Citation : 2019 Latest Caselaw 1922 Del
Judgement Date : 8 April, 2019
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: April 08, 2019
+ W.P.(C) 3375/2019, CM No. 15459/2019
CHENAB BRIDGE PROJECT UNDERTAKING ..... Petitioner
Through: Mr. Mukul Rohatgi and Mr. Dayan
Krishnan, Sr. Advs. with Mr.Anirudh
Krishnan, Mr.Balaji Srinivasan,
Mr.Adarsh Subramanian, Mr.Hitesh
Kumar, Ms.Garima Jain, Ms. Pallavi
Sengupta, Mr.Siddhant Kohli, Advs.
versus
NORTHERN RAILWAY AND ANR. ..... Respondents
Through: Mr. J.K.Singh, Standing Counsel with
Ms. Madhulika Agrawal and
Mr.Harsh Pandit, Advs. for Northern
Railway-R-1
Ms.Kiran Bhagalia, Adv. with
Ms. Suchitra A. Chitate and
Ms.Pallavi Bali, Adv. for R-2
CORAM:
HON'BLE MR. JUSTICE V. KAMESWAR RAO
V. KAMESWAR RAO, J. (ORAL)
1. The present petition has been filed by the petitioner /
Chenab Bridge Project Undertaking with the following prayers:
"In view of the above, the Petitioner humbly prays that this Hon'ble Court may be pleased to issue:
i. Any writ, order or direction in the nature of mandamus and/or any writ, order or direction directing the Respondents to enforce the findings in
the minutes of Meeting dated 15.05.2018 signed by the Respondent No.1;
ii. Any writ, order or direction in the nature of certiorari and/or any writ, order or direction to quash the impugned notice dated 27.03.2019 issued by the Respondent No. 3;
iii. Any writ, order or direction in the nature of mandamus and/or any writ, order or direction to the Respondent No. 3directing it enter in to supplementary agreements with the Petitioner and thereby act in adherence of Clause 41 of the GCC and to conclude the variations at the earliest;
iv. For such further and other orders as the nature and circumstances of the case may require and costs, if any against the Respondents for this petition."
2. Some of the relevant facts as noted from the writ petition
are, pursuant to a tender process initiated by respondent no.2,
Konkan Railway Corporation Limited (KRCL), the petitioner was
awarded the contract for design and construction of a Special Bridge
across the River Chenab at Kilometer 50/800 on the Katra - Laole
Section of Udhampur-Srinagar-Baramulla Rail Link Bridge. The
duration of the contract was set at 30 months with a date of
completion as April 30, 2007. There is no dispute that the contract
has not yet been completed.
3. It is the case of the petitioner, that on April 4, 2005, it had
submitted a revised Design Based Note (DBN) complying with
modifications, to DBN submitted with Tender, proposed by the
Respondent No.2 and on June 2, 2005, the respondent no.2 KRCL
provisionally approved the said DBN. It is also pleaded that KRCL
on its own issued revised DBN on September 5, 2006.
Subsequently on April 23, 2010, final DBN was issued by KRCL.
As on date it is the DBN of 2010, which is valid, with correction
slips to the same having been issued in 2011 and 2013.
4. It is the case of the petitioner that it must be paid for
difference in quantities of structural steel between tender DBN and
2010 DBN. For the purpose of reaching a via-media in the
interregnum the petitioner was willing to accept payment for the
difference in quantities issued between 2005 DBN and 2010 DBN.
It is the case of the petitioner that on May 15, 2018, deliberations
have been held when the officer of the Northern Railway, for whom
respondent no.2 is executing the project, was also present, wherein
the following decision was taken:
Sl. Item Remarks / Status
No.
2. Commercial issues It has been jointly decided
of enhanced steel that KRCL will forward the
quantity details submitted by WSP,
(designer of this bridge)
regarding enhanced quantity
of steel over and above
approved DBN of 2005 to
M/s Flint & Neill, the proof
checker. CBPU should
arrange to provide any
additional information, if
asked by M/s. Flint & Neil.
KRCL should organize a
meeting of the designer and
the proof of checker to
conclude this issue
expeditiously.
5. It is their case that the minutes of meeting dated May 15,
2018 needs to be implemented. It is averred that further the KRCL
on August 29, 2018 contended that the statement in the minutes of
meeting dated May 15, 2018 is only advisory and on November 6,
2018 issued a letter enclosing therewith a letter of respondent no.1
negating the promise made in the minutes of meeting dated May 15,
2018. It appears, the petitioner has informed the KRCL that it was
unable to proceed with the work on the ground that several
modifications / variations brought about by respondent no.2 KRCL
attracted Clause 41 of GCC whereby the petitioner ought not to
proceed with the work until supplementary agreements are entered
into by the parties for such modifications / variations.
6. It is noted that on March 27, 2019, respondent no.2 invoked
clause 62 of the GCC by issuing a show-cause notice giving
petitioner 7 days' time to commence the work to make good the
progress failing which further action as provided under Clause 62 of
the GCC, viz., terminating the contract between respondent no.2
KRCL and the petitioner and a decision to complete the work at the
petitioner's risk and cost would be taken.
7. Mr. Mukul Rohatgi and Mr. Dayan Krishnan, learned Sr.
Counsels appearing for the petitioner submitted that they are
conscious that an arbitration clause exists in the agreement executed
between the petitioner and the KRCL, but as this petition has been
filed seeking a direction to the Northern Railway to implement the
Minutes of the Meeting dated May 15, 2018, the present petition is
maintainable. It is their submission that the project being of
national importance, respondent no.1 was actively involved in the
project monitoring / execution of the project even though they are
not signatory to the contract with the petitioner. In other words, the
most crucial decisions in respect to the project have always been
taken pursuant to the approval of the respondent no.1. So, the
appropriate remedy is to invoke the writ jurisdiction of this court for
a direction to the respondent no.1 to ensure the implementation of
the minutes of the meeting dated May 15, 2018. It was submitted
by them that on July 6, 2018 the parties acted in furtherance of the
decision dated May 15, 2018, inasmuch as the required documents
have been submitted to the proof-checker and in fact CAO
instructed the KRCL to ask the proof-checker to expedite the
proceedings. They stated that the stand of the respondent KRCL in
the letter dated August 29, 2018 is that the minutes of the meeting
dated May 15, 2018 are only advisory is untenable. Even the letter
dated November 02, 2018 of respondent no.1 has been issued by
completely ignoring the Minutes of Meeting dated May 15, 2018.
According to them, the increase in structural steel quantities have to
be decided due to changes in DBN. It is their submission that DBN
2006 was neither approved nor implemented at any point of time.
In fact, final DBN of 2005 incorporated the suggestions given by
the petitioner. It was their submission that based on DBN 2005, the
petitioner had altered its position by executing works based on the
said approved DBN, therefore the respondents are estopped from
going back on their promise. So, in substance, their submission was,
as the increase in structural steel is relatable to variations /
modifications in the work, clause 41 of the GCC gets attracted and
the parties mandatorily have to enter into a supplementary
agreement incorporating the agreed terms and conditions before the
work continues. They stated that despite requests to the respondents
to enter into supplementary agreement on agreed terms and
conditions so that the work can be resumed, the same has not been
acceded to. Mr. Rohatgi and Mr. Krishnan had relied upon the
following judgments of the Supreme Court and this Court in support
of their submissions about the maintainability of the writ petition
despite an arbitration clause which according to them shall not be
applicable as the writ petition has been filed seeking a direction
against the Northern Railway to implement the minutes of meeting
dated May 15, 2018.
1. Union of India and Ors. v. Tantia Construction Pvt.
Ltd. 2011 5 SCC 697
2. Gujarat State Financial Corporation v. M/s. Lotus Hotels Pvt. Ltd. 1983 2 SCC 379
3. LPA 57/2019 NTPC Ltd. and Anr. V. M/s BGR Mining and Infra Ltd.
8. On the other hand, Ms. Kiran Bhagalia, learned counsel for
the respondent no.2 / KRCL had challenged the maintainability of
the petition on three grounds; (i) the plea of the petitioner that for
the limited relief sought for, i.e., implementing the minutes of
meeting dated May 15, 2018 by the Northern Railway, the writ
petition is the only remedy, is untenable as the contract for the
design and construction of a special bridge across the river Chenab
has been executed by the petitioner with the respondent no.2 and the
issue in question about the increase in the structural steel is a related
issue with contract and the petition under the garb of seeking a
direction against the Northern Railway is not maintainable; (ii) there
is an arbitration clause in the agreement executed between the
petitioner and the respondent no.2 and any dispute between the
parties needs to be decided through the arbitration; (iii) there are
disputed question of facts and the writ petition is not an appropriate
remedy.
9. On merit it was her submission that the 2005 DBN was
provisional and this fact had not been contested by the petitioner at
any point of time. It was in the year 2006 that DBN was approved
and the same should be the basis for calculating the increase in steel
till 2010. It was her submission that the only stand of the petitioner
throughout, had been that it is entitled to extra cost because of the
increase in the steel. It did not at any point of time sought
modification of contract. In fact, according to her, the petitioner
had been raising bills, which were being duly paid. Ms. Bhagalia
during her submissions had drawn a distinction between clauses 39
and 41 of the contract to contend that the contract being for
lumpsum amount, the increase in quantities required no
modification. She also stated that clause 41 says, if the parties think
that the contract needs to be modified, then only it can be modified.
She admitted that respondent no.2 is required to pay the petitioner
for the extra material used in the execution of the work. She also
stated no supplementary agreement can be executed without
quantities and rates being determined. In other words, if the
quantities and rates are fixed, the supplementary agreement can be
executed. She justifies the show-cause notice dated March 27, 2019
issued by invoking clause 62 of the GCC. She stated that a
Mandamus cannot be sought by the petitioner against the
respondent no.2, not to exercise the right under the contract. It was
her plea that the filing of the writ petition by the petitioner is not
bona fide and liable to be dismissed. She relied upon the following
judgments of the Supreme Court in support of her submissions:
1. Rajasthan State Industrial Development and Investment Corporation and Anr. V. Diamond and Gem Development Corporation Limited and Anr. 2013 5 SCC 470.
2. State of Jammu and Kashmir v. Ghulam Mohd. Dar and Anr. 2004 12 SCC 327
3. Pimpri Chinchwad Municipal Corporation and Ors.
v. Gyatri Construction Company and Anr. 2008 8 SCC 172
4. State of Bihar and Ors. v. Jain Plastics and Chemicals Ltd. 2002 1 SCC 216
5. Hanil Era Textiles Ltd. v. Puromatic Filters (P) Ltd.
2004 4 SCC 671
10. Mr. J.K. Singh, Adv. who appeared for the respondent /
Northern Railway had submitted that the project, even though of
Northern Railway, the same is being executed through the aegis of
respondent No.2 / KRCL which had issued the tender and awarded
the contract. According to him, there is no agreement between the
Northern Railway and the petitioner and the agreement is between
the petitioner and the respondent no.2 and all financial and
commercial terms have to be looked into by respondent no.2 based
on the contractual stipulations.
11. Having heard the learned counsel for the parties, the issue
which arises for consideration is whether a direction can be issued
to respondents including the Northern Railway to implement the
minutes of the meeting dated May 15, 2018.
12. There is no dispute that the Project in question falls under
the Northern Railway Zone of Indian Railways. The Northern
Railway decided to get the same executed through respondent no.2
KRCL. It is the KRCL which issued the tender. It also issued the
Letter of Acceptance to the petitioner, on being found successful in
the tendering process. The contract incorporates all technical and
commercial terms relatable to the project. The contract has also an
arbitration clause in terms of the arbitration agreement executed
between the parties on February 28, 2012.
13. The plea of Mr. Rohatgi and Mr. Krishnan was, since the
proceedings dated May 15, 2018 were held under the aegis of
Northern Railway, whose project is being executed by the KRCL,
the Northern Railway should ensure that the minutes of meeting
dated May 15, 2018, more specifically item no.2 thereof is
implemented and a supplementary agreement is executed on the
basis of the said decision. The plea of the counsel for the respondent
Northern Railway is that any financial / commercial terms has to be
decided by KRCL based on the contract stipulations. In other
words, the issue of increase in structural steel, whether based on
DBN 2005 or DBN 2006 needs to be looked into by the KRCL in
terms of the stipulations in the contract. If that be so, the petition
against Northern Railway is not maintainable as the issue raised,
which is noted above is an issue connected with the contract
executed between the petitioner and the KRCL and not Northern
Railway. If a need is felt by the petitioner, at a later point of time
to establish the purport of the minutes of the meeting dated May 15,
2018 to mean that extra steel has to be calculated on the basis of
DBN 2005, the petitioner can summon the officer present for the
Northern Railway in such proceedings, that are initiated finally
including Arbitration Proceedings.
14. That apart, I find after the meeting of May 15, 2018, the
parties, i.e., the petitioner and the respondent no.2 KRCL have
moved much forward, as can be seen from the various
communications / documents annexed from Page 252 onwards of
the writ petition, a perusal of the same does reveal that there is a
dispute which has arisen between the petitioner and the KRCL and
the same necessarily has to be decided by the Arbitral Tribunal, on
the same lines of previous 19 claims filed by the petitioner, as
submitted by Ms. Bhagalia during her submissions. Moreover, the
arbitration is the appropriate remedy when disputed questions of
fact arise, as can be inferred from the above, which cannot be
decided on the basis of affidavits (Ref. State of Jammu and
Kashmir v. Ghulam Mohd. Dar and Anr. (Supra))
15. What is glaring in this case is that filing of the present
petition has got triggered because of the issuance of the show-cause
notice dated March 27, 2019 as is clear from the proximity between
the date of show-cause notice, i.e., March 27, 2019 and filing of the
writ petition on April 1, 2019. So, the show-cause notice is only a
ploy for the petitioner to approach this court (after at least 10
months) on the pretext of seeking an implementation of the minutes
of meeting dated May 15, 2018, as I note the petitioner has also
challenged the show-case notice dated March 27, 2019.
16. It is a settled position of law by the Supreme Court in the
case of Union of India v. Kunisetty Satyanarayana 2006 12 SCC
28, wherein the court has deprecated the practice of entertaining
writ petitions questioning the legality of the show-cause notice,
stalling the enquiries as proposed and retarding investigation into
facts, except it is a case of absolute want of jurisdiction of the
authority to investigate into the facts, the writ petition will not be
entertained on the mere asking and as a matter of routine. The said
position of law squarely applicable in the facts of this case as I have
been informed that the petitioner has responded to the show-cause
notice by filing a reply to the same on March 31, 2018 and a
decision is yet to be taken by the competent authority on the said
show-cause notice. It goes without saying that an order to be passed
by the authority concerned shall be subject to arbitration
proceedings as agreed to between the parties to the contract.
17. In so far as the judgments relied upon by Mr. Rohatgi and
Mr. Krishanan in the case of Tantia Construction Pvt. Ltd. (supra)
and Joshi Technologies (supra) on the proposition of law that
arbitration clause is not a bar to invoke the writ jurisdiction when
injustice is caused and rule of law is violated is concerned, there is
no dispute on the said proposition, but it must be noted, as stated
during submissions that the petitioner herein has made 19 claims
against the respondents before the Arbitral Tribunal. There is no
reason why deviation should be made, only on the ground that the
petition is directed against Northern Railway, which plea is without
merit, being not maintainable, in facts. Suffice it to state the
Judgments are distinguishable on facts.
18. Similarly, in so far as the Judgment relied upon by Mr.
Rohatgi and Mr. Krishnan in the case of Gujarat State Financial
Corporation (supra) is concerned, the same would not be relevant
to the facts of this case.
19. In view of my discussion above, this court is of the view
that the present petition is not maintainable and is liable to be
dismissed. Ordered accordingly.
CM. No. 15459/2019 (for Stay) Dismissed as infructuous.
V. KAMESWAR RAO, J
APRIL 08, 2019/jg
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!