Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Cxl Titon Electronics Pvt Ltd vs The Joint Secretary Ministry Of ...
2022 Latest Caselaw 183 Del

Citation : 2022 Latest Caselaw 183 Del
Judgement Date : 18 January, 2022

Delhi High Court
Cxl Titon Electronics Pvt Ltd vs The Joint Secretary Ministry Of ... on 18 January, 2022
$~1(2021)
*     IN THE HIGH COURT OF DELHI AT NEW DELHI
%                                          Date of decision:18.01.2022
+     ARB.P. 766/2021
      CXL TITON ELECTRONICS PVT LTD.         ..... Petitioner
                    Through: Mr. Sanjay Goswami, Advocate

                         Versus

      THE JOINT SECRETARY MINISTRY OF FISHERIES, ANIMAL
      HUSBANDRY AND DAIRYING & ANR.         ..... Respondents
                    Through: Mr. Vinod Diwakar, CGSC with
                             Mr.Vishal Kumar Singh, Advocate

      CORAM:
      HON'BLE MR. JUSTICE SURESH KUMAR KAIT

                        J U D G M E N T (oral)

1. The present petition has been filed by the petitioner under the

provisions of Section 11(5) and 11(6) of the Arbitration and Conciliation

Act, 1996 seeking appointment of Arbitrator to adjudicate the disputed with

respondent.

2. Petitioner is a Private Limited company dealing in RO Systems,

Water Purifiers, Effluent Treatment Plants, Sewerage Treatment Plants and

Water Softening Plants, who was awarded work under tender No.7-15/2013

-14/PUR/DES/73 dated 18.09.2013 for installation, commissioning,

operation and ultimately transfer of Reverse Osmosis Plants etc. capable of

supplying minimum 7-12 lacs liters of treated RO water per day, by the

respondents. Under the said work, petitioner was obliged to fulfil

requirements of respondent No.2- DMS by installing two machines which

could provide approximately 12 lacs litres RO water per day, for which

Respondent No.2 (DMS) had agreed to provide petitioner two Borewell for

24 hours each. For accomplishing the work, petitioner had to provide shed,

RO machines, two tube wells and pipe lines etc. at its own costs and had to

invest Rs.3.5 Crores for installation of machinery, furniture and fixture to

meet out the requirements of respondent No.2. The work tender was for a

period of five years to recover its investments and operational costs at the

optimum supply of minimum 7 lacs litres of treated RO water on daily basis

in the said operation period of five years.

3. According to petitioner, it was agreed that the said agreement was for

5 years @ Rs.99/- per kiloliter of treated water being paid by the respondent

No.2 DMS to the petitioner for the first year and thereafter to be increased at

the rate of 5% for every subsequent year. However, for reasons know to

respondent No.2, it could not get the permission from the Delhi Jal Board

for extraction of ground water from the borewell made available to the

Petitioner to an extent as was stipulated to be supplied for generation of 12

Lac liters of treated RO water. On 24.04.2014, respondent No.2- DMS

issued an amendment letter to revise the minimum and maximum uptake of

the treated water from the petitioner, whereunder petitioner was required to

supply minimum 4.375 lacs litres RO water per day and up to a maximum of

7 lacs litres of RO water per day to the Respondent No.2- DMS a revised

period of 8 years.

4. During the course of hearing, learned counsel for petitioner has

submitted that the petitioner was already suffering loss due to non-

availability of the untreated water and the objections of the Delhi Jal Board

to Respondent No.2-DMS, however, it accepted the amended work order as

it has already invested on operations and machinery. Further submitted that

despite this, respondent No.2 vide its letter dated 10.10.2019 pre-terminated

illegally the said agreement without assigning any reason and that the

petitioner had incurred expenses of more than Rs.11 Crores on the said

project. According to petitioner, against the pre-mature termination of the

contract, petitioner made several representations and held meeting with the

senior officers of DMS, but to no avail.

5. Learned counsel for petitioner has submitted despite a series of

writing letters when matter could not be resolved, petitioner vide Notice

dated 12.03.2021 under Section 80 of the CPC asked the respondents to pay

compensation of Rs.3,14,18,580 /- along with interest i.e. the amounts due

towards the monthly invoices, but neither the said notice was replied nor

payment was made. So, petitioner was constraint to send Notice dated

07.06.2021 to the respondent invoking arbitration and also proposed names

of panel of five arbitrators, which was also not replied to.

6. According to learned counsel for petitioner, as per Clause-18 of

second Schedule of the tender, which stipulated "that in case of any disputes

concerning the agreement, the Secretary, Ministry of Law Department of the

Legal Affairs Govt. of India shall nominate the Sole Arbitrator and the

Petitioner shall have no right to object to the same", however, since by

virtue of decision of Hon'ble Supreme Court in Perkins Eastman Architects

DPC & Anr. vs. HSCC (India) Ltd. 2019 SCC Online SC 1517, the aforesaid

clause has become null and void, therefore, the present petition has been

filed seeking appointment of arbitrator.

7. At this stage, learned CGSC appearing on behalf of respondent has

submitted that the averments made in the present petition are disputed

however, invocation of arbitration by petitioner by virtue of notice dated

07.06.2021 and existence of arbitration Clause-18 in the second schedule of

tender, is not disputed. Learned CGSC submitted that the disputes are

arbitrable and this Court may appoint an Arbitrator for adjudication of

disputes.

8. Accordingly, Mr.D.C. Anand, DHJS (Retd.) (Mobile: 9910384644)

is appointed the sole Arbitrator to adjudicate the dispute between the parties.

9. The fee of the learned Arbitrator shall be governed by the Fourth

Schedule of the Arbitration and Conciliation Act, 1996.

10. The learned Arbitrator shall ensure compliance of Section 12 of

Arbitration and Conciliation Act, 1996 before commencing the arbitration.

11. The present petition and pending application, if any, are accordingly

disposed of.

(SURESH KUMAR KAIT) JUDGE JANUARY 18, 2022/r

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter