Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Yfc Projects Private Limited vs Ramprastha Promoters And ...
2022 Latest Caselaw 590 Del

Citation : 2022 Latest Caselaw 590 Del
Judgement Date : 23 February, 2022

Delhi High Court
Yfc Projects Private Limited vs Ramprastha Promoters And ... on 23 February, 2022
$~23
*      IN THE HIGH COURT OF DELHI AT NEW DELHI
%                                            Date of decision: 23.02.2022
+      ARB.P. 222/2022 & I.A. 2992/2022
       YFC PROJECTS PRIVATE LIMITED             ..... Petitioner
                     Through  Mr. Vibhor Garg, Mr. Aditya
                              Bhardwaj, Mr. Keshav Tiwari and
                              Mr. Sidhant Bhatia, Advs.
                     versus
       RAMPRASTHA PROMOTERS AND DEVELOPERS PRIVATE
       LIMITED                               ..... Respondent
                   Through Mr. Sougat Sinha and Ms. R.
                           Gayathri Manasa, Advs.


       CORAM:
       HON'BLE MR. JUSTICE SURESH KUMAR KAIT

                          J U D G M E N T (oral)

1. The present petition has been filed by the petitioner under Section 11

(6) of the Arbitration and Conciliation Act, 1996 seeking appointment of

sole Arbitrator.

2. Learned counsel for petitioner submits that petitioner is a company

and is engaged in business of construction and other development activities.

Respondent is a non-government company and is a real estate developer

running its business operation in NCR region. Respondent during year 2010

obtained licence bearing No.40 of 2010 for development of group housing

society admeasuring 24.53 acres in sector 95 (in short 'Project'). Further,

respondent informed the petitioner that it had sold the FSI of the Project to

the Army Welfare Housing Organization (AWHO). As per the terms and

conditions entered between the AWHO and respondent, the development

rights were given to the respondent for construction of Multi Storied

Residential Towers and other related work for personal use of

member/allottees of AWHO. Respondent in furtherance of the contracts

which it had entered with AWHO, issued a letter of intent dated 25.05.2013

in favour of petitioner for execution of certain Civil & Structural Work for a

contract price of Rs.80,00,00,000/- in the Project. However, later certain

additional works were also awarded to petitioner relating to internal

Electrical, Sanitary & Plumbing work through a letter of intent on

10.06.2013 for a total amount of Rs.19,50,00,000/- and for installation of

Aluminium sub frames vide Work Order dated 12.07.2014 which was

costing around Rs. 41,65,000/-. Since the commencement of work in May

2013, the petitioner faced issues resulting from the lackadaisical attitude of

the respondent. There were no proper instructions with respect to the

construction activity and the respondent even had constant conflict with

AWHO, which resulted in termination of contract by AWHO with

respondent. In spite of satisfactory performance of work in accordance with

the drawing and data provided by the respondent, there was considerable

delay in the payments.

3. Petitioner further clams that in the year 2016 was informed by

respondent that further construction under the contract will not continue, on

account of certain disputes which arose between the respondent and AWHO.

Thereafter, with mutual consent it was decided that the contract shall stand

discharged and the petitioner shall submit final bills for the work done and

all payments due towards the pending bills shall be cleared by the

respondents. Thereafter, in May 2016, the final bills were also submitted by

the petitioner for the work done, which is also acknowledged by the

respondent. As such till date a principal amount of Rs. 5,22,97,877/- is still

due and payable by the respondent in favour of the petitioner. However,

despite the respondent's admitted liability the bills submitted by the

petitioner remains unpaid till date. Since the respondent failed to make

payment of the above stated liability, petitioner issued a demand notice

dated 14.08.2018 demanding payment of the principal amount of Rs.

5,22,97,877/- along with 18 % interest. However, respondent vide its reply

dated 23.08.2018 denied its liability and admitted the factum of dispute

between the parties and placed reliance on Clause 69 of the Contract

Agreement dated 25.05.2013 and claimed invocation of arbitration.

Consequently, petitioner by its legal notice dated 31.12.2021 invoked

arbitration which was served upon respondent vide email dated 31.12.2021,

however, respondent did not respond. Thereafter, again a reminder notice

dated 14.01.2022 was served upon the respondent and despite that, there was

no response from respondent. Hence, the present petition has been filed.

4. Learned counsel for respondent has entered appearance on advance

notice and submitted that though the claims raised in the present petition are

disputes, however disputes are arbitrable and Sole Arbitrator be appointed to

adjudicate the dispute between the parties.

5. Accordingly, the present petition is allowed and Mr. Justice (Retd.)

Jayant Nath (Mobile: 8527959494) is appointed sole Arbitrator to

adjudicate the dispute between the parties. Needless to say, all the issues

between the parties shall remain open before the learned Sole Arbitrator.

6. The arbitration shall be conducted under the Delhi International

Arbitration Centre (DIAC). The fee of the Arbitrator shall be in accordance

with the Schedule of Fees prescribed under the Delhi International

Arbitration Centre (DIAC) (Administrative Cost and Arbitrators Fees)

Rules, 2018.

7. The learned Arbitrator shall ensure compliance of Section 12 of

Arbitration and Conciliation Act, 1996 before commencing the arbitration.

8. The present petition is accordingly disposed of. Pending application is

disposed of as infructuous.

(SURESH KUMAR KAIT) JUDGE FEBRUARY 23, 2022 rk

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter