$~7, 13, 14 and 21
*     IN THE HIGH COURT OF DELHI AT NEW DELHI

%                                                          Date of decision: 05.07.2019

+       W.P.(C) 6842/2019 and C.M. Appl. No. 28545/2019 (for stay)
        NITIN KUMAR GARG                                                  ..... Petitioner
                     Through:                        Mr. Lovish Sharma and Mr. Gobind
                                                     Malhotra, Advocates.

                                   versus

        DELHI DEVELOPMENT AUTHORITY                 ..... Respondent
                        Through: Mr. Kush Sharma and Ms. Asiya
                                 Khan, Advocates for DDA.
+       W.P.(C) 6818/2019

        ROMI GUPTA & ANR                                               ..... Petitioners
                     Through:                        Mr. Sarthak Bhatia and Mr. Sanil
                                                     Garg, Advocates.
                                   versus

        DELHI DEVELOPMENT AUTHORITY               ..... Respondent
                     Through: Mr. Kush Sharma and Ms. Asiya
                              Khan, Advocates for DDA.

+       W.P.(C) 6836/2019 and C.M. Appl. Nos. 28534/19 (for interim
        relief) 28535/2019 (for exemption)

        MEENU JAIN                                                        ..... Petitioner
                                   Through:          Mr. Prateek Sharma, Advocate.

                                   versus

        DELHI DEVELOPMENT AUTHORITY THROUGH
        ITS VICE CHAIRMAN VIKAS SADAN     ..... Respondent

W.P.(C) Nos. 6842/2019, 6818/2019, 6836/2019 & 6981/2019                            Page 1 of 8
                                               Through:          Mr. Kush Sharma and Ms. Asiya
                                                                Khan, Advocates for DDA.

           +        W.P.(C) 6981/2019 and C.M. Appl. No. 29041/2019 (for stay)
                    PATIALA KASHMIR ROADWAYS PVT. LTD.         ..... Petitioner
                                 Through: Mr. Niloy Das Gupta and Mr. Arun
                                          Kumar Sharma, Advocates.
                                 versus

                    DELHI DEVELOPMENT AUTHORITY                ..... Respondent
                                 Through: Mr. Pawan Mathur, SC for DDA with
                                           Mr. Kush Sharma, Advocate.
                    CORAM:
                    HON'BLE MR. JUSTICE G.S. SISTANI
                    HON'BLE MS. JUSTICE JYOTI SINGH

                                                         JUDGMENT

G.S. SISTANI, J. (ORAL)

1. All these four writ petitions involve similar facts and almost identical issues have been raised and, therefore, they being disposed of by a common judgment.

2. Three writ petitions bearing W.P.(C) Nos. 6818/2019, 6842/2019 and 6836/2019 relate to e-auction by the Delhi Development Authority (DDA) of certain residential plots. The plot numbers, which are subject matter of each writ petition, are being detailed herein below:-


Srl. No.   W.P.(C) Nos.    Auction      Auction           No. of      Total    Reserve      H1 Bid (Rs)   H1 Bidder
                           Sub Item     Description of    Bidders     No. of   Price (rs)
                                        Work                          Bids

1          W.P.(C)         Sl No.       Rohini Sec-7      1           1        11254848     11304848      Meenu
           6836/2019       100 Plot     Block E-4                                                         Jain

                           Blk E-4




 2   W.P.(C)         Sl No.       Rohini Sec-7     1            1    5804026   5854026   Nitin
    6842/2019       118 Plot     Block E-4                                              Kumar

                    Blk E-4

3   W.P.(C)         Sl No.       Plot No. 47 C-   4            8    1472640   1872640   Shilpee
    6818/2019       248 Plot     4 Block New                                            Kumari
                    No. 47       Kondli
                    Blk C-4

4   W.P.(C)         Sl No.       Plot No. 52 C-   3            1    1472640   1522640   Romi
    6818/2019       253 Plot     4 Block New                                            Gupta
                    No. 52       Kondli
                    Blk C-4

5   W.P.(C)         Sl No.       Plot No. 47 C-   5            29   1472640   2922640   SUSHIL
    6818/2019       316 Plot     5 Block New                                            KUMAR
                    No. 47       Kondli                                                 GIRI
                    Blk C-5

6   W.P.(C)         Sl No.       Plot No. 52 C-   5            15   1472640   2222640   Akash
    6818/2019       321 Plot     5 Block New                                            Gupta
                    No. 52       Kondli
                    Blk C-5




3. Writ petition, being W.P.(C) No. 6981/2019, relates to e-auction by the DDA of a commercial plot bears no.BT-5/255 Mangolpuri Industrial Area, Phase-I, New Delhi, held on 15th April, 2019 with the reserve price of Rs.4,20,48,000/-. The petitioner had deposited earnest money amounting to Rs.21,02,459/- on 20th April, 2019. The respondent DDA had informed the petitioner vide e-mail dated 27.4.2019 that the e-auction had ended on 26.4.2019 and the bid of the petitioner was the highest. However, later the EMD was refunded directly into the bank account of the petitioner on 6.6.2019, without assigning any reason.

4. The common facts that emerge in these writ petitions are that the DDA issued a notice for e-auction of plots on 9.3.2019. The Brochure was uploaded on 1.4.2019. The petitioners submitted their bid documents, along

with Earnest Money Deposit (EMD) on different dates. E-auction was held on 24.4.2019/26.4.2019. The petitioner in W.P.(C) No. 6818/2019 received a mail informing him that he has emerged as the highest bidder in the auction process. Similar intimations were also received by the petitioners in the other writ petitions. The common grievance of the petitioners is that they learnt subsequently that their bids have been cancelled.

5. The learned counsel appearing for the DDA submits that since the petitioners were single bidders and in the opinion of the Competent Authority, the plots in question could fetch a much greater value. It is submitted that this was subsequently established from the fact that when all these plots were re-auctioned far higher bids were received. Mr. Sharma has handed over a chart/tabulation in Court in support of his submission, which we have taken on record.

6. Learned counsels for the petitioners submit that the bid document nowhere states that in case of a single bidder, the auction would be cancelled. Additionally, they contend that serious prejudice has been caused to their rights as they could not participate in the subsequent bid. It is also pointed out that after the first bid was accepted, the system got locked and the petitioners were not allowed to participate again with respect to other plots. Thus, they have been deprived of their valuable rights, except Ms. Meenu Jain, petitioner in W.P.(C) No. 6836/2019, who had also participated in the subsequent auction. It is also submitted that in case the reason for rejection is that the DDA wanted competition and was not willing to consider a single bid, in that event, the DDA should have postponed the auction and should have invited the bids again, in which case, the petitioners would have participated.

7. There are two other grievances which have been raised by learned counsels for the petitioners. Firstly, it is submitted that in terms of Clauses 2.4.6 and 2.6 (iii) of the tender conditions, in case a bidder was unsuccessful the Competent Authority was required to communicate to the bidder the non- acceptance of his bid within 15 days of the date of completion of the e- auction process. In addition, there was an obligation on the Competent Authority to return the EMD paid by the unsuccessful bidders without interest. The said EMD had to be refunded electronically directly in their bank account and that too within 15 days of the completion of the auction process. It is submitted that these conditions of the tender have not been complied with and the EMDs deposited by the respective petitioners were not refunded within 15 days. The contention thus is that since the refund was made by the DDA far beyond the period of 15 days, DDA is liable to pay interest on the amount illegally withheld by them. Secondly, the respondent has not informed the petitioners as to what is the reason for non- acceptance of the bid. It is submitted that the least that is accepted of a public authority is to communicate the reasons for not accepting the bid, more particularly, when at the initial stage in the first tender the petitioners ware informed that they had emerged as the highest bidders.

8. Responding to these contentions, learned counsel for DDA has submitted that in fact the reasons for not accepting the bids of the petitioners was informed and this would be evident from a document which was placed on the e-portal. Learned counsel has drawn the attention of the Court to the document which has been placed on record by the petitioner himself in W.P.(C) 6842/2019. He points out that the last column of this document is titled „reason‟ and in case the petitioner would have opened the document he would have known the reason for rejection. He further argues that the reason

of rejection was that the single bid was not conducive to competition and once the DDA was able to fetch higher prices, after survey of the adjoining plots, it was decided not to accept the single bids.

9. In response to the argument of the petitioner that the EMD was not refunded within 15 days in terms of clauses 2.4.6 and 2.6(iii), the learned counsel submits that he has no explanation or justification for the delay.

