Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Arkas Energy Llp vs M/S Inox Wind Limited
2021 Latest Caselaw 2570 Del

Citation : 2021 Latest Caselaw 2570 Del
Judgement Date : 17 September, 2021

Delhi High Court
M/S Arkas Energy Llp vs M/S Inox Wind Limited on 17 September, 2021
$~2
*     IN THE HIGH COURT OF DELHI AT NEW DELHI
%                                           Date of decision: 17.09.2021
+     ARB.P. 778/2021

      M/S ARKAS ENERGY LLP                             ......Petitioner
                   Through:           Mr. Matragupta Mishra, Advocate

                         Versus

      M/S INOX WIND LIMITED                         ...... Respondent
                    Through:          Mr. Aseem Chaturvedi, Advocate

      CORAM:
      HON'BLE MR. JUSTICE SURESH KUMAR KAIT

                         J U D G M E N T (oral)

1. The present petition has been preferred under Section 11(6) of the

Arbitration and Conciliation Act, 1996 seeking appointment of an

Arbitrator.

2. Petitioner is a company incorporated under the provisions of the

Limited Liability Partnerships Act, 2008. Respondent herein is a company

registered under the Companies Act, 1956, which provides wind energy

services including but not limited to manufacturing wind turbine generators.

3. According to petitioner, it was setting up an MW (2x2000 KW) wind

farm project at Mandsaur District in the State of Madhya Pradesh, wherein

vide letter dated 25.06.2015 being Order No. 002/ Arkas/2015-16, petitioner

had issued a work order for erection and commissioning of three INOX

made WT-2000 DF (93/80) 2000 KW capacity wind turbine generators

(WTG) at the site.

4. Further, vide letter dated 25.06.2015 being Order No.

001/Arkas/2015-16, petitioner claims to have issued a purchase order for

three INOX made WT-2000 DF 93/80) 2000 KW capacity wind turbine

generators (WTG) at the site. According to petitioner, the respondent was

also responsible for installation of power evacuation systems and shared

services, for evacuating power in the said project and had committed to the

commissioning of the WTGs not later than 31.03.2016 but the said date was

pushed several times.

5. Petitioner further claims that petitioner vide its letter dated 29.12.2015

asked the respondent to stick to the schedule however, despite repeated

requests respondent failed to execute its part of obligations towards timely

commissioning of the project. According to petitioner, respondent failed to

reply to petitioner's communication dated 14.04.2016 and has thereby failed

to commissioning of WTGs by 31.03.2016 and so, the commissioning

certificates could not be issued. Further claimed that petitioner's reminders

dated 19.04.2016, 22.04.2016 and 25.04.2016 and Demand Notice dated

03.05.2016 have not been acknowledged by the respondent.

6. Petitioner claims to have suffered huge loss due to failure on the part

of respondent to fulfil its part of obligations and therefore, it had issued a

letter dated 15.12.2020 along with a debit note for claim of compensation of

Rs.5,50,76,462/- with interest towards generation loss and loss of GBI, but

even this has not been acknowledged by the respondent. It is in such

circumstances, petitioner claims to have invoked 'Dispute Resolution Clause

No.13" in terms thereof, issued a notice dated 25.02.2021 to respondent

invoking arbitration under the Arbitration and Conciliation Act, 1996.

7. During the course of hearing, learned counsel for petitioner submits

that vide aforesaid Notice dated 25.02.2021, petitioner has already

nominated its Arbitrator but respondent has failed to respond thereto within

stipulated time of 30 days, therefore, the preset petition be allowed.

8. During pendency of this petition, learned counsel for respondent had

sought time to obtain instructions. Today, it is submitted by learned counsel

that to resolve the disputes inter se parties, sole Arbitrator be appointed by

this Court.

9. In view of the aforesaid, Justice (Retd.) Kailash Gambhir (Mobile:

9871300033) is appointed sole Arbitrator to adjudicate the disputes between

the parties.

10. The fees of the learned Arbitrator shall be according to Fourth

Schedule of the Arbitration and Conciliation Act, 1996.

11. The learned Arbitrator shall ensure compliance of Section 12 of

Arbitration and Conciliation Act, 1996 before commencing the arbitration.

12. A copy of this order be sent to the learned Arbitrator for information.

(SURESH KUMAR KAIT) JUDGE SEPTEMBER 17, 2021 r

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter