoking the arbitration cannot be faulted.

63. In view of the above, GAIL's challenge to the impugned award entered against Claim No.3 to the extent that a sum of ₹30,00,000/- has been awarded by the Arbitral Tribunal to Armtech towards pending retention money, is accepted. The impugned award to the said extent is set aside. Armtech is at liberty to refer the said disputes to Arbitration afresh.

64. The petitions are disposed of in the aforesaid terms. All pending applications are also disposed of.

VIBHU BAKHRU, J JULY 04, 2022 'gsr'

Signature Not Verified Digitally Signed

Signing Date:04.07.2022

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter