Citation : 2020 Latest Caselaw 636 Del
Judgement Date : 30 January, 2020
IN THE HIGH COURT OF DELHI AT NEW DELHI
Judgment delivered on: January 30, 2020
+ ARB. A. (COMM.) 1/2020, CAV. 34/2020 & I.As. 443/2020,
444/2020
GMR HYDERABAD VIJAYAWADA EXPRESSWAYS LTD.
..... Petitioner
Through: Mr.Rajiv Nayar, Sr. Adv. with
Mr.Mahesh Agarwal, Mr.Rishi
Agrawala, Ms.Megha Mehta
Agrawal, Mr.Nishant Rao and
Ms.Shruti Arora, Advs.
versus
NATIONAL HIGHWAYS AUTHORITY OF INDIA
..... Respondent
Through: Mr.Manish K. Bishnoi, Mr.Umang
Raj, Mr.Anurag Sarda and Mr.Sachin
Sharma, Advs.
+ ARB. A. (COMM.) 2/2020 & I.As. 621/2020, 622/2020
NATIONAL HIGHWAYS AUTHORITY OF INDIA
..... Petitioner
Through: Mr.Manish K. Bishnoi, Mr.Umang
Raj, Mr.Anurag Sarda and Mr.Sachin
Sharma, Advs.
versus
GMR HYDERABAD VIJAYAWADA
..... Respondent
Through: Mr.Ciccu Mukhopadhyaya, Sr. Adv.
with Mr.Mahesh Agarwal, Mr.Rishi
Agrawala, Ms.Megha Mehta
Agrawal, Mr.Nishant Rao and
Ms.Shruti Arora, Advs.
ARB.A.01/2020 and connected matter Page 1 of 8
CORAM:
HON'BLE MR. JUSTICE V. KAMESWAR RAO
JUDGMENT
V. KAMESWAR RAO, J
CAV. 34/2020 IN ARB. A. (COMM.) 1/2020 Learned counsel for the caveator has put in appearance. Caveat stands disposed of.
ARB. A. (COMM.) 1/2020 & ARB. A. (COMM.) 2/2020
1. The aforesaid two appeals have been filed by the appellants GMR Hyderabad Vijayawada Expressways Ltd. ('M/s GMR', for short) and National Highways Authority of India ('NHAI', for short) under Section 37 of the Arbitration and Conciliation Act, 1996 ('Act', for short) challenging a common order dated December 09, 2019 ('impugned order', for short) passed by the Arbitral Tribunal wherein the learned Tribunal has inter-alia stated as under;-
"XXXX XXXX XXXX The Tribunal is of the considered view that while passing any interim order of the nature prayed for, three factors have to be taken into consideration. They are prima facie case, balance of convenience and irreparable loss. These factors have to be cumulatively considered.
Obviously the merits of the case will be dealt with in the Award to be pronounced. But taking into consideration the consequences of the impugned letter
/ notice dated 18.11.2019 which essentially amounts to termination of the Concession Agreement, (though it is a suspension of the arrangement,) the Tribunal is of the view that the Claimant has to deposit the following amounts by the dates indicated on without prejudice basis, as an interim measures.
1) By 31.12.2019 Rs.25 Crore
2) By 31.01.2020 Rs.25 Crore
3) By 29.02.2020 Rs.25 Crore
In case, the award is not delivered by 29.02.2020, the matter shall be taken up thereafter for further directions.
In case of failure to make deposit of the stipulated amounts by the dates indicated, this order shall not be operative.
The amounts when deposited shall be kept in a no lien escrow account which will carry interest as per the applicable bank rates. The utilization of the amount would depend upon the results of the Award to be delivered.
Ordered accordingly."
2. Some of the brief facts to be noted with regard to both the appeals are that the parties are before the Arbitral Tribunal for adjudication of certain disputes which arose between them. M/s GMR is the Claimant and NHAI is the respondent. The learned Tribunal has reserved the matter for Award.
3. While the proceedings being in that position, the NHAI
issued a communication dated November 18, 2019 to the M/s GMR wherein they, by referring to the provisions of the Concession Agreement date October 9, 2010 ('Concession Agreement', for short), has by stating that M/s GMR has not paid to NHAI concession fee since April 01, 2015, which resulted in a severe financial distress and thereby impacting its public obligations of building other highways, issued notice in exercise of rights and powers conferred upon it by virtue of the provision contained in Article 36 of the Concession Agreement to suspend the rights of the concessionaire (M/s GMR) under the Concession Agreement. It is this order, which resulted in an application under Section 17 of Act, filed by the M/s GMR before the learned Tribunal wherein the impugned order has been passed.
