Citation : 2021 Latest Caselaw 3126 Del
Judgement Date : 18 November, 2021
$~24 to 27
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 18.11.2021
(i) + ARB.P. 1100/2021, I.As.14884-85/2021
RAYS POWER EXPERTS PVT. LTD ..... Petitioner
Through: Ms. Surabhi Pandey, Advocate
Versus
LOHIA GRAMIN VIKAS PVT. LTD. & ORS. .... Respondents
Through: Mr. Shrey Yadav & Mr. Achal
Singh, Advocates
(ii) + ARB.P. 1041/2021
LOHIA GRAMIN VIKAS PVT LTD ..... Petitioner
Through: Mr. Shrey Yadav & Mr. Achal
Singh, Advocates
Versus
RAYS POWER EXPERTS PVT LTD AND ORS. .... Respondents
Through: Ms. Surabhi Pandey, Advocate
(iii) + ARB.P. 1042/2021
LOHIA DEVELOPERS INDIA PVT. LTD. ..... Petitioner
Through: Mr. Shrey Yadav & Mr. Achal
Singh, Advocates
Versus
RAYS POWER EXPERTS PVT LTD AND ORS. .... Respondents
Through: Ms. Surabhi Pandey, Advocate
ARB.P.1100/2021; 1041/2021; 1042/2021 & 1043/2021 Page 1 of 7
(iv) + ARB.P. 1043/2021
DESIGNCO ..... Petitioner
Through: Mr. Shrey Yadav & Mr. Achal
Singh, Advocates
Versus
RAYS POWER EXPERTS PVT LTD AND ORS. .... Respondents
Through: Ms. Surabhi Pandey, Advocate
CORAM:
HON'BLE MR. JUSTICE SURESH KUMAR KAIT
J U D G M E N T (oral)
1. The above captioned four petitions have been filed under the
provisions of Section 11(5) of the Arbitration and Conciliation Act, 1996
seeking appointment of sole Arbitrator.
2. Pertinently, parties to these petitions are common and the subject
matter of these petitions is also common, therefore, with the consent of
learned counsel for the parties, these petitions have been heard together and
are being disposed of vide this common judgment.
3. M/s Rays Power Experts Pvt. Ltd. has raised grievances against Lohia
Gramin Vikas Pvt. Ltd.; Lohia Developers (India) Pvt. Ltd. and Designco
through their Directors, who are common in all these companies. Similarly,
Lohia Gramin Vikas Pvt Ltd., Lohia Developers (India) Pvt. Ltd. and
Designco have raised grievances against M/s Rays Power Experts Pvt. Ltd.
as well as its Directors- Mr. Rahul Gupta & Ms Nidhi Gupta.
4. The claim of M/s Rays Power Experts Pvt. Ltd., who is engaged in the
business of construction, commissioning, and Operation & maintenance of
Solar Power Plants, is that it had entered into six different Engineering
Procurement and Construction Agreements ("EPC Agreements") for
construction of Solar Power Plants/Projects and for the Operation &
Maintenance ("O&M services") of each of the Solar Power Plants for a
period of 25 years from the commissioning of the Solar Plants with the
Lohia Gramin Vikas Pvt. Ltd.; Lohia Developers (India) Pvt. Ltd. and
Designco. Further claimed that it had completed the 6 Solar Projects as per
the time scheduled in the EPC Agreements and respondents were evacuating
power from the transmission lines constructed by the petitioner. However,
Lohia Gramin Vikas Pvt. Ltd.; Lohia Developers (India) Pvt. Ltd. and
Designco did not adhere to the repayment schedule and only a part of project
cost was paid despite various requests while stating that O&M related
payments were to be made depending upon the generation guarantee and
they were entitled to the payments qua generation loss incurred. This was
disputed by M/s Rays Power Experts Pvt. Ltd., however, parties arrived at a
conciliation in October, 2018, which failed and so, it decided to terminate
the O&M agreement.
5. It is further claimed by M/s Rays Power Experts Pvt. Ltd. that
petitions under Section 9 of the Act were filed by Lohia Gramin Vikas Pvt.
