Citation : 2018 Latest Caselaw 5685 Del
Judgement Date : 19 September, 2018
$~27
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Decision: 19th September, 2018
+ O.M.P. 1683/2014
M/S BARTONICS INDIA LTD & ANR ..... Petitioners
Through: Mr. Sudipto Sircar, Advocate.
(M:9871908992)
versus
M/S S.E INVESTMENTS LTD ..... Respondents
Through: Mr. P. Nagesh and Mr. Dhruv Gupta,
Advocates. (M:9999877566)
CORAM:
JUSTICE PRATHIBA M. SINGH
Prathiba M. Singh, J. (Oral)
1. The present petition challenging the award dated 12th July, 2014 has been filed under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter, „the Act‟). The learned Arbitrator has awarded in favour of Respondents/Claimants in the following terms: -
"30. This Tribunal therefore holds that the Claimant is entitled to receive a sum of Rs.10,40,87,831/- (Rupees Ten Crore Forty Lacs Eighty Seven Thousand Eight Hundred Thirty One only) due till 10.07.2013 jointly and severally from the two Respondents which they must pay. Further in addition to above sum of Rs.10,40,87,831/-(Rupees Ten Crore Forty Lacs Eighty Seven Thousand Eight Hundred Thirty One only) late fees from 11.07.2013 (Date of start of arbitration) and till 11.07.2017 has been worked out at Rs. 6,45,32,877/-(Rupee Six Crore
Forty Five Lacs Thirty Two Thousand Eight Hundred Seventy Seven Only), however after 11.07.2013 there are two items first the amount of Rs.15,00,000/- (Rupees Fifteen Lacs Only) on 28.09.2013 and TDS adjustment of Rs.8,27,750/-(Rupees Eight Lacs Twenty Seven Thousand Seven Hundred Fifty Only) on 22.10.2013 have to be adjusted to the credit of Respondents, which thus makes a total claim awarded at Rs.16,62,92,958/- (Rs. Sixteen Crore Sixty Two Lacs Ninety Thousand Nine hundred Fifty Eight Only) the Respondents will pay interest on the sum aforesaid @18% p.a. compounded monthly from the date of this award i.e. 12.07.2014 to the date of actual realization and shall also pay the cost of the award/decree to the Claimant which are assessed of Rs.2,50,000/-(Rupees Two Lacs Fifty Thousand Only), which include the fees and administrative charges of the Arbitration and this award is made accordingly."
2. The facts leading up to the passing of the award are that the Petitioners availed of a loan facility of a total sum of Rs.16.5 crores, by way of two separate loan agreements, both dated 19th November, 2010. There were two loan accounts namely; LD2414 and LD2416 i.e. the former for Rs.8 crores and latter for Rs.8.5 crores. LD2414 and LD2416 were to be repaid in 24 instalments equally. Thus, under LD2414, the total payment was to be Rs.9.72 crores with an interest component of Rs.1.72 crores and in LD 2416, the total payment was to be Rs.10,32,75,000/-, with an interest component of Rs.1,82,75,000. Petitioner No.2 acted as a guarantor to the above loans.
3. The Petitioners made payments of a few instalments and did not make the remaining payments. Thus, the Respondents invoked the arbitration clause on 10th July, 2013 and a sole arbitrator was appointed. Orders were
passed under Section 9/Section 15, which are not the subject matter of the present petitions. The final award was thereafter passed on 12th July, 2014.
4. The learned counsel appearing for the Petitioners' submits that the main ground of challenge is that the imposition of late fee is unreasonable and even the interest which has been granted by the arbitrator is on the higher side. Further it is submitted by learned counsel for the Petitioners, Mr. Sudipto Sircar, that the initial amount which was held back by the Respondents at the time of disbursal of the loan, ought to be given credit for. The total amount which has been awarded in favour of Respondents is beyond what was even agreed to in the contract, and thus, is liable to be set aside.
5. On the other hand, Ld. Counsel for the Respondents, Mr. P. Nagesh, submits that the Petitioners admittedly defaulted in making the payments, and therefore, the arbitrator has awarded the interest and the licence fee as per the contractual rate as stipulated in the loan agreements. The submission of the learned counsel is that the arbitrator is bound by the terms of the agreement and cannot go beyond the same. Furthermore, the Petitioners having enjoyed the loan facility and the funds of the Respondents, ought to be made to adhere to the terms of the contract. However, he fairly submitted that insofar as the amount of Rs.4.12 crores is concerned, the adjustment of the same could be given to the Petitioners.
6. Upon hearing the counsels for the parties, one fact which is admitted is the availing of the loan facility. The execution of the loan agreement is also not disputed. This being the position, Petitioners' obligation to repay the loan with interest is also beyond dispute. The only question is as to whether the late fee charges which were to be imposed to the tune of
Rs.5,98,45,837 and Rs.6,45,32,877/- are liable to be granted to the Respondents or not.
7. The loan agreement dated 19th November, 2010 has the following stipulations/terms and conditions: -
"1. The said loans shall carry interest as the flat rate of 10.75% per annum or such modified rates as indicated by the company. In addition to the said interest, the interest tax, service tax or any other tax or levy imposed by the Government and other authorities from time to time shall also be payable by the borrower.
2.That the financed amount shall not exceed Rs.8,00,00,000/- (Rupees Eight Crores Only). This amount may be disbursed in one or more tranches at the opinion of the Company on execution of such documents by the Borrower and Guarantors as required by the Company and this facility will be available for a period of 24 months only from the date of disbursement of the loan tranche.
.....................
7.Without prejudice to the other rights of the Company, if the Borrower defaults in making payments to the Company on due dates, the late fee at the rate of Rs.2/- per thousand per day shall be charged or at such higher rate as the Company may specify from time to time, on the entire outstanding amounts from the date of default till the date of payment of the entire outstanding amount.
............................
Attached to and forming part of Loan/Hypothecation agreement dated 19.11.2010
SCHEDULE "A"
(Description of the hypothecated assets)
All machinery equipments installation and other movables etc, and all other goods & commodities which belongs to the borrower including intangibles assets.
SCHEDULE "B"
(Due Date & Amount of each installment) Case No. Name Date: Amount Interest(Rs) LD-2414 Bartronics 19.11.2010 8,00,00,000/- 1,72,00,000/-
India Ltd
Ins. No. Due Date Amount Principal Interest 1 20.11.10 48,60,000/-
2. 19.12.10 48,60,000/-
3. 19.01.11 48,60,000/-
4. 19.02.11 48,60,000/-
5. 19.03.11 48,60,000/-
6. 19.04.11 48,60,000/-
7. 19.05.11 48,60,000/-
8. 19.06.11 48,60,000/-
9. 19.07.11 48,60,000/-
10. 19.08.11 48,60,000/-
11. 19.09.11 48,60,000/-
12. 19.10.11 48,60,000/-
13. 19.11.11 32,40,000/-
14. 19.12.11 32,40,000/-
15. 19.01.12 32,40,000/-
16. 19.02.12 32,40,000/-
17. 19.03.12 32,40,000/-
18. 19.04.12 32,40,000/-
19. 19.05.12 32,40,000/-
20. 19.06.12 32,40,000/-
21. 19.07.12 32,40,000/-
22. 19.08.12 32,40,000/-
23. 19.09.12 32,40,000/-
24. 19.10.12 32,40,000/-
8. The second loan agreement has clauses which are almost identical except that the loan amount which was disbursed was Rs.8.5 crores and Schedule A and B of the second agreement reads as under: -
"Attached to and forming part of Loan/Hypothecation agreement dated 19.11.2010
SCHEDULE "A"
(Description of the hypothecated assets)
All machinery equipments installation and other movables etc, and all other goods & commodities which belongs to the borrower including intangibles assets.
SCHEDULE "B"
(Due Date & Amount of each installment) Case No. Name Date: Amount Interest(Rs) LD-2416 Bartronics 19.11.2010 8,50,00,000/- 1,82,75,000/-
India Ltd
Ins. No. Due Date Amount Principal Interest
1. 20.11.10 51,63,750/-
2. 19.12.10 51,63,750/-
3. 19.01.11 51,63,750/-
4. 19.02.11 51,63,750/-
5. 19.03.11 51,63,750/-
6. 19.04.11 51,63,750/-
7. 19.05.11 51,63,750/-
8. 19.06.11 51,63,750/-
9. 19.07.11 51,63,750/-
10. 19.08.11 51,63,750/-
11. 19.09.11 51,63,750/-
12. 19.10.11 51,63,750/-
13. 19.11.11 34,42,500/-
14. 19.12.11 34,42,500/-
15. 19.01.12 34,42,500/-
16. 19.02.12 34,42,500/-
17. 19.03.12 34,42,500/-
18. 19.04.12 34,42,500/-
19. 19.05.12 34,42,500/-
20. 19.06.12 34,42,500/-
21. 19.07.12 34,42,500/-
22. 19.08.12 34,42,500/-
23. 19.09.12 34,42,500/-
24. 19.10.12 34,42,500/-
9. In the present petition, it was recorded on 24th December, 2014 that the Petitioners restricts its challenge to the award only to the payment of penalty and rate of interest. It was also recorded that the Petitioners are also willing to pay the principal amount. On 21st April, 2015, the Petitioners were directed to pay the principal amount before the next date, failing which the petition would not be entertained. Thereafter, settlement negotiations took place between the parties, they however failed. As recorded on 24th February, 2016, there was a difference between the parties on what constituted the principal amount and thus, without prejudice, payment of Rs.1 crore was made by the Petitioners in two equal instalments, to be paid by 15th March, 2016 and 31st March, 2016.
10. In view of the fact that the imposition of the late fee and the interest amount are the subject matter of the challenge, the entire principal amount which is due is liable to be paid by the Petitioners. The question is as to what is the principal amount which is due. The calculations in schedule B attached to the loan agreement are based on the total number of instalments that were to be paid back by the Petitioners. Admittedly, the actual
disbursement, against the sanctioned amount was as under:
Loan Account No. Sanctioned Amount Disbursed Amount LD2414 Rs.8 crores Rs.6 crores LD2416 Rs.8.5 crores Rs.6,37,50,000/-
11. As held in M/s. Schifflies India Ltd. & Anr. v. M/s. S.E. Investments Ltd. & Others [OMP 1589/2014 decision dated 7th September, 2018], the late fee charges are in the nature of penalty and thus, cannot be imposed without proving actual loss. The observation in the said judgment is set out below:
"10. However, insofar as the late fee of Rs.2 per thousand per day of default is concerned, the same is in the nature of a penalty. A penalty cannot be imposed as part of the contract unless and until actual loss is established, as per Sections 73 and 74 of the Contract Act. This is the settled position as per Fateh Chand v. Balkishan Dass (1964) 1 SCR 515, and Oil and Natural Gas Corporation Ltd. v. Saw Pipes Ltd. (2003) 5 SCC 705. Thus, the payment of late fee is liable to be set aside."
12. From the above it is clear that 25% of the amount was, therefore, retained as cash collateral by the Respondents. Thus, the adjustment has to be given for the said cash collateral amount. Since, the actual disbursement under both the agreements was Rs.6 crores and Rs.6,37,50,000 i.e. Rs.12,37,50,000/-, the Petitioners are liable to pay the entire principal amount i.e. Rs.12,37,50,000/-. The Respondents are entitled to interest as per clause 1 of the contract till date of award on the sum of Rs.12,37,50,000/- minus any instalment amounts that stand paid by the
Petitioners, which shall be given complete credit for. Thereafter, from the date of award till actual payment, simple interest @18% p.a. shall be payable on the said amount. From the amount so calculated, a sum of Rs.1 crore shall be deducted w.e.f. 1st April, 2016 and interest would be liable to be paid only on the remaining amount. No late fee shall be payable by the Petitioners.
13. The OMP is disposed of accordingly. Parties are directed to bring the calculations as per the above order in order to avoid any ambiguity in future. List on 12th December, 2018.
PRATHIBA M. SINGH JUDGE SEPTEMBER 19, 2018 Rekha
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!