4. The submissions of Mr. Manish K. Bishnoi, in support of the appeal filed by the NHAI are, that the Tribunal in the impugned order directed M/s GMR to make deposit of Rs.25 crores each in three months, which amounts were to be kept in a no-lien escrow account as an interim-measure, is too meager and insignificant an amount considering the outstanding premium obligations of the M/s GMR being around `554.84 Crores and that the impugned order is prejudicial to the NHAI, as it effectively bars the NHAI from recovering its admitted dues under the Concession Agreement and from exercising its rights under the Concession Agreement. He stated that the learned Tribunal has not considered the factors namely prima facie case, balance of convenience and irreparable loss being caused to the parties. He further stated that the Tribunal has failed to
appreciate the claim raised by the M/s GMR is still in the nature of a 'Claim' only and no debt liability „eo instanti‟ arises in praesenti in its favour till it has been adjudicated and an award passed is in its favour. He has relied upon the judgment of the Supreme Court in the case of Union of India vs. Raman Iron Foundry (1974) 2 SCC 231. He also relied upon Clause 44.3.5 of the Concession Agreement to contend that the Concession Agreement provides, rights and obligations of the parties shall remain in full force and effect, pending the Award in any arbitration proceedings there under. Thus, he submitted M/s GMR cannot say that it will not pay premium amount citing pendency of arbitration proceedings. It was also his submission, by drawing my attention to Clauses like 26.2, 26.3 and 26.4 of the Concession Agreement that, on a conjoint reading it is clear that the premium is part of the concession fee and liability to pay the premium is independent of revenue generation. He further stated that the Tribunal failed to appreciate the fact that the amount claimed by NHAI is around `554.84 Crores and the liability to deposit the premium was a quantified amount flowing from the Concession Agreement. He has drawn my attention to various applications filed by M/s GMR from time to time and the orders passed by the Tribunal on those applications to contend that the NHAI has been making efforts to claim the premium payable as per the Concession Agreement but could not recover the same in view of the those orders. To sum up, it was his submission that the Tribunal could not have exercised the jurisdiction when M/s GMR is in breach of Concession
Agreement. He has also relied upon the following two judgments in support of his contentions:-
(i) (2007) 7 SCC 125 Adhunik Steels Ltd. v. Orissa Manganese and Minerals (P) Ltd.;
(ii) (2016) 11 SCC 720 Gangotri Enterprises Limited v. Union of India and Others;
5. On the other hand Mr. Ciccu Mukhopadhyaya, learned Senior Counsel has stated that the commercial operation date was achieved on December 20, 2012. The first claim letter in respect of change in law / claim was issued on July 06, 2013. He stated that the plea of Mr. Bishnoi that there is no claim in praesenti is a mis-conceived argument, as the claim arises from the Concession Agreement. In other words, he stated that the claim of M/s GMR is not for damages, which can only be paid upon determination. He stated that the claim of the M/s GMR is for an amount of `1341 Crores whereas the claim of NHAI in terms of letter dated November 18, 2019 is only for `554.84 Crores, which according to M/s GMR is not payable at all. Alternatively, the amount being much less, can be set off against the amount to be granted in favour of M/s GMR.
6. According to him, M/s GMR is aggrieved by the impugned order as the same shall have disastrous consequences affecting the subject matter of the arbitration. The Arbitral Tribunal ought to have appreciated that the arguments have concluded in the proceedings and the matter has been reserved for Award and status quo should have been maintained. He laid stress on the fact that almost entire amount of toll collection has
been utilized for payment to the lenders and small percentage utilized for operation and maintenance. There is no surplus available for payment of premium. In the last, he stated that the dates on which payments have been directed to be made by the learned Tribunal be deferred as there is a likelihood that Award may come by that time.
7. Having heard the learned counsel for the parties, from the submissions made, it is noted that the grievance of NHAI is primarily (i) the impugned order has the effect of staying its claim of `554.84 Crores; and (ii) staying the suspension of the Concession Agreement.
8. On the other hand, the grievance of GMR is, that pending adjudication of the dispute between the parties, the Tribunal could not have directed the GMR to deposit `25 Crores each, in the month of December 2019, January 2020 and February 2020.
9. I have already reproduced the operative part of the impugned order. It is a conceded case of the parties that the application filed by the GMR under Section 17 of the Act has not been disposed of.
10. The order passed by the learned Tribunal is pending adjudication of the dispute between the parties. The Tribunal has stated that the merits of the case will be dealt with in the Award. Pending pronouncement of the Award, it directed M/s GMR to deposit the amount, as per the schedule laid therein. No doubt and it is a conceded case of the parties that the order has the effect of NHAI being unable to claim the amount of `554.84 Crores and staying the suspension of the Concession Agreement
but the Tribunal's order is primarily on the ground that it is adjudicating the dispute between the parties and merits of the case shall be dealt with in the Award and also making it clear that if the Award is not delivered by February 29, 2020, the matter shall be taken up for further directions and also in case of failure to make deposit of the stipulated amount by the dates indicated, the order shall not be operative. In view of such a conclusion, this Court holds that the impugned order does not require any interference at the behest of both the parties.
11. The appeals are dismissed. No costs.
I.As. 443/2020 & 444/2020 in ARB. A. (COMM.) 1/2020 I.As. 621/2020 & 622/2020 in ARB. A. (COMM.) 2/2020
Dismissed as infructuous.
V. KAMESWAR RAO, J
JANUARY 30, 2020/ak
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!