Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Ashutosh Builders ... vs Union Of India & Ors.
2021 Latest Caselaw 3028 Del

Citation : 2021 Latest Caselaw 3028 Del
Judgement Date : 10 November, 2021

Delhi High Court
M/S Ashutosh Builders ... vs Union Of India & Ors. on 10 November, 2021
$~4
*     IN THE HIGH COURT OF DELHI AT NEW DELHI

%                                            Date of decision: 10.11.2021

+     ARB.P. 900/2021
      M/S ASHUTOSH BUILDERS CONTRACTORS
      AND ENGINEERS                                        ..... Petitioners
                          Through:     Ms.Seema Singh, Adv.

                          Versus

      UNION OF INDIA & ORS.                              ..... Respondents
                    Through:           Ms.Arti Bansal, Adv.

      CORAM:
      HON'BLE MR. JUSTICE SURESH KUMAR KAIT

                          J U D G M E N T (oral)

1. Petitioner has filed the present petition under the provisions of Section

11(6) of the Arbitration and Conciliation Act, 1996 seeking appointment of

sole arbitrator for adjudication of all the disputes with respondents in terms

of arbitration clause 70 of IAFW 2249.

2. Petitioner is a contractor and has been engaged by the respondent on

several occasions for carrying out various constructions and other activities

of respondent. Respondent is an establishment fully controlled and

supervised by the Ministry of Defence, Union of India and is a state under

Article 12 of the Constitution of India. Respondent no.1 is Union of India

through Engineer in Chief (E-IN-C) of the Wing of Army for carrying out

works of infrastructure. Respondent nos.2, 3 & 4 are subordinate offices to

respondent no.1.

3. Petitioner was awarded the acceptance letter of the contract agreement

vide letter dated 28.06.2019 for the work "CA NO.CWE/WEST-02/2019-

20;SPL REPAIR OF ROMNEY HUTS T-156,T-165,T-166,T-167,T-168

AND T-169 OF CENTRAL STORAGE FACILITY AT CVD UNDER GE

(WEST)DELHI CANTT.-10" to the tune of Rs.31,19,233/-.

4. Thereafter, respondent no.4 issued work order dated 02.07.2019 to the

petitioner wherein date of commencement was mentioned as 12.07.2019 and

date of completion was mentioned as 11.01.2020. Upon this, petitioner firm

issued a letter dated 26.07.2019 requesting to handover the complete vacant

site and thereafter, petitioner time and again sent letters dated 13.08.2019,

09.09.2019 and 21.09.2019 requesting to handover Shed No. T-156, T-167

& T-165.

5. Subsequently, again petitioner sent letter on 05.12.2019 and stated

that Hon'ble Supreme Court vide order dated 04.11.2019 has enforced the

ban upon the construction activities carried in Delhi. He also stated that the

work could only be started after the ban is uplifted and requests for

extension of time.

6. In response to the abovementioned letter, respondent no.4 vide letter

dated 20.12.2019 stated that the Hon'ble Supreme Court has given

relaxation in time for construction activities from 09.12.2019 and also

alleged that no activity can be seen at the site and stated to levy

compensation as time being essence of contract and granted two weeks time

to cancel the contract at certain risk and cost.

7. Thereafter petitioner again sent a letter dated 09.01.2020 to

respondent no.4 in response to its letter dated 20.12.2019 expressing delay

attributable to the respondent while proceeding with the execution of the

work at site, delay in handing over site, delay in taking decision at paint,

delay decision in installing the CG sheets, etc.

8. It is averred on behalf of the petitioner that despite of the due date of

completion of work as per work Order No.1 which was expired on

11.01.2020, vacant site of the shed T-165 was not handed over. Thereafter

petitioner again sent letter dated 22.01.2020 wherein stated that respondent

no.4 has not granted extension of time to the petitioner and on the other side,

notice of levying compensation was sent but complete vacant site was not

handed over to the petitioner even after lapse of due date of completion of

contract work. Respondent no.4 in response to the petitioner's

abovementioned letter sent letters dated 20.08.2020 and 21.08.2020 stating

that CGI sheet of M/s Bhushan has developed defect of rust from many

places.

9. Upon this, petitioner sent a letter to respondent no.5 as well as TATA

Steel (manufacturer) along with letter of respondent no.4 to replace the

steel/material as rust can be seen on CGI sheet.

10. Petitioner being aggrieved with the high handed attitude of respondent

no.4 issued legal notice on 24.10.2020 stating that site T-165 has not been

handed over after lapse of 10 months from the due date of completion and

also failure in providing the extension despite of numerous requests.

11. During the course of hearing, learned counsel for the petitioner

informed that the petitioner firm had previously sent notice for conciliation

and thereafter sent a notice invoking arbitration vide notice dated

17.07.2021 under condition 70 of IAFW and requested for appointment of a

sole arbitrator to adjudicate the disputes between the parties.

12. Respondents have filed reply to the present petition wherein it has

been stated that as per the Agreement the serving officer having requisite

qualification has to be appointed as an arbitrator to adjudicate the disputes

solely by the appointing authority i.e. Chief Engineer Delhi Zone, Delhi

Cantt.

13. Both sides have been heard and record of this case has been perused.

However, the Hon'ble Supreme Court in Perkins Eastman Architects DPC

& Anr. vs. HSCC (India) Ltd. 2019 SCC Online SC 1517 has categorically

stated that no single party can be permitted to unilaterally appoint the

Arbitrator, as it would defeat the purpose of unbiased adjudication of dispute

between the parties. The aforesaid decision in Perkins (Supra) has been

followed by a Coordinate Bench of this Court in Proddatur Cable TV Digi

Services Vs. Citi Cable Network Limited: (2020) 267 DLT 51. Thus, the

Arbitrator either has to be appointed with the consensus of the parties or by

this Court.

14. During the course of hearing, learned counsel appearing for the

parties pressed that this Court may appoint Arbitrator to adjudicate the

disputes pending amongst the parties.

15. Accordingly, Mr.P.B. Vijay, (Civil Engineer) (Mobile:

9810543411) is appointed sole Arbitrator to adjudicate the disputes between

the parties.

16. The arbitration shall be conducted under the Delhi International

Arbitration Centre (DIAC). The fee of the Arbitrator shall be in accordance

with the schedule of fees prescribed under the Delhi International

Arbitration Centre (DIAC) (Internal Management) Rules and Delhi

International Arbitration Centre (Administrative Cost and Arbitrators' Fees)

Rules, 2018.

17. The learned Arbitrator shall ensure compliance of Section 12 of

Arbitration and Conciliation Act, 1996 before commencing the arbitration.

18. The present petition is accordingly disposed of.

19. Pending application also stands disposed of

20. A copy of this order be sent to the learned Arbitrator for information.

(SURESH KUMAR KAIT) JUDGE NOVEMBER 10, 2021 ab

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter