Citation : 2021 Latest Caselaw 2696 Del
Judgement Date : 28 September, 2021
$~4
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 28.09.2021
+ ARB.P. 685/2021
PRAGATI CONSTRUCTION CONSULTANTS ..... Petitioner
Through Mr.Sumit Bansal, Adv.
versus
UNION OF INDIA ..... Respondent
Through Mr.J.K. Singh, Standing Counsel for
Railways with Mr.Amit Kumar, Adv.
CORAM:
HON'BLE MR. JUSTICE SURESH KUMAR KAIT
J U D G M E N T (oral)
1. The relief sought in the present petition before this Court is to appoint
sole Arbitrator under Section 11(6) of the Arbitration and Conciliation Act,
1996 to adjudicate the disputes between the parties in accordance with
clause 63 and 64 of the General Conditions of the Contract, 2014.
2. It is stated by the petitioner that respondent vide letter dated
03.05.2016 had awarded the work of extensive repairs and complete
renovation of old washing line nos.3, 4 & 5 including assembling and
linking of track and other allied works at Coach Care Centre, Hazrat
Nizammuddin at New Delhi. The total cost of work at the accepted rates was
worked out at Rs.12,07,05,992.60/-. The stipulated date of completion of
work was 15 months from the date of issuance of acceptance letter. Thus, in
the present case, the stipulated date for completion of work was 02.08.2017.
3. It is contended by the petitioner that immediately upon the award of
work, petitioner fully mobilized at the site and constructed the labour
hutments which was duly confirmed vide letter dated 07.05.2016 issued to
the respondent. During the execution of the work, respondent got various
extra items executed at the site but failed to make complete payments
towards the work done to the petitioner. Consequently, petitioner could not
complete the work within the extended time period due to non-availability of
funds by the respondent.
4. Learned counsel for the petitioner submits that on 05.11.2019,
petitioner invoked arbitration in terms of clause 64 of the General
Conditions of the Contract and requested the Chief Engineer/Construction of
the respondent to consider the claim for arbitration and further on
30.07.2020 petitioner issued a letter regarding the losses/claims of the
petitioner and requested for appointment of Arbitrator in terms of clause 64
of the General Conditions of Contract.
5. Respondent did not take any steps for a period of more than 4 months
and then for the very first time, on 19.01.2021 issued a letter to petitioner
wherein it was stated that for the appointment of sole arbitrator/arbitral
tribunal, Clause of Section 12(5) & 31(5) of the Arbitration and Conciliation
Act, 1996 should be waived off but petitioner refused to waive off the same
and again requested for appointment of the Arbitrator by the competent
authority.
6. Vide letter dated 09.03.2021, respondent had nominated a panel of
four retired railway officers, not below the rank of Senior Administrative
Grade Officers to suggest at least two names out of the panel and thereafter,
respondent shall appoint one out of them to act as the nominee of the
Petitioner. Petitioner vide its letter dated 24.03.2021 had responded to the
letter dated 09.03.2021, stating that appointment of the nominee by the
respondent as co-arbitrator is bad in the eyes of law as it is contrary to the
law laid down by the Hon'ble Supreme Court in the case of Perkins
Eastman Architects DPC & Anr. Vs. HSCC (India) Ltd.: (2019) SCC
OnLine SC 1517 wherein it has been categorically stated that "person who
has interest in the outcome or decision of the dispute must not have the
power to appoint a sole arbitrator" and further requested to refer the dispute
to The Delhi International Arbitration Centre, New Delhi for the
appointment of sole and independent arbitrator.
7. However, respondent had again reiterated its contentions as stated in
letter dated 09.03.2021 and sought consent of the petitioner for appointment
of the Arbitrator as clause 64 of General Conditions of Contract does not
contemplate for the appointment of an outside arbitrator.
8. At the hearing, learned counsel for petitioner submits that petitioner
has already invoked arbitration vide notice dated 05.11.2019 and for claim
of Rs.4,64,65,000/- (Rupees Four Crores Sixty Four Lacs Sixty Five
Thousand), an Arbitrator is required to be appointed by this Court.
9. Respondent has filed a short counter affidavit to the petition wherein
it has been stated that contractor has given "no claim certificate" against the
contract at the time of passing of final bill for the work executed. As per
Clause 43(2) of Indian Railways Standard General Conditions of Contract,
2018, if a contractor submits "no claim certificate" then the demand of
arbitration shall not be considered. He has placed reliance upon the
judgment of Hon'ble Supreme Court Union of India vs. Onkar Nath Bhalla
& Sons: (2009) 7 SCC 350.
10. In the case of Vidya Drolia vs. Durga Trading Corpn. (2021) 2 SCC
1, it was held that even where there is a disputed no-claim certificate or a
plea of discharge of the liability on the ground of novation or accord and
satisfaction is raised, the matter should appropriately be referred to the
Arbitral Tribunal and that it is only where, "it is manifest that the claims are
ex facie time barred and dead or there is no subsisting dispute" that the
Court can, at the referral stage, refuse to refer the matter to arbitration. The
judgment also states that the appropriate course to be followed by the Court
in all cases would be to refer the matter to arbitration, even where a plea of
non-arbitrability of the dispute is raised except where the dispute is
manifestly in the nature of "deadwood", meaning, thereby, that reference to
arbitration would be a futile exercise.
11. Pertinently, allocation of work order vide respondent's acceptance
letter bearing No.74-W/4/1/WA/SE Rd dated 03.05.2016 and invocation of
arbitration by petitioner vide notice dated 05.11.2019 is not disputed.
12. A coordinate bench of this Court in the case of M/s ABC EXPERTS
AND ENGINEERS vs. UNION OF INDIA in ARB.P. 170/2021 vide order
dated 11.08.2021 has passed an order wherein the matter was referred to the
Delhi International Arbitration Centre for adjudication of the disputes after
considering the objections by both the parties.
13. Considering the facts of the present case and the decision taken by a
coordinate bench of this Court and Apex Court in the abovementioned cases,
I am of the opinion that to resolve the disputes between the parties, an
independent arbitrator is required to be appointed.
14. Accordingly, Mr. Justice (Retd.) Satpal Garg (Mobile:
9910384627) is appointed as sole Arbitrator to adjudicate the disputes
between the parties.
15. The arbitration shall be conducted under the Delhi International
Arbitration Centre (DIAC). The fee of the Arbitrator shall be in accordance
with the schedule of fees prescribed under the Delhi International
Arbitration Centre (DIAC) (Internal Management) Rules and Delhi
International Arbitration Centre (Administrative Cost and Arbitrators' Fees)
Rules, 2018.
16. The learned Arbitrator shall ensure compliance of Section 12 of
Arbitration and Conciliation Act, 1996 before commencing the arbitration.
17. The present petition is accordingly disposed of.
18. A copy of this order be sent to the learned Arbitrator for information.
(SURESH KUMAR KAIT) JUDGE SEPTEMBER 28, 2021 ab
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!