10. We have heard learned counsels for the parties.

11. To appreciate the contentions of learned counsels for the parties we deem it appropriate to reproduce the relevant portion of Clause 2.4 of the tender document:-

"2.4 Evaluation of Bid 2.4.1 The accepting officer, subject to confirmation of the VC, DDA, normally accept the highest Bid for a plot, provided that it is above the reserve price and found to be competitive enough to reflect the market value of the plot auctioned for. 2.4.2 The confirmation of the highest Bid shall be in the sole discretion of the Vice Chairman, DDA who does not bind himself to confirm the highest bid and reserve to himself the right to reject all or any of the bid without assigning any reasons. Any Bid not fulfilling any of the prescribed conditions or incomplete in any respect shall be rejected"

12. A reading of this Clause would show that discretion is vested in the Vice Chairman, DDA to reject the bids, without assigning any reason. Learned counsel for DDA has explained that in the present case, this clause was invoked not on account of arbitrary or whimsical reasons, but when it was noticed that the adjoining plot had been auctioned at a much higher price.

13. We find force in the submission made by learned counsel for the DDA. The tabulation handed over by learned counsel for the DDA would show gross difference of value in the first auction. The same reads as under:-

Sl    Phase III Property No.    Reserve          Price   Amount Quoted by Name of the H1        Amount Quoted by the   Difference of H1
No.                             (In INR)                 the bidder in Phase Bidder             bidder in Phase IV     Value of Phase III
                                                         III          Auction                   Auction   25.06.2019   &     IV   Auction
                                                         24.04.2019                             (In INR)               (In INR)
                                                         (In            INR)




1     Sl No. 69 BT-5/255 42,048,000.00                   42,148,000.00    Patiala Kashmir Not placed for Auction
      Mangolpuri Industrial                                               Roadways       Pvt.
      Area Phase-I                                                        Ltd.
                                                                          W.P. (c) - 6981/19



2     Sl No. 118, Plot No         5,804,026.00            5,854,026.00    Nitin       Kumar         23,304,026.00        17,450,000.00
      103, Block-E4, Rohini                                               W.P. (c) - 6842/19




3     Sl No. 253, Plot No.        1,472,640.00            1,522,640.00    Romi         Gupta         2,687,640.00      1,165,000.00
      52, Block C-4, New                                                  W.P. (c) - 6818/19
      Kondli                                                              [Petitioner No. 1]




4     Sl No. 252, Plot No.        1,472,640.00            1,522,640.00    Neetu        Gupta         2,672,640.00      1,150,000.00
      51, Block C-4, New                                                  W.P. (c) - 6818/19
      Kondli                                                              [Petitioner No. 2]




5     Sl No. 100, Plot No.       11,254,848.00           11,304,848.00    Meenu          Jain       33,004,848.00        21,700,000.00
      48, Block E-4, Rohini                                               W.P. (c) - 6836/19




14. On examining this tabulation, we are satisfied that the Competent Authority exercised the powers vested in Clause 2.4 without any mala fide and for justifiable reasons, and we do not find any fault in the action so taken which would require interference in these proceedings.

15. As far as the submission of non-communication of the reasons is concerned, we find that the information was infact provided on the website. The document which we have referred to above, reflects the reason as well. There are, however, no justifiable reasons forthcoming on behalf of the DDA as to why the EMDs were not returned to the petitioners within fifteen days. For this lapse, we direct the DDA to pay interest at the rate of 8% per annum for the period beyond 15 days till the amount was returned. This amount shall be cleared within a period of four weeks from today.

16. As regards the contention of the learned counsel appearing in W.P.(C) 6842/2019 that the DDA be directed to consider that in case of a single bid in an e-auction rather than rejecting the bid, the auction itself should be postponed so that the single bidder is not deprived of his right to participate in the other auctions and also in case the re-auction is to take place then re- auction should be conducted only after the bidders of the earlier auctions are informed. We are of the view that there is some substance in the said contention. We therefore deem it fit to request the DDA that it should consider this suggestion made by the learned counsel for the petitioner, in future tenders, if so advised.

17. With the aforesaid observations, all the four writ petitions are dismissed. Interim orders, if any, stands vacated.

G.S.SISTANI, J

JYOTI SINGH, J

JULY 05, 2019/AK/S

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter