Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Sap Electro Contracts (Pvt) Ltd vs The Reiyukai
2022 Latest Caselaw 451 Del

Citation : 2022 Latest Caselaw 451 Del
Judgement Date : 11 February, 2022

Delhi High Court
Sap Electro Contracts (Pvt) Ltd vs The Reiyukai on 11 February, 2022
$~6
*     IN THE HIGH COURT OF DELHI AT NEW DELHI
%                                               Date of decision: 11.02.2022
+     ARB.P. 34/2022
      SAP ELECTRO CONTRACTS (PVT) LTD                       ..... Petitioner
                           Through      Mr.Syed Hasan Isfahani, Adv.

                           versus

      THE REIYUKAI                                        ..... Respondent
                           Through      Mr.Abhijit Banerjee & Mr.Nitin
                                        Chopra, Advs.

      CORAM:
      HON'BLE MR. JUSTICE SURESH KUMAR KAIT

                           J U D G M E N T (oral)

The hearing has been conducted through video conferencing.

1. The present petition has been filed under Section 11 of the Arbitration

and Conciliation Act, 1996 seeking appointment of sole Arbitrator to

adjudicate the disputes inter-se the parties.

2. According to petitioner, respondent was awarded the work order for

Internal Electrical Works for Institutional Religious Building "Eternal

Oasis" for total amount of Rs.82,60,000/- inclusive of all taxes e.g. Labour

Cess, WCT & GST as applicable on the basis of Schedule of Rates enclosed

with the work order for supply, installation, testing and commissioning of

Internal Electrical Works at the project site and a Contract Agreement was

signed with all terms and conditions including BOQ. Petitioner claims to

have started the said work according to the specification as per BOQ and

satisfaction of respondent's consulting Engineers/Project Managers and

thereafter drawings were made final from respondent's side and

mobilization advance received. Thereafter on 18.04.2018, respondent

awarded new work order to the petitioner for supply, installation, testing and

commissioning of High Side Electrical Works Institutional Religious

Building "Eternal Oasis" for total amount of Rs.44,25,000/- exclusive of

GST and Labour Cess and contract agreement was also signed with all terms

and conditions including BOQ. Again, petitioner started the said work

according to the specification as per BOQ and satisfaction of respondent's

consulting Engineers/Project Managers and thereafter drawings were made

final from respondent's side and mobilization advance received. After the

start of work, respondent started providing fresh drawings for those work

which was already completed and directed the petitioner to dismantle

everything and again carry out the work order according to the new

drawings. Petitioner did so for which respondent paid extra to the petitioner.

Petitioner raised the running bills for both the work order and paid the GST

as per applicable rate and respondent certified the payment and released part

payments.

3. Suddenly, on 20.05.2021, respondent terminated the contract in

violation of the terms and conditions of the GCC clause and work order.

Petitioner contacted the respondent and demanded the payment of

outstanding amount, however, respondent refused to pay the same.

Subsequently, various disputes arose between the parties regarding illegal

termination of the contract/work orders and non-payments of outstanding

against the certified invoices/bills.

4. During the course of arguments, learned counsel for the petitioner

submitted that petitioner sent a letter to respondent on 18.10.2021 requesting

to settle the disputes and differences amicably as per clause 52 of GCC but

of no avail. Thereafter, petitioner sent a legal notice dated 02.11.2021 and

invoked the arbitration in terms of clause 52.1 of GCC and called upon the

respondent to file application under Section 11 of the Arbitration and

Conciliation Act, 1996 before this Court for appointment of sole arbitrator.

However, respondent neither replied nor filed any application. Hence, the

present petition has been filed.

5. During the course of hearing, learned counsel appearing on behalf of

the respondent has not opposed the present petition and submitted that the

claims raised in the present petition are disputed, however, fairly conceded

that the disputes inter se parties are arbitrable. Learned counsel also

submitted that respondent has no objection if disputes are referred to an

independent arbitrator appointed by this Court.

6. Since counsel representing both the sides have consented that the

disputes are arbitrable and an independent Arbitrator be appointed by this

Court, the present petition is allowed.

7. Accordingly, Mr. R.K. Dhawan, Advocate (Mobile: 9899775330) is

appointed as the sole Arbitrator to adjudicate the dispute between the

parties.

8. The fee of the learned Arbitrator shall be governed by the Fourth

Schedule of the Arbitration and Conciliation Act, 1996.

9. The learned Arbitrator shall ensure compliance of Section 12 of

Arbitration and Conciliation Act, 1996 before commencing the arbitration.

10. The present petition and pending application, if any, are accordingly

disposed of.

(SURESH KUMAR KAIT) JUDGE FEBRUARY 11, 2022/ab

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter