Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Gbk Project Pvt. Ltd vs Union Of India Through The General ...
2021 Latest Caselaw 3154 Del

Citation : 2021 Latest Caselaw 3154 Del
Judgement Date : 22 November, 2021

Delhi High Court
Gbk Project Pvt. Ltd vs Union Of India Through The General ... on 22 November, 2021
$~9(2021)
*     IN THE HIGH COURT OF DELHI AT NEW DELHI
%                                           Date of decision: 22.11.2021
+     ARB.P. 1055/2021
      GBK PROJECT PVT. LTD.                             ......Petitioner
                   Through:           Mr. S.W. Haider, Advocate

                         Versus

      UNION OF INDIA THROUGH THE GENERAL
      MANAGER                               ......Respondent
               Through: Mr. Ashok Singh, Advocate

      CORAM:
      HON'BLE MR. JUSTICE SURESH KUMAR KAIT

                         J U D G M E N T (oral)

1. By Way of present petition, petitioner is seeking appointment of an

independent Arbitrator under the provisions of Section 11 of the Arbitration

and Conciliation Act, 1996 read with Section 151 CPC.

2. Petitioner-company claims to be involved in the business of

construction and Railway contracts, who vide acceptance letter dated

26.09.2016 of respondent was awarded work pertaining to "Balance work of

quarters at Asoati Faridabad, construction of station building, power cabin,

RRI and other station building, extension of platforms, retaining wall,

development of circulating area, drainage arrangements in yards and other

allied works at different location in between AST and Jn cabin TKD in C/W

4th line" for Rs. 12,64,61 ,022.97 (Rupees Twelve Crore Sixty Four Lac

Sixty One Thousand Twenty Two and Ninety Seven Paise only). The work

was to be completed within stipulated period of 15 months i.e. 25.12.2017.

3. According to petitioner, petitioner had made all necessary

arrangements, however, work could not be completed by the stipulated time

i.e. 25.12.2017 due to several failures on the part of the respondent and so,

the period for completion of work was last extended upto 01.12.2019.

However, during execution of the work, various claims, clarifications and

disputes arose between the parties, which were brought to the notice of

concerned department of respondent, but instead of finding out any solution

and acting oblivious to the genuine difficulties faced by the petitioner,

respondent issued several notices to the petitioner with a view to

escape/wriggle out from its contractual obligations and vide notice dated

23.09.2019 the respondent terminated the contract.

4. It is averred by the petitioner that respondent was under the obligation

to serve 48 hours notice upon the petitioner before terminating the contract

as mandated and so, petitioner vide its letter dated 23.07.2021, invoked the

arbitration clause as contained under clause 64 of the General Conditions of

the Contract.

5. At the hearing, learned counsel for the petitioner has submitted that

petitioner claims amount to Rs.4,76,34,485/- (Rupees Four Crore Seventy

Six Lac Thirty Four Thousand Four Hundred Eighty Five Only) against the

respondent and therefore, the present petition be allowed.

6. On the other hand, learned counsel appearing for respondent has

disputed the averments made by the petitioner and has submitted that in

response to petitioner's letter dated 23.07.2021 invoking arbitration,

respondent in its reply dated 23.08.2021 had sought waiver of Section 12(5)

of the Act, however, it was not replied to by the petitioner. Further submits

that in terms of Clause-64(3) of the General Conditions of Contract, if the

total value of claim does not exceed Rs.25,00,000, , the Arbitral Tribunal

shall consist of a Sole Arbitrator who shall be a Gazetted Officer of Railway

not below JA Grade, nominated by the General Manager otherwise, the

Arbitral Tribunal shall consist of a Panel of three Gazetted Railway Officers

not below JA Grade or 2 Railway Gazetted Officers not below JA Grade and

a retired Railway Officer, retired not below the rank of SAG Officer, as the

arbitrators.

7. Both sides have been heard and record of this case has been perused.

8. Pertinently, invocation of arbitration vide letter dated 23.07.2021 by

the petitioner is not disputed. Though the present petition has been opposed

by learned counsel for respondent, however, it is not disputed that any

dispute inter se parties has to be resolved through arbitration in terms as

contained under clause 64 of the General Conditions of the Contract.

However, contention of learned counsel for respondent that appointment of

Arbitrator has to be made in terms of Clause-64(3) of the General

Conditions of Contract, is rejected in view of Hon'ble Supreme Court's

decision in Perkins Eastman Architects DPC & Anr. vs. HSCC (India) Ltd.

2019 SCC Online SC 1517, wherein it has been categorically stated that no

single party can be permitted to unilaterally appoint the Arbitrator, as it

would defeat the purpose of unbiased adjudication of dispute between the

parties. The aforesaid decision in Perkins (Supra) has been followed by a

Coordinate Bench of this Court in Proddatur Cable TV Digi Services Vs.

Citi Cable Network Limited: (2020) 267 DLT 51. Thus, the Arbitrator either

has to be appointed with the consensus of the parties or by this Court.

9. In view of the above, the present petition is, therefore, allowed and

Mr. Justice (Retd) I.S.Mehta, former Judge of Delhi High Court

(Mobile: 9910384616) is appointed the Sole Arbitrator to adjudicate the

dispute between the parties.

10. The arbitration shall be conducted under the Delhi International

Arbitration Centre (DIAC). The fee of the Arbitrator shall be in accordance

with the Schedule of Fees prescribed under the Delhi International

Arbitration Centre (DIAC) (Administrative Cost and Arbitrators Fees)

Rules, 2018.

11. The learned Arbitrator shall ensure compliance of Section 12 of

Arbitration and Conciliation Act, 1996 before commencing the arbitration.

12. A copy of this order be sent to learned Arbitrator for information.

13. With aforesaid directions, the present petition is accordingly disposed

of.

(SURESH KUMAR KAIT) JUDGE NOVEMBER 22, 2021 r

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter