Tuesday, 28, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S M P Tyagi Engineers And ... vs Union Of India & Ors.
2021 Latest Caselaw 3348 Del

Citation : 2021 Latest Caselaw 3348 Del
Judgement Date : 7 December, 2021

Delhi High Court
M/S M P Tyagi Engineers And ... vs Union Of India & Ors. on 7 December, 2021
$~4
*     IN THE HIGH COURT OF DELHI AT NEW DELHI
%                                             Date of decision: 07.12.2021
+     ARB.P. 1053/2021
      M/S M P TYAGI ENGINEERS AND
      CONTRACTORS                                         ..... Petitioner
                          Through      Ms. Seema Singh, Adv.

                          versus

      UNION OF INDIA & ORS.                             .... Respondents
                    Through            Mr. Bhagvan Swarup Shukla, CGSC
                                       with Mr. Sarvan Kumar, UOI

      CORAM:
      HON'BLE MR. JUSTICE SURESH KUMAR KAIT

                          J U D G M E N T (oral)

1. The present petition has been filed under Section 11 (6) of the

Arbitration and Conciliation Act, 1996 seeking appointment of sole

Arbitrator in terms of Arbitration Clause 70 of IAFW 2249 forming the part

of contract entered between the parties.

2. Petitioner herein is a contractor, who claims to have been engaged by

the respondents, respondent No.1- Union of India and respondent No.2,3 &

4 subordinates of respondent No.1, on several occasions for carrying out

various constructions and other activities.

3. The basis of present petition rests upon Arbitration Clause 70 of

IAFW 2249 forming the part of contract entered between the Parties, which

was entered into pertaining to a work order bearing No.

CEWAC/GUR/26/20 17-18 to the tune of sum of Rs 3,02,26,089.80/-

pursuant to acceptance letter dated 21.09.2017 against a tender for the work

CA NO. CEWAC/GUR/T-52/2017-lS:ADDN ALTN TO SMQ OF SAFED

NAGAR AREA PH I AT VSV GURGAON published on 27.07.2017.

4. It is averred in the present petition that as per the Work Order issued

on 05.10.2017 by the respondent No.4, date of handing over of the site for

the execution of the contract work was 16.10.2017 and date of completion of

the contract work was 15.01.2019.

5. Learned counsel for petitioner submits that the petitioner on

26.10.2017, issued letter seeking approval of samples of various items from

the Respondent /GE (I)(AF)MES GURGAON-122001 and vide letter dated

29.10.2017, submitted names of four supervisors along with tokens for

personnel, for execution of the work at site. Furthermore, sample approval

for certain more items was also requested on the same date vide letter dated

29.10.2017. According to petitioner, the work was successfully completed at

site in all three phases. The completion letter for the work being completed

at site was issued vide letter dated 01.10.2018, 03.03.2019 & 12.03.2020.

Thereafter, certain disputes arose between the parties.

6. According to petitioner, notice dated 05.09.2020 was sent to the

respondents seeking appointment of Arbitrator under condition 70 of IAFW

2249 for adjudication of disputes under the contract Agreement, which was

replied to vide letter dated 07.09.2021 seeking further action. However,

respondents failed to appoint Sole Arbitrator as per the Arbitration Clause.

Therefore, the present petition has been filed.

7. Learned counsel for petitioner submits that Sole Arbitrator may be

appointed to adjudicate the dispute between the parties.

8. Learned counsel appearing on behalf of respondents submits that he

has no objection if sole Arbitrator is appointed for adjudication of dispute

between the parties, however, has brought attention of this Court to a Notice

dated 30.11.2021 issued by the respondent to petitioner herein, nominating

names of three Arbitrators, as suggested by the department.

9. During the course of hearing, counsel appearing both the sides have

consented upon the name of Mr. R.P. Singhal, ADG being appointed as

Arbitrator in this case.

10. Accordingly, the present petition is allowed and Mr. R.P. Singhal,

ADG (Arbitration) (as suggested by respondents) is appointed sole

Arbitrator to adjudicate the dispute between the parties in terms of

Arbitration Clause 70 of IAFW 2249 forming the part of contract entered

between the parties.

11. Since the aforenamed Arbitrator has been appointed with the consent

of the parties, therefore, compliance under Section 12 of Arbitration and

Conciliation Act, 1996 is dispensed with.

12. The present petition stands disposed of accordingly.

13. A copy of this order be sent to the learned Arbitrator for information.

(SURESH KUMAR KAIT) JUDGE DECEMBER 07, 2021 rk

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter