Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Designco vs Rays Power Experts Pvt Ltd And Ors.
2021 Latest Caselaw 3126 Del

Citation : 2021 Latest Caselaw 3126 Del
Judgement Date : 18 November, 2021

Delhi High Court
Designco vs Rays Power Experts Pvt Ltd And Ors. on 18 November, 2021
$~24 to 27
*       IN THE HIGH COURT OF DELHI AT NEW DELHI
%                                            Date of decision: 18.11.2021
(i)     + ARB.P. 1100/2021, I.As.14884-85/2021
        RAYS POWER EXPERTS PVT. LTD            ..... Petitioner
                     Through: Ms. Surabhi Pandey, Advocate

                          Versus

        LOHIA GRAMIN VIKAS PVT. LTD. & ORS.    .... Respondents
                     Through: Mr. Shrey Yadav & Mr. Achal
                              Singh, Advocates

(ii)    +    ARB.P. 1041/2021
        LOHIA GRAMIN VIKAS PVT LTD             ..... Petitioner
                     Through: Mr. Shrey Yadav & Mr. Achal
                              Singh, Advocates

                          Versus

        RAYS POWER EXPERTS PVT LTD AND ORS. .... Respondents
                     Through: Ms. Surabhi Pandey, Advocate

(iii)   +    ARB.P. 1042/2021
        LOHIA DEVELOPERS INDIA PVT. LTD.                ..... Petitioner
                          Through:     Mr. Shrey Yadav & Mr. Achal
                                       Singh, Advocates

                          Versus

        RAYS POWER EXPERTS PVT LTD AND ORS. .... Respondents
                     Through: Ms. Surabhi Pandey, Advocate

ARB.P.1100/2021; 1041/2021; 1042/2021 & 1043/2021                  Page 1 of 7
 (iv)   +     ARB.P. 1043/2021
       DESIGNCO                                         ..... Petitioner
                          Through:     Mr. Shrey Yadav & Mr. Achal
                                       Singh, Advocates

                          Versus

       RAYS POWER EXPERTS PVT LTD AND ORS. .... Respondents
                    Through: Ms. Surabhi Pandey, Advocate

       CORAM:
       HON'BLE MR. JUSTICE SURESH KUMAR KAIT

                         J U D G M E N T (oral)

1. The above captioned four petitions have been filed under the

provisions of Section 11(5) of the Arbitration and Conciliation Act, 1996

seeking appointment of sole Arbitrator.

2. Pertinently, parties to these petitions are common and the subject

matter of these petitions is also common, therefore, with the consent of

learned counsel for the parties, these petitions have been heard together and

are being disposed of vide this common judgment.

3. M/s Rays Power Experts Pvt. Ltd. has raised grievances against Lohia

Gramin Vikas Pvt. Ltd.; Lohia Developers (India) Pvt. Ltd. and Designco

through their Directors, who are common in all these companies. Similarly,

Lohia Gramin Vikas Pvt Ltd., Lohia Developers (India) Pvt. Ltd. and

Designco have raised grievances against M/s Rays Power Experts Pvt. Ltd.

as well as its Directors- Mr. Rahul Gupta & Ms Nidhi Gupta.

4. The claim of M/s Rays Power Experts Pvt. Ltd., who is engaged in the

business of construction, commissioning, and Operation & maintenance of

Solar Power Plants, is that it had entered into six different Engineering

Procurement and Construction Agreements ("EPC Agreements") for

construction of Solar Power Plants/Projects and for the Operation &

Maintenance ("O&M services") of each of the Solar Power Plants for a

period of 25 years from the commissioning of the Solar Plants with the

Lohia Gramin Vikas Pvt. Ltd.; Lohia Developers (India) Pvt. Ltd. and

Designco. Further claimed that it had completed the 6 Solar Projects as per

the time scheduled in the EPC Agreements and respondents were evacuating

power from the transmission lines constructed by the petitioner. However,

Lohia Gramin Vikas Pvt. Ltd.; Lohia Developers (India) Pvt. Ltd. and

Designco did not adhere to the repayment schedule and only a part of project

cost was paid despite various requests while stating that O&M related

payments were to be made depending upon the generation guarantee and

they were entitled to the payments qua generation loss incurred. This was

disputed by M/s Rays Power Experts Pvt. Ltd., however, parties arrived at a

conciliation in October, 2018, which failed and so, it decided to terminate

the O&M agreement.

