Citation : 2022 Latest Caselaw 627 Del
Judgement Date : 28 February, 2022
$~21 (2022)
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of Decision: 28th February 2022
+ O.M.P.(I) (COMM.) 68/2022
GAMMON ENGINEERS AND CONTRACTORS
PVT. LTD. ..... Petitioner
Through: Mr Jayant Mehta, Senior
Advocate along with Mr
Subhojit Roy, Ms Sonia Dube,
Mr Ishaan Saha, Mr Satyaki
Mitra, Ms Kanchan Yadav, Ms
Ramanuj Raychaudhuri and Mr
Amrit Singh, Advocates.
Versus
RAIL VIKAS NIGAM LIMITED ..... Respondent
Through: Mr Udit Seth and Mr Anil Seth,
Advocates.
CORAM:
HON'BLE MR. JUSTICE VIBHU BAKHRU
VIBHU BAKHRU, J. (ORAL)
[Hearing held through videoconferencing]
IA No. 3262/2022
1. Exemption is allowed, subject to all just exceptions.
2. The application stands disposed of.
O.M.P.(I) (COMM.) 68/2022
3. The petitioner has filed the present petition under Section 9 of the
Signature Not Verified Digitally Signed By:Dushyant Rawal
Arbitration and Conciliation Act, 1996 (hereafter 'the A&C Act'), inter alia, praying that an order be passed restraining the respondent from taking any further action in terms of the letters dated 11.02.2022 and 16.02.2022.
4. In terms of the said letters, the respondent had called upon the petitioner to pay an amount of ₹9,21,22,006.33/- failing which, it would be recovered by encashment of the Bank Guarantees available with the respondent. The petitioner, thus, also prays that an order be passed restraining the respondent from making any claim for payment under the Performance Bank Guarantees submitted by the petitioner.
5. The controversy in this case arises in the following context:
6. The respondent had issued a Notice Inviting Tender (NIT) for "construction of Behala Bazar, Taratala and Majerhat stations including all related works (architecture, electrical and mechanical (E&M), HVAC, fire detection and fire suppression system and Public health engineering works) in Joka BBD Bag corridor of Kolkata Metro Railway Line (JMS2)".
7. The petitioner submitted its bid in response to the said NIT on 09.02.2012. The petitioner was selected as the successful bidder and by a Notice of Award dated 14.04.2012, the respondent awarded the contract to the petitioner for a total value of ₹1,62,66,53,074/-.
8. In terms of the tender conditions, the petitioner was required to deposit 10% of the contract amount, being ₹16,26,65,307/- as performance security as well as an additional performance security of ₹7,26,560/.
Signature Not Verified Digitally Signed By:Dushyant Rawal
9. The petitioner states that the value of the contract was subsequently reduced to ₹80.76 crores, however, the Bank Guarantees furnished by the petitioner were not correspondingly reduced.
10. Mr Mehta, learned senior counsel appearing for the petitioner, supported the prayers made in the present petition by contending that it was incumbent upon the respondent to reduce the value of the Performance Bank Guarantee, as in terms of the tender conditions, the value of the Performance Bank Guarantee was pegged at 10% of the contract value. Since the contract value had been reduced by removing certain works from the scope of works of the petitioner, commensurate with the reduced value of the contract, the Performance Bank Guarantees were required to be reduced as well.
11. He further submitted that apart from the fact that the respondent possessed the Performance Bank Guarantees of higher value, there were certain amounts due and payable by the respondent to the petitioner and therefore, there was no question of the respondent invoking any Bank Guarantee.
12. He submitted that the petitioner had made a claim amounting to ₹156.35 crores, which was being considered by the committee constituted for resolving the claims as raised by the petitioner. He submitted that encashment of the Performance Bank Guarantee(s) at this stage would amount to mulcting the petitioner with an additional burden while delaying the resolution of the claims made by the petitioner.
13. Mr Udit Seth, learned counsel appearing for the respondent had
Signature Not Verified Digitally Signed By:Dushyant Rawal
sought time to take instructions as to whether any amount was otherwise due and payable to the petitioner for the work done or was under process. He states that the respondent has since, filed an affidavit clearly stating that no amount is payable to the petitioner. On the contrary, the respondent claims a sum of ₹46,46,152.41/- from the petitioner.
14. He submitted that the Performance Bank Guarantee will be invoked only for a sum of ₹9,21,22,006.33/- as that is the additional amount incurred by the respondent for executing the works, which were earlier contracted to the petitioner. He submits that the petitioner could not complete part of the works and therefore, had requested that certain works be removed from its scope of works and awarded to another agency, at its risk and cost. This was done and the respondent is seeking recovery of the additional amount incurred over and above the value at which the said work was contracted to the petitioner. He submits that the amount of ₹9,21,22,006.33/-, recovery of which is sought by the respondent, is directly relatable to the failure on the part of the petitioner for executing the works in accordance with the contract.
15. It is at once clear from the above that there are disputes between the parties in regard to the performance of the contract in question. Both the parties are claiming that certain amounts are due and payable by the other.
16. Insofar as the relief regarding interdicting a bank guarantee is concerned, the law relating to the same is well settled. An unconditional bank guarantee cannot be interdicted except on the grounds of egregious fraud and special equities [Svenska Handelsbanken v. M/s Indian
Signature Not Verified Digitally Signed By:Dushyant Rawal
Charge Chrome and Others: (1994) 1 SCC 502; Himadri Chemicals Industries Ltd. v. Coal Tar Refining Co.: (2007) 8 SCC 110; and Larsen & Toubro Limited v Maharashtra State Electricity Board and Others: (1995) 6 SCC 68]. In the present case, no such ground exists.
17. In view of the above, this Court is unable to accede to the prayer made by the petitioner for interdicting the Performance Bank Guarantee furnished by the petitioner.
18. The petition is, accordingly, dismissed.
19. It is clarified that all rights and contentions of the parties are reserved and nothing stated in this order shall be construed as an expression of opinion on the merits of the rival claims.
VIBHU BAKHRU, J FEBRUARY 28, 2022 RK/v
Signature Not Verified Digitally Signed By:Dushyant Rawal
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!