Ltd.; Lohia Developers (India) Pvt. Ltd. and Designco before District Court,
Bikaner which were dismissed on 16.12.2019 on jurisdictional aspect with
direction to approach the appropriate jurisdiction of NCT of Delhi.
Thereafter, petitions were filed before Delhi District Court (South), which
were disposed of with direction to allow M/s Rays Power Experts Pvt. Ltd
readings with DISCOM representatives and enter the Solar Power Plant for
routine inspection and to pay a total sum of Rs.5,00,000/- in two monthly
instalments i.e., by or before 15th July, 2020 and 15th August, 2020. Further,
vide order dated 23.09.2020 and 30.06.2020 in two different petitions,
directions were given to pay amount of Rs.5,00,000/-and Rs.2,50,000/-
respectively under different heads.
6. It is further averred by M/s Rays Power Experts Pvt. Ltd. that Lohia
Gramin Vikas Pvt. Ltd. and Lohia Developers (India) Pvt. Ltd. had
thereafter invoked arbitration in terms of Article-15 of EPC Agreement
dated 12.09.2020, in reply to which M/s Rays Power Experts Pvt. Ltd vide
notice dated 04.12.2020 had invoked arbitration against all the three
companies Lohia Gramin Vikas Pvt. Ltd.; Lohia Developers (India) Pvt.
Ltd. and Designco, which was not replied to and so, a prayer is made before
this Court for appointment of sole Arbitrator.
7. On the contrary, the stand of Lohia Gramin Vikas Pvt. Ltd.; Lohia
Developers (India) Pvt. Ltd. and Designco, is that though the execution of
"EPC Agreements" is not disputed, however, its engineers were never
allowed/ permitted to take reading of the power generated park as per work
order for the reason sub-standard machines were used by M/s Rays Power
Experts Pvt. Ltd. to generate power in the solar plant. When their repeated
efforts for inspection of the plant failed, petitions under Section 9 of the Act
were filed before the Court at Bikaner to seek interim relief for breach of
terms and agreements, which were dismissed while giving liberty to
approach the appropriate jurisdiction at NCT of Delhi. Thereafter, Section 9
petitions were filed in Delhi, which were partly allowed and the disputed
portion of the order was challenged before this Court, which were later
withdrawn. However, when M/s Rays Power Experts Pvt. Ltd. on
18.07.2020 disconnected the transmission line of the solar power plant,
which cause huge financial losses, so, Lohia Gramin Vikas Pvt. Ltd.; Lohia
Developers (India) Pvt. Ltd. and Designco invoked arbitration vide Notices
dated 12.09.2020, 12.09.2021 and 19.01.2021 respectively.
8. During the course of hearing, learned counsel appearing from both the
sides neither disputed the execution of "EPC Agreements" between the
parties nor that disputes/difference have to be resolved through arbitration in
terms of Article-15 of EPC Agreements dated 22.5.2013, 08.01.2014,
11.08.2014, 03.02.2016, 03.03.2016 & 12.09.2020. Thereby, learned
counsel reached a consensus that an Arbitrator may be appointed by this
Court to resolve the disputes between the parties. Hence, these petitions are
allowed.
9. Accordingly, Ms. Justice (Retd) G. Rohini (former Chief Justice of
this Court) (Mobile: 8527027027) is appointed sole Arbitrator in these
petitions to adjudicate the dispute between the parties.
10. The fee of the learned Arbitrator shall be governed by the Fourth
Schedule of the Arbitration and Conciliation Act, 1996.
11. The learned Arbitrator shall ensure compliance of Section 12 of
Arbitration and Conciliation Act, 1996 before commencing the arbitration.
12. The date of 10.01.2022 in ARB.P.1041/2021; 1042/2021 and
1043/2021 stands cancelled.
13. These petitions are accordingly disposed of.
14. Pending applications also stand disposed of.
15. A copy of this order be sent to the learned Arbitrator for information.
(SURESH KUMAR KAIT) JUDGE NOVEMBER 18, 2021 r
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!