5. It is further claimed by M/s Rays Power Experts Pvt. Ltd. that

petitions under Section 9 of the Act were filed by Lohia Gramin Vikas Pvt.

Ltd.; Lohia Developers (India) Pvt. Ltd. and Designco before District Court,

Bikaner which were dismissed on 16.12.2019 on jurisdictional aspect with

direction to approach the appropriate jurisdiction of NCT of Delhi.

Thereafter, petitions were filed before Delhi District Court (South), which

were disposed of with direction to allow M/s Rays Power Experts Pvt. Ltd

readings with DISCOM representatives and enter the Solar Power Plant for

routine inspection and to pay a total sum of Rs.5,00,000/- in two monthly

instalments i.e., by or before 15th July, 2020 and 15th August, 2020. Further,

vide order dated 23.09.2020 and 30.06.2020 in two different petitions,

directions were given to pay amount of Rs.5,00,000/-and Rs.2,50,000/-

respectively under different heads.

6. It is further averred by M/s Rays Power Experts Pvt. Ltd. that Lohia

Gramin Vikas Pvt. Ltd. and Lohia Developers (India) Pvt. Ltd. had

thereafter invoked arbitration in terms of Article-15 of EPC Agreement

dated 12.09.2020, in reply to which M/s Rays Power Experts Pvt. Ltd vide

notice dated 04.12.2020 had invoked arbitration against all the three

companies Lohia Gramin Vikas Pvt. Ltd.; Lohia Developers (India) Pvt.

Ltd. and Designco, which was not replied to and so, a prayer is made before

this Court for appointment of sole Arbitrator.

7. On the contrary, the stand of Lohia Gramin Vikas Pvt. Ltd.; Lohia

Developers (India) Pvt. Ltd. and Designco, is that though the execution of

"EPC Agreements" is not disputed, however, its engineers were never

allowed/ permitted to take reading of the power generated park as per work

order for the reason sub-standard machines were used by M/s Rays Power

Experts Pvt. Ltd. to generate power in the solar plant. When their repeated

efforts for inspection of the plant failed, petitions under Section 9 of the Act

were filed before the Court at Bikaner to seek interim relief for breach of

terms and agreements, which were dismissed while giving liberty to

approach the appropriate jurisdiction at NCT of Delhi. Thereafter, Section 9

petitions were filed in Delhi, which were partly allowed and the disputed

portion of the order was challenged before this Court, which were later

withdrawn. However, when M/s Rays Power Experts Pvt. Ltd. on

18.07.2020 disconnected the transmission line of the solar power plant,

which cause huge financial losses, so, Lohia Gramin Vikas Pvt. Ltd.; Lohia

Developers (India) Pvt. Ltd. and Designco invoked arbitration vide Notices

dated 12.09.2020, 12.09.2021 and 19.01.2021 respectively.

8. During the course of hearing, learned counsel appearing from both the

sides neither disputed the execution of "EPC Agreements" between the

parties nor that disputes/difference have to be resolved through arbitration in

terms of Article-15 of EPC Agreements dated 22.5.2013, 08.01.2014,

11.08.2014, 03.02.2016, 03.03.2016 & 12.09.2020. Thereby, learned

counsel reached a consensus that an Arbitrator may be appointed by this

Court to resolve the disputes between the parties. Hence, these petitions are

allowed.

9. Accordingly, Ms. Justice (Retd) G. Rohini (former Chief Justice of

this Court) (Mobile: 8527027027) is appointed sole Arbitrator in these

petitions to adjudicate the dispute between the parties.

10. The fee of the learned Arbitrator shall be governed by the Fourth

Schedule of the Arbitration and Conciliation Act, 1996.

11. The learned Arbitrator shall ensure compliance of Section 12 of

Arbitration and Conciliation Act, 1996 before commencing the arbitration.

12. The date of 10.01.2022 in ARB.P.1041/2021; 1042/2021 and

1043/2021 stands cancelled.

13. These petitions are accordingly disposed of.

14. Pending applications also stand disposed of.

15. A copy of this order be sent to the learned Arbitrator for information.

(SURESH KUMAR KAIT) JUDGE NOVEMBER 18, 2021 r

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter