Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Ngc Network India Pvt Ltd vs Orangefish Entertainment ...
2018 Latest Caselaw 5659 Del

Citation : 2018 Latest Caselaw 5659 Del
Judgement Date : 18 September, 2018

Delhi High Court
Ngc Network India Pvt Ltd vs Orangefish Entertainment ... on 18 September, 2018
*     IN THE HIGH COURT OF DELHI AT NEW DELHI
                            Judgment reserved on: 06.09.2018
                            Judgment pronounced on: 18.09.2018
+     O.M.P.(I) (COMM.) 326/2018

      NGC NETWORK INDIA PVT LTD                           ..... Petitioner

                             Through:   Mr. Dayan Krishanan, Sr. Adv. Mr.
                                        Sahil Sethi, Ms. Sneha Jain, Ms.
                                        Snehima Jauhari, Mr. Devvrat Joshi
                                        and Mr. Sanjeevi, Seshadri.

                             versus

      ORANGEFISH ENTERTAINMENT
      PRIVATE LIMITED                                     ..... Respondent
                             Through:   Mr.Suhail Dutt, Sr.Adv. with R.S.
                                        Mittal and Mr. Ankur Manchanda
      CORAM:
      HON'BLE MR. JUSTICE RAJIV SHAKDHER

RAJIV SHAKDHER, J.

Preface

1. This action encapsulates a war of attrition which has been going on

between two entities since August, 2017. The relationship between the

petitioner and the respondent emanates from a Memorandum of

Understanding dated 16.10.2012 (hereafter referred to as 'MOU'). The

MOU was followed by an Addendum dated 01.12.2015 (in short

'Addendum'). The Addendum was executed to essentially extend the tenure

OMP (I) (COMM) No.326/2018 Pg. 1 of 65 of the MOU. Broadly, under the MOU, the parties herein were required to

organize India Bike Week Event (in short 'ÍBW Event'). This event, it

appears, has been conducted annually by the parties, as indicated above,

without a hitch in Goa from February, 2013 till February, 2016. The annual

event of 2016 was followed by a mini event which was also held in and

about 20/21st February, 2017.

1.1 As indicated above, the dispute between the parties erupted in

August, 2017 when, according to the petitioner, it became aware of the fact

that the respondent had filed an application with the Registrar of Trade

Marks for registering the trademark 'India Bike Week' (in short 'IBW'),

exclusively, in its own name. It is vis-à-vis this aspect of the matter qua

which parties had approached Courts even on an earlier occasion to assert

their rights in consonance with the terms of the MOU.

Backdrop

2. The background in which the instant action has been instituted in this

Court is, broadly, as follows:

OMP (I) (COMM) No.326/2018 Pg. 2 of 65 2.1 On 16.10.2012, the petitioner and the respondent entered into an

MOU. The IBW Event, as indicated above, was organized by the parties

each year between February, 2013 and February, 2016.

3. It appears that the petitioner was aggrieved by steps taken by the

respondent to have the IBW trademark registered solely in its own name.

4. This led to the petitioner issuing a termination notice dated

24.08.2017. By this notice the petitioner, inter-alia, asserted that the

breaches committed by the respondent had brought about immediate

cessation of the MOU. Since, the petitioner was of the view that, it was a

'non-defaulting" party, it called upon the respondent to sell its share in the

IBW trademark/Event for INR 1 million.

5. The respondent, on the other hand, fired its own missive vide e-mail

dated 24.08.2017. The respondent alleged that the petitioner was in breach

of the terms of the MOU. The respondent, thus, threatened the petitioner, in

effect, with termination of the MOU within a period of 15 days in the event

the alleged breaches were not rectified.

5.1 The petitioner issued an interim response to this communication of

the respondent and, inter alia, informed the respondent about cessation of

OMP (I) (COMM) No.326/2018 Pg. 3 of 65 the MOU. It appears that thereafter, in and about September, 2017, the

respondent, albeit, unilaterally, without consulting the petitioner announced

the dates for the 2017 IBW Event.

6. This action of the petitioner, as it appears, propelled the respondent

into issuing a formal termination notice dated 09.09.2017. The termination

notice, clearly, indicated that the MOU would cease to have effect upon

expiry of the notice period of 15 days.

7. The petitioner, on the other hand, to ventilate its grievance and exists

its rights approached the Additional District Judge, Gurugram (in short

'ADJ') with a petition under Section 9 of the Arbitration and Conciliation

Act, 1996 (in short '1996 Act'). This petition was numbered as: Arb. Case

No. 54/2017.

8. Parallelly, the petitioner issued a response to the respondent's

termination notice. In this communication, the petitioner called upon the

respondent to cease and desist from exploiting the IBW trademark.

Furthermore, the petitioner also triggered the arbitration agreement

incorporated in clause XIII of the MOU and proposed appointment of a

sole Arbitrator.

OMP (I) (COMM) No.326/2018 Pg. 4 of 65

9. Even while the petitioner was awaiting the respondent's response to

its suggestion for appointment of an Arbitrator, the Additional District and

Sessions Judge rendered it is decision on the petitioner's application

preferred under Section 9 of the 1996 Act vide order dated 16.11.2017.

The learned ADJ dismissed the Section 9 petition filed by the petitioner,

inter alia, on the ground that it had failed to make out a prima facie case

and that the balance of convenience was also not in favour of the petitioner

apart from the fact that injuncting the 2017 IBW Event would cause

irreparable harm to the respondent. The learned ADJ, however, directed the

respondent to maintain accounts with respect to the Event that it proposed

to hold so that they could be produced before the Arbitrator at the time of

adjudication.

10 Being aggrieved, the petitioner carried the matter in appeal to the

Punjab and Haryana High Court. The appeal came up for hearing for the

first time on 22.11.2017, when, the learned Single Judge passed the

following order:

"It is contended that the effect of Clause 10 of the

Memorandum of Understanding (MOU) dated 16.10.2012 has

OMP (I) (COMM) No.326/2018 Pg. 5 of 65 been illegally ignored by the learned Additional District Judge,

Gurugram, while dismissing the application for temporary

injunction vide impugned order dated 16.11.2017. Learned

counsel for the respondent-caveator submits that in view of the

urgency of the matter, without going into the merits of the

contention, his clients are ready and willing to work out

workable modalities for the successful holding of the event,

subject to the ultimate' decision by the Arbitrator·.

In response, counsel for the appellant is not averse to such an

arrangement at this stage.

List on 24.11.2017 for further consideration.

Let the parties to file an affidavit detailing the modalities

thrashed out on the date fixed.

To be shown in the urgent list."

(emphasis is mine)

11 As directed, the matter was listed on the board of the learned Single

Judge on 24.11.2017. On the said date, counsel for the parties, placed for

OMP (I) (COMM) No.326/2018 Pg. 6 of 65 consideration of the Court a joint statement dated 23.11.2017. Furthermore,

counsel for the parties not only sought modification of the order dated

16.11.2017 passed by the learned ADJ but also sought a further direction

that the appeal be disposed of as having being rendered infructuous.

11.1 Accordingly, the learned Single Judge, keeping in mind the

submissions of the counsel and the joint statement placed before him,

modified the order dated 16.11.2017, passed by the ADJ, and disposed of

the appeal as having being rendered infructuous. Furthermore, the learned

Judge explicitly stated that the parties would be bound by the stand taken

before him.

12. Given this background, it would be necessary to cull out, verbatim,

the joint statement dated 23.11.2017 as extracted in the judgment of the

learned Single Judge as much has been said on behalf of the parties as to

the nature of interim arrangement they intended to put in place till the final

adjudication of their inter se disputes took place.

" · For ready reference the joint statement dated 23.11.2017 reads as under:-

" That NGC Network (India) Pvt. Ltd. & Orangefish Entertainment

OMP (I) (COMM) No.326/2018 Pg. 7 of 65 Pvt . Ltd. Jointly held the IPR as defined in Clause 1.3 of the MoU dated l6th October, 2012. Disputes have arisen with regard to the same and the same is subject matter of determination in Arbitmtion. Adequate notice or mention of this shall be made by Orangefish Entertainment Pvt. Ltd. on the website www. Indiabikeweek.in, Facebook Page, Twitter Page of 1ndia Bike Week as well as on the website of Orangefish Entertainment Pvt. Ltd. being www. Seventyemg.com. The disclaimer to the contrary posted by Orangefish Entertainment Pvt. Ltd. shall be removed/deleted from the above websites/facebook and twitter handle.

Orangefish Entertainment Pvt Ltd. shall maintain ledger account while trading as Seventy EMG for organizing the Event 'India Bike Week' on 24-25th November, 2017 and shall preserve the accounts which can be audited by NGC Network (India) Pvt Ltd. Orangefish Entertainment Pvt. Ltd. shall render its audited accounts with the Arbitrator for IBW 2017 on or before 25th December, 2017.

NGC Network (India) Pvt. Ltd., and Orangefish Entertainment Pvt. Ltd., post conduct of the IBW 2017 event on 24-25 November, 2017 shall not directly or indirectly organize India Bike Week event as defined in Clause 1.1 of the MoU or use the IPR as defined under Clause 1.3 of the MOU uptill the arbitration proceedings commence and for a period of one week thereafter, subject to a maximum of two months from today. Both the parties will be at liberty to move an appropriate application including an application under Section 17 of the Arbitration and Conciliation Act, 1996 before the Arbitrator for appropriate Orders.

The present statement would be without prejudice to rights of both the parties to raise all pleas in all forums including before the Arbitrator both at the interim stage as well as final hearing and the statement made would have no bearing in the said adjudication.

OMP (I) (COMM) No.326/2018 Pg. 8 of 65 Both the parties shall meet within one week from today to discuss and decide the name of the Arbitrator".

12.1 A perusal of the joint statement would show that the parties bought

temporary peace, inasmuch as while the respondent was allowed to go

ahead with the 2017 IBW Event a caveat was entered, which was, that it

would maintain and preserve accounts which could be audited by the

petitioner, enabling, in effect, the production of audited accounts before the

learned Arbitrator on or before 25.12.2017.

12.2 Furthermore, parties also bound themselves to desist from organizing

directly or indirectly an IBW Event after the 2017 IBW Event (as defined

in clause 1.1 of the MOU) or use the Intellectual Property Rights (in short

'IPR') [as defined in clause 1.3 of the MOU] until the commencement of

arbitration proceedings and for a period of one week thereafter subject to a

maximum period of two months from the date when the joint statement was

executed inter se the parties.

12.3 Inter alia, the parties also agreed, as evident on a plain reading of the

joint statement, to convene a meeting for the purposes of zeroing down on

the name of the Arbitrator.

OMP (I) (COMM) No.326/2018                                        Pg. 9 of 65
 13    It appears on 18.12.2017 the respondent conveyed to the petitioner

that it was agreeable that the disputes be referred to the Delhi International

Arbitration Centre (in short 'DIAC'). Evidently, this step was taken as

parties were unable to agree on their own as to who should act as the

Arbitrator for adjudication of disputes which had arisen between them.

14 While there is nothing on record to show as to what transpired

between 18.12.2017 and February, 2018 qua reference of the disputes to

the DIAC, the record does reveal that on 17.02.2018, the petitioner served a

cease and desist notice on the respondent.

14.1 This notice, as it appears, was, inter-alia, issued since the respondent

had put out in the public domain that it was going to hold an event, similar

to IBW Event, under the caption ''MOTOCAMP'' and for this purpose,

intended to use the IBW trademark.

14.2 In response thereto, the respondent issued a communication dated

28.02.2018 via its counsel. The stand taken by the respondent was that, it

was free to hold the event qua which grievance has been raised by the

petitioner as the order of the learned ADJ dated 16.11.2017, which had

OMP (I) (COMM) No.326/2018 Pg. 10 of 65 merged in the judgment dated 24.11.2017, passed by the learned Single

Judge of the Punjab and Haryana High Court, had worked itself out.

15. It appears that notwithstanding the stand taken by the parties in their

respective communications, the stand taken by them in the joint statement

before the Punjab and Haryana High Court weighed heavily on them and

consequently, parties entered into a fresh Arbitration Agreement dated

21.03.2018 (hereafter referred to as '2018 Arbitration Agreement‟). By

virtue of the 2018 Arbitration Agreement, the parties agreed that the

disputes which had arisen between them would be adjudicated upon by the

Arbitrator, albeit, under the aegis of the DIAC. This agreement was in line

with the discussion that the parties had in December, 2017, immediately,

after the disposal of the petitioner's appeal by the Punjab and Haryana High

Court.

16. As a result of this development, the petitioner, on 06.04.2018,

tendered a request to the Coordinator, DIAC, to initiate the process of

appointment of an Arbitrator. The petitioner also undertook to file its

Statement of Claim (in short 'SOC') with the DIAC in consonance with the

OMP (I) (COMM) No.326/2018 Pg. 11 of 65 DIAC Rules within a period of 15 days of its request or within such time

frame as may be specified by the Coordinator in that behalf.

17. The record shows that the DIAC invited the petitioner to file its SOC

vide communication dated 20.04.2018. Notably, a copy of this

communication was dispatched to the respondent.

18 As directed on 21.04.2018, the petitioner filed its SOC. The

petitioner followed it up by writing to the DIAC, on 27.04.2018, proposing

five names of former Supreme Court Judges for appointment of a sole

Arbitrator qua its disputes with the respondent.

19 Evidently, the DIAC, upon scrutiny of the SOC came to the

conclusion that the petitioner had failed to quantify its claims (a) to (d) in

monetary terms. This fact was communicated to the petitioner vide letter

dated 12.06.2018.

19.1 It appears that DIAC had brought this aspect to the notice of the

petitioner as quantification of claims in monetary terms would have

facilitated the fixation of fee that would have to be paid to the Arbitrator.

Importantly, by this very communication, the DIAC conveyed to the

OMP (I) (COMM) No.326/2018 Pg. 12 of 65 petitioner that it should choose an Arbitrator from a panel maintained by it.

For this purpose, the petitioner was requested to visit its website.

20 Upon the respondent receiving copy of the DIAC's communication

dated 20.04.2018, it advised its Advocate to respond to the said

communication. Accordingly, on 16.05.2018, the respondent's Advocate

wrote to the DIAC, making a grievance that the petitioner had not served

upon it the copy of the request dated 06.04.2018 and the documents, if any,

which accompanied the request, which included the 2018 Arbitration

Agreement executed between the parties. Furthermore, it was sought to be

brought to the notice of the DIAC that fees of the Arbitrator was to be

shared by the parties as stipulated in clause 6 of the Arbitration Agreement

and not in equal measure as was indicated in DIAC's letter.

21 The petitioner, it appears, in the meanwhile, vide e-mail dated

19.06.2018, suggested a panel of five names for appointment of a sole

Arbitrator.

22 Since, the process of appointment of the Arbitrator, was consuming

far too much time, the petitioner vide a letter dated 21.06.2018 called upon

the Coordinator, DIAC to appoint an Emergency Arbitrator. This

OMP (I) (COMM) No.326/2018 Pg. 13 of 65 communication, inter-alia, enclosed an application for grant of urgent

relief by the Emergency Arbitrator as also an application under Section 17

of the 1996 Act along with an amendment application.

22.1 It appears that the petitioner had filed an application under Section

17 prior to the request made for appointment of an Emergency Arbitrator in

the hope that the process of appointment of an Arbitrator would get

concluded at the earliest and in anticipation thereof, had suggested names

of five former Supreme Court Judges for appointment of a sole Arbitrator.

23 On 27.06.2018 DIAC called upon the respondent to either agree on

one of the names out of five, suggested by the petitioner for appointment of

a sole Arbitrator or in the alternative convey five names of its choice from

the panel maintained by it.

23.1 It appears that the respondent had also written a letter of even date

i.e. 27.06.2018, to the DIAC. Though, this letter is not on record what is

available on record is a communication dated 03.07.2018 issued by DIAC

in response to the said letter issued by the respondent. A perusal of the

DIAC's response would show that certain concerns were raised by the

respondent with regard to the request made by the petitioner for

OMP (I) (COMM) No.326/2018 Pg. 14 of 65 appointment of the Arbitrator. These concerns were sought to be addressed

by the DIAC vide its letter dated 03.07.2018.

24 In the interregnum, the petitioner, once again, on 02.07.2018 wrote

to the DIAC to expedite the process of appointment of an Arbitrator.

25 The respondent, on the other hand, via its Advocate's communication

dated 07.07.2018, reiterated its concerns with respect to the triggering of

the arbitration process by the petitioner and in this behalf adverted to the

DIAC's Rules and the 2018 Arbitration Agreement. The respondent, while

calling upon the DIAC to furnish a copy of the request made by the

petitioner and the copies of the documents appended to the said request,

sought time to file a reply and its counter claim.

25.1 Interestingly, the communication ended with a without prejudice

assertion that the 2018 Arbitration Agreement enabling the DIAC to

appoint an Arbitrator had ceased to have effect and therefore, the DIAC

had no 'jurisdiction', 'authority' or 'dominion' over the instant matter. The

respondent, thus, made it a point to convey to the DIAC that any

proceedings that it intended to conduct would be ''void'' and "invalid".

OMP (I) (COMM) No.326/2018                                        Pg. 15 of 65
 26    This was followed by the respondent writing to the DIAC, on

13.07.2018, indicating its disapproval of the names suggested by the

petitioner and in turn, suggested its own set of names.

27 The petitioner, in order to expedite the process, on the very same

date via e-mail dated 13.07.2018, conveyed to the DIAC its consent to the

appointment of Hon'ble Mr. Justice K.S.P. Radhakrishnan, former Judge,

Supreme Court, as the sole Arbitrator from amongst the panel of names

suggested by the respondent.

28 Evidently, on 16.07.2018, the DIAC wrote to the learned Arbitrator

i.e. Hon'ble Mr. Justice K.S.P. Radhakrishnan, that the parties had agreed

to his appointment as the sole Arbitrator. Furthermore, by this very

communication, the DIAC called upon the Arbitrator to file its declaration

of acceptance and statement of independence as per Schedule IV of the

DIAC (Arbitration Proceedings) Rules. In addition thereto, the DIAC

indicated to the learned Arbitrator that the petitioner had already filed its

SOC along with an application under Section 17 of the 1996 Act. A copy

of this communication was dispatched to the Advocates of the petitioner

and the respondent.

OMP (I) (COMM) No.326/2018                                       Pg. 16 of 65
 29    The petitioner claims that the copy of the DIAC letter dated

16.07.2018, addressed to the learned Arbitrator, was received by it only on

24.07.2018.

30 The petitioner, after a gap of nearly a week, wrote to the

Coordinator, DIAC, that there had been no further movement in the

constitution of the Arbitral Tribunal and that there was urgency in the

matter on account of continued usage of the IBW trademark by the

respondent, causing detriment to its interest.

31 Evidently, while the matter regarding the consent of the learned

Arbitrator was hanging fire, on 07.08.2018, the respondent advertized on

the social media that tickets for the 2018 IBW Event would be available

from 15.08.2018. For this purpose, it encouraged the viewers to visit its

website WWW. INDIABIKEWEEK.IN.

32 Given this provocation, the petitioner moved this Court by way of

the instant petition. The petition came for hearing for the first time before

me, on 14.08.2018, when an ad interim order was passed against the

respondent injuncting it from selling tickets with the trademark "India Bike

OMP (I) (COMM) No.326/2018 Pg. 17 of 65 Week", "The Biker's Festival", "IBW2018" and "#Indiabikeweek" or any

other mark which was deceptively similar to the foregoing marks.

33 The respondent, it appears, carried the matter in appeal to the

Division Bench. The said appeal was numbered as: FAO(OS)(COMM)

No.187/2018. The appeal was disposed of by the Division Bench vide

order dated 21.08.2018. In short, the Division Bench after noticing that the

returnable date fixed before me was 06.09.2018 exhorted the parties to

have the instant petition heard and disposed of on merits.

34 The respondent, since then, has filed its reply to the petition.

Submissions of counsel

35 In support of the petitioner's case, arguments have been advanced by

Mr. Dayan Krishnan, Senior Advocate, instructed by Mr. Sahil Sethi, while

submissions on behalf of the respondent have been made by Mr.Suhail

Dutt, Senior Advocate instructed by Mr. R.S. Mittal.

36 The arguments advanced by Mr. Krishnan can, broadly, be

paraphrased as follows:

OMP (I) (COMM) No.326/2018 Pg. 18 of 65 36.1 The IPR which emanated from the MOU was a joint property of the

parties. The parties were required to share the benefit emanating from the

IPR in the ratio of 60:40. The petitioner, under the MOU, is thus, entitled

to 40% share in the said joint property. This aspect is provided for in

Clauses I (1.3) & (1.7), Clause IV (1) and Clause V(6) of the MOU.

36.2 Furthermore, in the event of breach by either party, the 'non-

defaulting' party under clause IX of the MOU is empowered to buy out the

shares of the defaulting party for a maximum value of INR 1 million.

36.3 In the instant case, since the respondent had breached the terms of

the MOU by filing the application for registration of the subject trademark

without prior written consent or approval of the petitioner, the petitioner

was left with no choice but to terminate the MOU vide notice dated

24.08.2017. Therefore, the respondent's notice to terminate dated

24.08.2017, followed by a termination notice dated 09.09.2017 can have no

effect as the MOU had already been terminated by the petitioner.

36.4 The respondent has repeatedly violated the terms and conditions of

the MOU. This aspect came to the fore in July/August, 2017 when the

respondent attempted to and was successful in holding the 2017 IBW Event

OMP (I) (COMM) No.326/2018 Pg. 19 of 65 to the detriment of the petitioner‟s interest. Though, the petitioner sought

to protect its rights, as conferred upon it under the MOU, it failed to stop

the respondent from holding the 2017 IBW Event as the respondent had

gone too far in having third parties invest in the Event.

36.5 Given these circumstances, the petitioner had agreed to the disposal

of its appeal in the Punjab and Haryana High Court, based on an

understanding that till the rights in the IBW trademark/Event are finally

adjudicated upon by an Arbitrator, no precipitate action would be taken by

either party which could affect the interest of the other party. The

respondent, however, has chosen to, once again, embark on a course which

is wholly detrimental to the petitioner‟s rights under the MOU by

proposing to hold the 2018 IBW Event on 30.11.2018-01.12.2018.

36.6 Since, the parties could not agree on the appointment of a sole

Arbitrator, it was decided to have the arbitration proceedings conducted

under the aegis of the DIAC. The fact that the respondent agreed to this

suggestion is evident upon a bare perusal of the e-mail dated 18.12.2017,

addressed by the respondent to the petitioner. The intention of the parties to

OMP (I) (COMM) No.326/2018 Pg. 20 of 65 have the DIAC involved in the arbitration process got morphed into a

formal agreement, that is, the 2018 Arbitration Agreement.

36.7 However, even while the process of appointment of an Arbitrator

was on, the respondent precipitated the matter by advertising the sale of

tickets for the 2018 IBW Event. This unwarranted act of the respondent

propelled the petitioner to approach this Court for grant of injunctive relief.

36.8 The petitioner was constrained to move the Court as despite having

filed an application under Section 17 of the 1996 Act, as far back as on

21.06.2018 and an application for appointment of an Emergency Arbitrator

on 21.06.2018 with the DIAC, there was no movement in the matter. Due

to the dilatory tactics adopted by the respondent and the failure of DIAC to

move with alacrity in appointing an Emergency Arbitrator, the petitioner‟s

remedy under Section 17 of the 1996 Act had been rendered inefficacious.

37 On the other hand, Mr. Suhail Dutt, vigorously pressed for dismissal

of the petition and/or vacation of the interim order dated 14.08.2018. In

support of his prayers, Mr. Dutt advanced the following arguments:

37.1 The petitioner having approached the District Court at Gurugram, in

the first instance, by way of a petition under Section 9 of the 1996 Act, this

OMP (I) (COMM) No.326/2018 Pg. 21 of 65 Court would have no jurisdiction in view of the provisions of Section 42 of

the very same Act.

37.2 The contention that the Courts in Gurugram would have the

exclusive jurisdiction in the matter was sought to be supported by Mr. Dutt

by relying upon clause 9 of the 2018 Arbitration Agreement. Mr. Dutt

submitted that if clause 9 of the 2018 Arbitration Agreement were to be

read with clause XIII (which contained the arbitration clause) of the MOU,

it would be clear that the said clause had only been modified and not

superseded. In other words, according to Mr. Dutt, the jurisdictional Court

for filing of such a petition remained the Courts at Gurugram.

37.3 The Learned counsel went on to contend that the 2018 Arbitration

Agreement only changed the venue of the arbitration to Delhi without

affecting the exclusive jurisdictional clause contained in the MOU. In

support of this contention, reliance was placed by Mr. Dutt on the judgment

of the Supreme Court in: M/s Emkay Global Financial Services Ltd Vs.

Girdhar Sondhi, 2018 (10) SCALE 15.

37.4 Besides this, according to the counsel, the 2018 Arbitration

Agreement had ceased to operate in terms of clause 7 as arbitration

OMP (I) (COMM) No.326/2018 Pg. 22 of 65 between parties had not commenced within 30 days. It was stated that

neither the arbitration notice was served, as envisaged under Section 21 of

the 1996 Act and nor was a request given in accordance with Rule 3 of the

DIAC Rules nor was the same served on the respondent within the

stipulated period; as a matter of fact, the request has not been served on the

respondent till date.

37.5 The joint statement made by the parties before the Punjab and

Haryana High Court barred both parties from holding either an IBW Event

and/or from making use of the IPR for a maximum period of two months,

which came to an end on 23.01.2018. Therefore, the ex parte order dated

14.08.2018 was obtained by the petitioner on a clear misrepresentation of

facts and hence, the same ought to be vacated.

37.6 The petitioner, on the principle analogous to the doctrine of res-

judicata, is barred from filing successive petitions under Section 9 of the

1996 Act for the very same relief. The proceedings initiated before the

District Court at Gurugram, which culminated with the disposal of the

appeal by the Punjab and Haryana High Court was not limited to the 2017

OMP (I) (COMM) No.326/2018 Pg. 23 of 65 IBW Event. The order of the learned ADJ was not set aside but was only

modified by the Punjab and Haryana High Court.

37.7 Since, the Arbitral Tribunal was already in place w.e.f. 23.07.2018,

by virtue of the provisions of Section 9 (3) of the 1996 Act, the present

petition ought to have been dismissed in limine. This fact was in the

knowledge of the petitioner, which was, however, dishonestly, not

conveyed to the Court while securing the ex-parte order.

37.8 Assuming, without admitting, that the petitioner was unaware of the

constitution of the Arbitral Tribunal, even then, the bar under Section 9 (3)

of the 1996 Act would apply. The present petition, not being maintainable,

ought to be dismissed and the interim order be vacated.

37.9 The termination of the MOU by the petitioner was malafide on

account of the following:

(i) Firstly, the petitioner was aware since, January, 2013, that the

respondent had filed a trademark application. In this behalf, reference was

made to the documents appended by the respondent at pages 53 to 55 of its

document file.

OMP (I) (COMM) No.326/2018                                       Pg. 24 of 65
 (ii)    Secondly, the MOU was terminated by the petitioner without

providing for a 15 days cure period as mandated in clause VIII (3) of the

MOU.

(iii) Thirdly, filing of the trademark application in the sole name of the

respondent was merely a procedural issue and, therefore, sudden

termination of the MOU by the petitioner on this ground alone without

prior discussion or notice to the respondent, was mala fide and contrary to

the terms of the MOU.

38 The respondent was forced to terminate the MOU after giving 15

days notice to cure the breaches, as the petitioner had failed to bring

sponsors, or to promote, or even publicize the IBW Event.

38.1 Therefore, the petitioner being the defaulting party, the respondent

became the absolute owner of the IPR on tendering the stipulated amount,

equivalent to, INR 1 million to the petitioner in terms of clause IX(b) of the

MOU. The petitioner‟s contention that the IPR could not be used without

its consent had no merit as the MOU, admittedly, now stands terminated

and the respondent has become its absolute owner in terms of clause IX (b)

of the MOU.

OMP (I) (COMM) No.326/2018 Pg. 25 of 65 38.2 The continuance of the ex-parte order passed by this Court is causing

hardship and prejudice to the respondent as the entire work connected with

organizing the 2018 IBW Event has reached a standstill. The dates of 2018

IBW Event were announced on 11.07.2018. The sale of the tickets was to

commence on 15.08.2018, in view of the size of the annual Event, which is

being organized in Goa. The Event is expected to be attended by over

7500 bikers, 100 clubs and 75 exhibitors who hail from India and abroad.

Given the scale, necessary arrangements have to be completed, on an

expedited basis. Since, numerous sponsors for the 2018 IBW Event are in

the process of signing agreement(s) with the respondent, any hindrance in

the form of an interim order would have them back out from their

commitment(s).

38.3 The necessary arrangements, which include, inter-alia, tying up with

media agencies and ticketing agencies etc. have already been put in place

including the venue where the Event is to be held. The petitioner was

aware, all along, that the respondent would be holding the 2018 IBW Event

at the end of the year and, therefore, had managed to impact its interest by

delaying the initiation of arbitration proceedings, including the triggering

of Section 9 proceedings. The petitioner is not interested in organizing the

OMP (I) (COMM) No.326/2018 Pg. 26 of 65 annual Event, an aspect which has been recorded by the ADJ in its order

dated 16.11.2017. The respondent is the sole and exclusive inventor and

organizer as also responsible for conceptualizing the IBW Event and,

therefore, has an exclusive and superior interest in the IPR as well as in

keeping intact the value and reputation of the Event.

38.4 It is in the petitioner‟s interest that the subject mark is used and, in

case the petitioner succeeds in the arbitration proceedings, it will be

entitled to the 40% of the revenue/profits, in terms of the MOU. There is no

merit in the petitioner‟s plea that the Event be injuncted. The respondent

will, as, in the previous year, render accounts to the learned Arbitrator qua

the 2018 IBW Event as and when it is called upon to do so by the learned

Arbitrator.

38.5 The fact that the petitioner was aware of the alleged misuse of the

IPR is evident from its cease and desist notice dated 17.02.2018. Since, the

respondent refuted the same and followed it up by reply dated 28.02.2018,

the petitioner ought to have approached the Court and taken recourse to an

appropriate remedy at the earliest. The respondent is willing to publish a

OMP (I) (COMM) No.326/2018 Pg. 27 of 65 suitable disclaimer in respect of the pending disputes on its website, tickets

etc. and also to keep accounts, as indicated above.

39. In rejoinder, Mr. Krishnan stressed the point that the petitioner was

unaware of the letter dated 16.07.2018 issued to the learned Arbitrator till

its receipt on 24.07.2018. The fact that the petitioner was keen in having

the arbitration process expedited was sought to be brought to fore by Mr.

Krishnan, once again, by adverting to its letter dated 31.07.2018 addressed

to the DIAC. The fine point that Mr. Krishnan sought to make, is that, via

letter dated 16.07.2018, the DIAC, had called upon the learned Arbitrator

to given his consent and make a declaration in terms of Schedule IV of the

DIAC Rules, and therefore, the Arbitral Tribunal would get constituted

only when the petitioner had notice of occurrence of such an eventuality.

39.1 Furthermore, Mr. Krishnan made it a point to lay stress on the fact

that the petitioner was unaware of the purported declaration dated

23.07.2018, said to have been issued by the learned Arbitrator on which

reliance was placed by the respondent to show that the Arbitral Tribunal

had been constituted. In any event, according to Mr. Krishnan, the

supposed declaration dated 23.07.2018, which had been placed on record,

OMP (I) (COMM) No.326/2018 Pg. 28 of 65 was an unsigned document which did not reflect that the learned Arbitrator

had accepted his appointment. Given this position, Mr. Krishnan contended

that the bar under Section 9 of the 1996 Act would not apply in this case.

39.2 As regards the contention raised on behalf of the respondent that this

Court had no jurisdiction in the matter, in view of the fact that the 2018

Arbitration Agreement only changed the venue of Arbitration from

Gurugram to Delhi, Mr. Krishnan submitted to the contrary. It was the

learned counsel‟s contention that the exclusive jurisdiction clause obtaining

in the MOU ceased to have an effect with the execution of the 2018

Arbitration Agreement as the parties intended to change both, the seat as

well the venue from Gurugram to Delhi. In support of his submission, that

this court had the jurisdiction, reliance was placed by the learned counsel

on the judgment of the Supreme Court in Bharat Aluminium Co. Vs.

Kaiser aluminium Technical Services Inc1, (2012) 9 SCC 552.

"... 96. Section 2(1)(e) of the Arbitration Act, 1996 reads as under: "2. Definitions.--(1) In this Part, unless the context otherwise requires--

(a)-(d)***

(e) „Court‟ means the Principal Civil Court of Original Jurisdiction in a district, and includes the High Court in exercise of its ordinary original civil jurisdiction, having jurisdiction to decide the questions forming the subject-matter of the arbitration if the same had been the subject-matter of a suit, but does not include any civil court of a grade inferior to such Principal Civil Court, or any Court of Small Causes;" We are of the opinion, the term "subject-matter of the arbitration" cannot be confused with "subject- matter of the suit". The term "subject-matter" in Section 2(1)(e) is confined to Part I. It has a reference and connection with the process of dispute resolution. Its purpose is to identify the courts having

OMP (I) (COMM) No.326/2018 Pg. 29 of 65 39.3 With regard to the other submission that the instant petition was

barred, in view of the provisions of Section 42 of the 1996 Act, learned

counsel submitted that the earlier petition under Section 9 was filed in

pursuance to the arbitration agreement which was incorporated in the MOU

whereas the subject petition is filed pursuant to the 2018 Arbitration

Agreement. It was contended that the two petitions pertained to different

arbitration agreements and different cause of action and hence Section 42

of the 1996 Act could not come in the way of the subject petition being

pursued by the petitioner in this Court.

39.4 As regards the argument of balance of convenience, put forth by the

respondent, Mr. Krishnan submitted that in view of flagrant breach of the

MOU by the respondent, the petitioner had exercised its option under

supervisory control over the arbitration proceedings. Hence, it refers to a court which would essentially be a court of the seat of the arbitration process. In our opinion, the provision in Section 2(1)(e) has to be construed keeping in view the provisions in Section 20 which give recognition to party autonomy. Accepting the narrow construction as projected by the learned counsel for the appellants would, in fact, render Section 20 nugatory. In our view, the legislature has intentionally given jurisdiction to two courts i.e. the court which would have jurisdiction where the cause of action is located and the courts where the arbitration takes place. This was necessary as on many occasions the agreement may provide for a seat of arbitration at a place which would be neutral to both the parties. Therefore, the courts where the arbitration takes place would be required to exercise supervisory control over the arbitral process. For example, if the arbitration is held in Delhi, where neither of the parties are from Delhi, (Delhi having been chosen as a neutral place as between a party from Mumbai and the other from Kolkata) and the tribunal sitting in Delhi passes an interim order under Section 17 of the Arbitration Act, 1996, the appeal against such an interim order under Section 37 must lie to the courts of Delhi being the courts having supervisory jurisdiction over the arbitration proceedings and the tribunal. This would be irrespective of the fact that the obligations to be performed under the contract were to be performed either at Mumbai or at Kolkata, and only arbitration is to take place in Delhi. In such circumstances, both the courts would have jurisdiction i.e. the court within whose jurisdiction the subject-matter of the suit is situated and the courts within the jurisdiction of which the dispute resolution i.e. arbitration is located. ...."

OMP (I) (COMM) No.326/2018 Pg. 30 of 65 Section IX(b) of the MOU and had, thus, become the sole owner of IBW

Event. In other words, at this juncture, according to Mr. Krishnan, the

respondent had no right in the IPR. Furthermore, learned counsel submitted

that the respondent chose, if at all, to invest the 2018 IBW Event, knowing

fully well that the IPR created under the MOU, if not the sole property,

was, in the very least, a joint property and that the respondent could not be

permitted to canvass argument of creation of third party and financial

difficulty, after having embarked on a similar course in 2017.

39.5 Mr. Krishnan, was at pains to point out that it cannot be that each

year the respondent would violate the petitioner‟s right and because it

claims to have invested funds and third party rights are involved, it would

force the hand of the Court to put in place an ad-interim arrangement till

the dispute is finally adjudicated upon by the Arbitrator.

39.6 In fact, Mr. Krishnan contended that since the learned Arbitrator has

fixed 18.09.2018 as the date of hearing, no prejudice would be caused to

the respondent, if the interim order is continued as the 2018 IBW Event is

scheduled to be held only on 30.11.2018-01.12.2018.

OMP (I) (COMM) No.326/2018 Pg. 31 of 65 39.7 In sum, the contention of Mr. Krishnan was that, if the respondent is

allowed to sell the tickets for the 2018 IBW Event till final adjudication of

disputes, indeterminable third party rights would get embedded, which

would further only complicate the matter. According to Mr. Krishnan,

balance of convenience lay with the petitioner and not the respondent.

Analysis and Reasons.

40 I have heard the arguments of learned counsel for the parties as also

carefully examined the record.

41 What emerges upon the perusal of the record and on consideration of

the submissions advanced by the counsel over which, there is largely no

dispute is as follows:

(i) That in and about October, 2012 an MOU was executed between the

parties concerning holding of an annual IBW Event and sharing of IPR

generated therefrom, in 60:40 ratio. Forty percent (40%) share going to the

petitioner.

OMP (I) (COMM) No.326/2018                                       Pg. 32 of 65
 (ii)    That the respondent had taken steps, albeit, unilaterally to seek

registration of IBW trademark/event by filing an application with the Trade

Mark Authority on 10.12.2012, albeit, in its own name.

(iii) That apparently, respondent, sent an e-mail dated 14.01.2013

through, its Finance Manager, one, Mr. Deepak Bhagne, to Mr. Manoj Jain,

said to be connected with the petitioner, informing him, inter alia, that

"membership fee amounting to INR 56,000 for trademark registration had

been paid".

(iv) That the respondent had issued a notice dated 24.08.2017 wherein,

inter alia, it informed the petitioner that if it failed to remedy the breaches

pointed out in the notice within a period of 15 days, then, it would have no

other alternative but to terminate the MOU and the Addendum.

Furthermore, it also indicated to the petitioner that if termination of the

MOU and the Addendum became effective, it would be entitled to acquire

petitioner's share/interest under the MOU by making the payment as

stipulated in clause IX of the MOU.

(v) That the petitioner issued a termination notice of its own of even date

i.e. 24.08.2017.

OMP (I) (COMM) No.326/2018 Pg. 33 of 65

(vi) That the respondent, after the 15 days notice period was over, served

a termination notice dated 09.09.2017, on the petitioner, since, according to

it, breaches pointed out had not been cured.

(vii) Given the aforesaid circumstance, petitioner had approached the

District Court at Gurugram to have the 2017 IBW Event injuncted. This

endeavour of the petitioner failed as the learned ADJ vide order dated

16.11.2017, dismissed the Section 9 petitioner, albeit, with a direction to

the respondent to maintain accounts for production before the Arbitrator.

(viii) That the matter was carried in appeal by the petitioner, to the Punjab

and Haryana High Court, which was disposed of vide judgment dated

24.11.2017, based on a joint statement of the parties dated 23.11.2017. The

interim arrangement put in place by the parties, pending final adjudication

of inter se disputes received the imprimatur of the Court.

(ix) In pursuance, of the interim arrangement, on 18.12.2017, the

respondent sent an e-mail to the petitioner, whereby it agreed in principle

that the disputes obtaining between them could be adjudicated under the

aegis of DIAC.

OMP (I) (COMM) No.326/2018 Pg. 34 of 65

(x) The Parties entered into a fresh arbitration agreement i.e. the 2018

Arbitration Agreement. Via this agreement, the parties agreed that the sole

Arbitrator would be appointed by the DIAC in accordance with its rules.

Parties further agreed that the sole Arbitrator which the DIAC would

appoint would be that former Judge of the Supreme Court who had not,

previously, acted as an Arbitrator for either party or their affiliates. Parties

also agreed that the venue of arbitration would be Delhi and, ordinarily, the

place where DIAC was located i.e. at the High Court of Delhi at New

Delhi. Clause 6 of the 2018 Arbitration Agreement also provided the

manner in which the burden of fee would have to be shared by the parties.

Clause 7 of the very same agreement provided that the said agreement

would remain valid and binding between the parties only if arbitration was

initiated within a period of 30 days of signing of the agreement.

Interestingly, clause 8 of the 2018 Arbitration Agreement laid emphasis on

the fact that the said agreement would be applicable only in respect of

arbitration conducted under the aegis of the DIAC and not before any other

forum/institution. Furthermore, clause 9 of the 2018 Arbitration Agreement

indicated that clause XIII of the MOU shall continue to apply and will be

OMP (I) (COMM) No.326/2018 Pg. 35 of 65 binding on the parties except insofar as it was modified by the said

agreement.

(xi) Consequent thereto, a request for constituting an Arbitral Tribunal

was made by the petitioner to the DIAC vide communication dated

06.04.2018. An acknowledgement was issued by the DIAC vide letter

dated 20.04.2018. By this communication, DIAC required the petitioner to

propose names of Arbitrator, albeit, from its own panel.

(xii) The petitioner filed its SOC with the DIAC on 21.04.2018. This was

followed by an e-mail dated 27.04.2018, whereby the petitioner provided a

panel of Arbitrators from which appointment could be made by the DIAC.

(xiii) On 16.05.2018, the respondent via its Advocates wrote to the DIAC

raising certain procedural objections.

(xiv) On 21.06.2018, the petitioner applied to DIAC for appointment of an

Emergency Arbitrator. The request was accompanied by an application for

interim relief.

(xv) On 02.07.2018, the petitioner, once again, wrote to the DIAC to

expedite the process of commencement of arbitration proceedings. This

OMP (I) (COMM) No.326/2018 Pg. 36 of 65 was followed by a letter dated 12.07.2018 wherein, once again, it was

brought to the notice of the DIAC that the respondent‟s actions taken vis-à-

vis the 2018 IBW Event were causing detriment to its interest.

(xvi) On 13.07.2018, the petitioner conveyed its consent to one of the five

names suggested by the respondent for being appointed as an Arbitrator via

its letter dated 12.07.2018 addressed to DIAC. Accordingly, the petitioner

in its letter gave consent to the appointment of Hon'ble Mr. Justice K.S.P.

Radhakrishnan, former Judge, Supreme Court as an Arbitrator in the

matter.

(xvii) The DIAC vide letter dated 16.07.2018, wrote to Hon'ble Mr. Justice

K.S.P. Radhakrishnan, former Judge, Supreme Court that parties had

agreed to his appointment as an Arbitrator. Furthermore, by this letter, the

DIAC also requested the learned Arbitrator to file a declaration of

acceptance and statement of independence as per Schedule IV of the DIAC

Rules.

(xviii) The petitioner, however, claims (and there is no proof to the

contrary) that it received DIAC's letter dated 16.07.2018 only on

24.07.2018.

OMP (I) (COMM) No.326/2018 Pg. 37 of 65 (xix) On 24.07.2018, the DIAC appears to have received the declaration

from the learned Arbitrator, which, apparently was signed by him on

23.07.2018. The petitioner claims that it had no knowledge of the

document dated 23.07.2018. The petitioner also claims that the document

dated 23.07.2018, on the face of it, does not bear the signature of DIAC

and, therefore, would not establish that the learned Arbitrator has, in fact,

given his consent.

(xx) On 31.07.2018, the petitioner, once again, addressed a letter to the

DIAC, wherein it expressed its concern that the matter had not moved

forward since the receipt of DIAC‟s letter dated 16.07.2018. This letter, in

fact, is relied upon by the petitioner to buttress its contention that it was

unaware of the fact that document dated 23.07.2018 had come into

existence.

(xxi) On 07.08.2018, the respondent proclaimed on the social media that

the tickets for 2018 IBW Event would be available from 15.08.2018 on its

website. This communiqué exhorted interested person to visit its website

WWW. INDIABIKEWEEK.IN.

(xxii) The instant petition was moved in Court on 14.08.2018.

OMP (I) (COMM) No.326/2018                                       Pg. 38 of 65
 ISSUES:

42      Given the aforesaid facts and circumstances, to my mind, the

following issues arise for consideration:

(i)     Whether the petitioner was aware of the constitution of the Arbitral

Tribunal? If so, what would be the consequences of such a fact having

come the knowledge of the petitioner?

(ii) Would the bar under Section 9 (3) of the 1996 Act apply, even if a

party is unaware of the constitution of the Arbitral Tribunal and seeks

interim relief from the Court by filing a petition under Section 9 of the

1996 Act?

(iii) Would this Court have jurisdiction to entertain the instant petition,

given the fact that under clause XIII of the MOU, exclusive jurisdiction

with regard to arbitration proceedings, including interim reliefs as available

under Section 9 of the 1996 Act, vested with Courts at Gurugram?

(iv) Is the instant petition not maintainable in view of the petitioner

having approached the District court at Gurugram in an earlier round in

view of the provisions of Section 42 of the 1996 Act?

(v) Was the ex-parte interim order dated 14.08.2018 obtained by the

petitioner by resorting to misrepresentation?

OMP (I) (COMM) No.326/2018 Pg. 39 of 65

(vi) Was the petitioner entitled to injunction as prayed for in the facts and

circumstances of the instant case?

Issue No. (i)

43 Insofar as this issue is concerned, in my view, the material placed

before me persuades me to come to the conclusion that the petitioner was

unaware of the fact that the declaration dated 23.07.2018 had been received

by the DIAC on 24.07.2018. The preponderance of probability propels me

to conclude that the petitioner had no knowledge that the learned Arbitrator

had given his consent in response to the DIAC‟s letter of 16.07.2018. The

communication dated 24.07.2018 sent by the petitioner to the DIAC,

wherein it indicated to DIAC that it had received DIAC‟s communication

dated 16.07.2018 only fortifies the conclusion that I have reached in this

behalf. The fact that the petitioner wrote to the DIAC on 31.07.2018

indicating therein that there has been no movement in the matter after the

DIAC‟s letter of 16.07.2018 would only further strengthen the probability

that the petitioner was unaware of the DIAC having received the

Arbitrator‟s declaration dated 23.07.2018. As a matter of fact, during the

course of arguments, Mr. Dutt had conceded that the document dated

23.07.2018 was generated by the respondent after carrying out an

OMP (I) (COMM) No.326/2018 Pg. 40 of 65 inspection of the file maintained by the DIAC. A bare perusal of the

document would show that it is not a copy of the original. I had called for

the original document from the DIAC. The original declaration bears the

signature of the learned Arbitrator, whereas the document put before the

Court simply bears the endorsement "Sd" instead of the signature of the

learned Arbitrator.

43.1 Therefore, as indicated above, this issue would have to be decided in

favour of the petitioner.

Issue No. (ii)

44 As regards the aforesaid issue, the argument advanced by Mr. Suhail

Dutt was that even if the petitioner was unaware of the factum of the

constitution of the Arbitral Tribunal, the bar under Section 9 (3) of the 1996

Act would apply and, hence, the petition was not maintainable. It would be

appropriate, at this juncture, to extract the relevant part of Section 9:

"9 Interim measures, etc. by Court.- (1) A party may, before or during arbitral proceedings or at any time after the making of the arbitral award but before it is enforced in accordance with section 36, apply to a court-

xxxxxxx

OMP (I) (COMM) No.326/2018 Pg. 41 of 65 (3) Once the arbitral tribunal has been constituted, the Court shall not entertain an application under sub-section (1), unless the Court finds that circumstances exist which may not render the remedy provided under section 17 efficacious."

44.1 A bare perusal of Sub-Section (3) of Section 9 would show that once

an Arbitral Tribunal has been constituted, the Court, ordinarily, would not

entertain an application for interim relief unless the Court comes to the

conclusion that circumstances obtain which have rendered the remedy

under Section 17 of the 1996 Act inefficacious.

44.2 Having said so, in this case, what is required to be noticed, is that, at

the point in time when the petition under Section 9 was instituted, the

petitioner verily believed that the Arbitral Tribunal was not constituted. An

explicit assertion to that effect, even according to the respondent, has been

made in the petition. The reason articulated in the petition for approaching

the Court was that the petitioner had failed to obtain interim relief despite

having made a request to the DIAC, as far back as on 21.06.2018.

44.3 Furthermore, what made matters worse from the point of view of the

petitioner was that despite having made a request for appointment of an

Emergency Arbitrator pending constitution of the Arbitral Tribunal vide

OMP (I) (COMM) No.326/2018 Pg. 42 of 65 communication dated 21.06.2018, there was no real alacrity shown in the

matter by the DIAC.

44.4 The DIAC, instead of dealing with the request for appointment of an

Emergency Arbitrator, processed, in the usual and ordinary course, the

petitioner's earlier request for constitution of the Arbitral Tribunal.

44.5 The petitioner being keen to hasten the process of the constitution of

the Arbitral Tribunal, immediately, upon receiving a copy of the

respondent‟s letter dated 12.07.2018, seeking consensus on one of the five

names suggested by it, agreed to one of the names via a return

communication dated 13.07.2018.

44.6 Despite the petitioner showing acute keenness in the constitution of

the Arbitral Tribunal, the same was not constituted with due expedition.

The petitioner being unaware of the fact that the DIAC had received the

Arbitrator's declaration of independence on 24.07.2018, had, in my view,

every reason to approach this Court for grant of ad-interim relief, as the

relief under Section 17 of the 1996 Act, though sought, was not

immediately made available to it. Delay and lack of knowledge about the

constitution of the Arbitral Tribunal, in my opinion, provided sufficient

ground to the petitioner to approach this Court via the instant petition.

OMP (I) (COMM) No.326/2018 Pg. 43 of 65 Therefore, in the instant case, in my view, the bar of Section 9 (3) of the

1996 Act would not apply, as was sought to be contended by Mr. Dutt.

44.7 I must also indicate at this juncture that at one point, it was

suggested by Mr. Krishnan that since, according to the respondent, the

Arbitral Tribunal had been constituted and the matter was posted before the

learned Arbitrator on 18.09.2018, this application could be placed before

the learned Arbitrator for appropriate orders. Mr. Dutt, however, did not

agree to the suggestion made by Mr. Krishnan and pressed for the dismissal

of the petition or in the very least, vacation of the interim order on the

grounds articulated by him.

44.8 Given the foregoing discussion, this issue would also have to be

decided in favour of the petitioner.

Issue No. (iii)

45 Insofar as the aforesaid issue is concerned, two important aspects

have to be borne in mind. First, the scope and ambit of Clause XIII of the

MOU. Second, as to how Clause XIII was impacted by the 2018

Arbitration Agreement. For the above said purpose, it would be necessary

to extract Clause XIII of the MOU and relevant clauses of the 2018

Arbitration Agreement i.e. Clauses 1, 3, 5, 8 & 9:

OMP (I) (COMM) No.326/2018                                     Pg. 44 of 65
       "A) MOU
      XIII. ARBlTRATION

If any dispute arises between the Parties hereto during the subsistence of this MoU or thereafter, the Parties shall try and resolve the dispute amicably failing which the dispute shall be referred to arbitrator appointed mutually by both parties as per the Arbitration and Conciliation Act.

l. The venue of the arbitration shall be Gurgaon (lndia).

2. The proceedings of arbitration shall be in the English language,

3. The Arbitrator's award shall be substantiated in writing. The costs of arbitration procedure shall be borne equally by the parties.

4. The Parties hereto shall submit to the Arbitrator's Award and the award shall be enforceable in any competent court of law.

Subject to the above provisions, the Courts having jurisdiction under the provisions of the Arbitration and Conciliation Act, 1996, to determine all matter which the Court is entitled to determine under the Act, including, without limitation provision of interim reliefs under the provisions of Section 9 of the Arbitration and Conciliation Act, 1996, shall exclusively be the courts at Gurgaon, India."

OMP (I) (COMM) No.326/2018                                         Pg. 45 of 65
       B)     2018 Arbitration Agreement

      1      The Parties agree to submit all disputes arising

from, connected with and/or in relation to the Agreement to arbitration in accordance with the Rules of the DAC. 3 The Parties agree that the venue of the arbitration proceedings shall be. at Delhi and ordinarily at the Delhi International Arbitration Centre located at the High Court of Delhi, New Delhi, India.

5 This Arbitration Agreement is executed only for purpose of the present intended arbitration. This Arbitration Agreement will have no application or effect on any future arbitration proceedings between the Parties.

8 It is clearly understood that this Arbitration Agreement shall be applicable only in respect of an arbitration conducted under the aegis of DAC in terms referred above and not before any other forum/institution.

9 The Parties agree that the Arbitration clause being clause XIII of the Agreement, except in so far as modified by this Arbitration Agreement, shall continue to apply and be binding on the parties."

45.1 A perusal of Clause XIII of the MOU would show that no seat of

arbitration was explicitly agreed to by the parties. However, in sub-clause

OMP (I) (COMM) No.326/2018 Pg. 46 of 65 (1) of Clause XIII, the venue of the arbitration, at the relevant point in time,

was indicated as Gurugram. Sub-clause (4) of Clause XIII also provided,

as would be apparent upon reading of the extract culled out above, that the

Award could be enforced in any competent Court of law.

45.2 Furthermore, the proviso to Clause XIII of the MOU states that

subject to the aforementioned provisions, the Courts at Gurugram would

have the exclusive jurisdiction including with regard to matters which came

within the ambit of Section 9 of the 1996 Act.

45.3 The argument advanced on behalf of the respondent is that in view of

the provisions of Clause 9 of the 2018 Arbitration Agreement, the

provisions made in the proviso to clause XIII of the MOU which conferred

exclusive jurisdiction on the Gurugram Courts remained unaffected despite

the execution of 2018 Arbitration Agreement. In order to appreciate this

contention, what one has to gather is the intention of the parties, given the

facts and circumstances obtaining in the present case. Clearly, no part of

cause of action, at any given point of time, arose in Gurugram. This fact

has to be kept in mind while taking cognisance of another fact, which is,

OMP (I) (COMM) No.326/2018 Pg. 47 of 65 that though the petitioner has its registered office at Gurugram, admittedly,

respondent's registered office is located in Mumbai.

45.4 In the MOU, the parties provided for Gurugram to be the venue and

conferred exclusive jurisdiction on Gurugram Courts subject to the other

provisions including the sub-clause (I) and (4) of Clause XIII of the MOU,

which, as indicated above, provided that the venue of arbitration would be

in Gurugram and the Award could be enforced in any competent Court of

law. Therefore, if the MOU had continued to operate and the 2018

Arbitration Agreement had not been executed by the parties then a petition

under Section 9 could lie, perhaps, only in the Courts in Gurugram. This

would be so, as the proviso to Clause XIII which conferred exclusive

jurisdiction on Gurugram Courts, was subject to the provisions preceding

the proviso.

45.5 However, with the execution of the 2018 Arbitration Agreement, the

parties consciously changed the venue to Delhi and went on to emphasizes

that arbitration would be held ordinarily where the DIAC sits, which is

within the precincts of this Court i.e. High Court of Delhi. Clause 8 of

2018 Arbitration Agreement lays stress on the fact that the said agreement

OMP (I) (COMM) No.326/2018 Pg. 48 of 65 would be applicable only in respect of an arbitration conducted under the

aegis of DIAC. There is no provision regarding jurisdiction of Courts, in

the 2018 Arbitration Agreement. Therefore, keeping in mind the

conspectus of the provisions incorporated in the MOU pertaining to

arbitration and those which obtain in the 2018 Arbitration Agreement

coupled with the fact that no part of cause of action arose in Gurugram, in

my opinion, the intention of the parties was to fix the seat of arbitration

where DIAC is located, which is, Delhi. The argument advanced on behalf

of the respondent that the provision in the MOU with regard Gurugram

Courts having exclusive jurisdiction survives despite execution of 2018

Arbitration Agreement, in my opinion, fails to take into account the fact

that the said provision was itself subject to what was stated in the preceding

clauses including the clause in the MOU which fixed the venue of the

arbitration at that point in time at Gurugram. Since, the venue was

changed, the conferment of exclusive jurisdiction, in the Courts located in

Guguram failed to have any efficacy for the parties. The parties, to my

mind, as indicated above, intended to fix Delhi as the seat of arbitration.

45.6 The decision in M/s Emkay Global Financial Services Ltd, to my

mind, is distinguishable as a perusal of paragraph 5 of the said judgment

OMP (I) (COMM) No.326/2018 Pg. 49 of 65 would show that under the National Stock Exchange bye laws, relevant

authorities prescribed Regulations for "creation of seats of arbitration for

different regions, or prescribing geographical locations for conducting

arbitrations and prescribing the Courts which will have the jurisdiction

for the purposes of the Act". In that case, the Arbitrator had held sittings

in Delhi and thereafter delivered the Award, presumably, at Delhi. A

Section 34 petition was filed in the District Court at Delhi, which was

rejected on the ground that the jurisdiction in relation to disputes arising

under the bye laws of National Stock Exchange was vested in the Civil

Courts at Mumbai. Pertinently, Chapter VII of clause (1)(a) of the National

Stock Exchange byelaws, inter alia, provided that any deal entered whether

through automated trading system or via any proposal for buying and

selling would be deemed to have been entered at the computerized

processing units at Mumbai and the place of execution of the contract as

between the trading members would be at Mumbai. The trading members

of the Exchange under the said bye laws were expressly directed to record

on their contract note that they had excluded the jurisdiction of all other

courts, save and except, that of Civil Courts in Mumbai in relation to any

dispute arising out or in connection or in relation to contract notes.

OMP (I) (COMM) No.326/2018 Pg. 50 of 65 45.7 Clearly, in Emkay's case the cause of action, which arose out of

contract notes or qua any deal entered though automated trading system

was agreed to be located in Mumbai. Therefore, the exclusive jurisdiction

clause in that case gave supervisory jurisdiction to Courts located in

Mumbai as against those in Delhi where the Arbitrator had only held

sittings. As indicated above, this judgment would not help the cause of the

respondent, especially in the circumstances that after the MOU, the 2018

Arbitration Agreement was executed between the parties which did not

confer exclusive jurisdiction on any Court much less Courts at Gurugram.

46 Therefore, this issue would also have to be answered in favour of the

petitioner and against the respondent.

Issue No. (iv)

47 In view of the foregoing discussion with regard to issue No. (i), I am

of the view that there can be no bar in the petitioner prosecuting the instant

action. The earlier arbitration agreement which obtained between the

parties and formed part of the MOU, was novated with the execution of the

2018 Arbitration Agreement. The instant action has been filed based on

the 2018 Arbitration Agreement and not on the basis of arbitration

OMP (I) (COMM) No.326/2018 Pg. 51 of 65 agreement which stood incorporated in Clause XIII of the MOU. The

earlier petition under Section 9 was filed based on Clause XIII of the

MOU. The instant petition is, in fact the first petition under the 2018

Arbitration Agreement. Therefore, to my mind, the bar of Section 42

would not come in the way of the petitioner prosecuting the instant

petition.

47.1 Consequently, this issue is also decided in favour of the petitioner

and against the respondent.

Issue No. (v)

48 As regard the aforementioned issue, Mr. Dutt drew my attention to

the judgment dated 24.11.2017, passed by the learned Single Judge of the

Punjab and Haryana High Court. Based on what is stated in the said

judgement, Mr. Dutt emphasized the fact that the ex-parte order dated

14.08.2018 had been obtained by the petitioner by misrepresenting the

facts.

48.1 Pertinently, in the order dated 14.08.2018, I had recorded Mr.

Krishnan's submission that the sale of tickets for the subject Event i.e. 2018

OMP (I) (COMM) No.326/2018 Pg. 52 of 65 IBW Event, was contrary to the "understanding" arrived at between the

parties which was reflected in the order dated 24.11.2017.

48.2 Thereafter, in the very same order, I had extracted a part of the

judgment dated 24.11.2017, on which, Mr. Krishnan had placed reliance.

Mr. Dutt, based on the very same extract, argued that a perusal of the

extract would show that the parties had agreed that they will not, directly or

indirectly, organize an IBW Event or use the IPR, as adverted to in the

MOU, up until such time arbitration proceedings commence and for a

period of one week thereafter, subject to maximum of two months from

that date. It was, thus, Mr. Dutt's contention that since the stipulated

maximum period of two months had expired on 23.01.2018, the

understanding had dissolved and, hence, could not have formed the basis of

the ex parte order.

48.3 To my mind, this submission of Mr. Dutt loses sight of two

important aspects. Firstly, the contention made before me by Mr. Krishnan

was that there was an "understanding" between the parties that they would

not organize an IBW Event or use the IPR till the arbitration proceedings

commence and this understanding was sought to be disturbed by the

OMP (I) (COMM) No.326/2018 Pg. 53 of 65 respondent, even though, to the knowledge of the respondent steps had

been taken to have an Arbitrator appointed.

48.4 The documents filed with the petition including the e-mail dated

18.12.2017, addressed by the respondent to the petitioner, was clearly

indicative of the fact that the respondent, in principle, had agreed to

arbitration being conducted under the aegis of the DIAC.

48.5 Therefore, it was sought to be contended on that date (and this

continues to be the contention of the petitioner before me, even today) that

the respondent without waiting for the Arbitral Tribunal to be constituted

had embarked upon a course which disturbed the understanding arrived at

between the parties on 23.11.2017, which translated into the judgment of

Punjab and Haryana High Court dated 24.11.2017.

48.6 Given these facts and the foregoing discussion, I am of the

unequivocal view that there was no misrepresentation made by the

petitioner while seeking to press for an ex-parte injunction.

48.7 Accordingly, in my opinion, there is no merit even in this contention

advanced on behalf of the respondent. The same is, accordingly, rejected.

OMP (I) (COMM) No.326/2018 Pg. 54 of 65 48.8 This issue is also decided in favour of the petitioner and against the

respondent.

Issue No. (vi)

49 This issue pertains to merits of the petition, inasmuch as, whether or

not in the given facts and circumstances of the case, the petitioner should

be granted injunctive relief. For this purpose, one would have to examine

the relevant provisions of the MOU. The relevant provisions of the MOU,

to my mind, are Clause I (1.3), Clause IV (1) and Clause X (1). For the

sake of convenience, the aforementioned provisions of the MOU are

extracted hereafter:

"I DEFINITIONS AND INTERPRETATION In this MOU, (including the Recitals) unless the context clearly indicates and intention to the contrary, a word or and expression, which denotes a natural person shall include an artificial person (and vice versa) any one gender shall include the other genders, the singular shall includes the plural (and vice verse) and the following words and expressions shall bear the meanings assigned to them below (and cognate words and expressions shall bear corresponding meanings):

     xxxxxxxx



OMP (I) (COMM) No.326/2018                                      Pg. 55 of 65

1.3. "IPR" shall mean the trademarks India Bike Week, IBW (both as a word-mark as well as a logo/label mark if applicable), and copyright in all artistic and literary works created in relation to the Event, and shall include nil associated rights in the nature of intellectual property rights (for instance, goodwill, exploitation and modification rights). All IPR shall be jointly held in Sharing Ratio as tenants-in- common, and neither Party shall have the right to alienate its share or deal with the IPR in any manner without the written consent of the other Party. "

IV RESPONSIBILITIES

1. 70 EMG shall be solely responsible for filing and obtaining all IPR protections with all relevant authorities within the Territory, and also for defending the said IPR against any infringement, subject to written notice and agreement with NGC for each such filing and/or infringement defense and any expenses incurred for the same shall be entitled to be deducted as expenses from the Profit. It has been explicitly agreed between the Parties that the IPR shall remain the joint property of both Parties in the Sharing Ratio and that either Party will not represent anything to the contrary. Any breach of this clause shall lead to immediate cessation of this MoU and shall specifically prohibit either Party from conducting

OMP (I) (COMM) No.326/2018 Pg. 56 of 65 any business as is envisaged under this MoU or any business similar in nature and intent of this MoU.

X. NON-COMPETITION AND NON-SOLICITATION I . The Parties undertake that during the tenure of this MoU and for a period of twelve (12) months after the termination of this MoU neither Party nor any of its affiliates, associates, agents or representatives, shall directly or indirectly organize the Event or any event, which may be competitive with the Event.

(emphasis is mine) 49.1 A bare perusal of Clause I (1.3) would show that the IPR emanating

from the MOU i.e. trademark "India Bike Week", "IBW" both, Word-Mark

as well as logo/label mark and the copy right in all artistic work and literary

works created in relation to the Event, and all associated rights in the nature

of IPR, were to be jointly held by the parties as tenants-in-common.

Neither party, as per the said clause, could alienate its share or deal with

the IPR in any manner without the written consent of the other party.

49.2 As per Clause IV (1), the responsibility for filing and obtaining IPR

protection with the relevant authorities and defending the IPR against the

infringement, was the sole responsibility of the respondent subject to the

OMP (I) (COMM) No.326/2018 Pg. 57 of 65 petitioner being notified in writing about such filing or institution of

infringement action (s) etc. The expenses, if any, incurred in that behalf by

the respondent were to be deducted from the profits that would be earned

by the parties.

49.3 Clearly, Clause IV (1) provided that the IPR would remain the joint

property of the parties in the sharing ratio provided in the MOU and that

neither party would represent anything to the contrary. More importantly,

Clause IV (1) also provided that in case of breach of the provisions of the

said clause, there would be an immediate cessation of the MOU with both

parties being injuncted from conducting any business as envisaged under

the MOU or, any business similar in nature and/or intent.

49.4 Clause X (1) which is a non-compete clause provides that during the

tenure of the MOU and for a period of 12 months post its termination

neither party or any of its agents, affiliates, associates or representatives

shall, directly or indirectly, organize the IBW Event or any other Event

which may compete with the subject Event.

49.5 Clearly, a conjoint reading of the aforesaid clause establishes that the

IPR which emanated pursuant to the Events organized in the past, based on

OMP (I) (COMM) No.326/2018 Pg. 58 of 65 the understanding incorporated in the MOU, were to remain a joint

property of the parties. The prescribed ratio under the MOU was 60:40.

The 60% share being conferred upon the respondent and the balance 40%

on the petitioner. The MOU in no uncertain terms sets out that the parties,

insofar as the IPR were concerned, were tenants-in-common. This aspect is

reflected in Clause I (1.3) and Clause IV (1) of the MOU.

49.6 As a matter of fact, as adverted to above breach of the conditions of

clause IV (1) was designed to cause "immediate cessation" of the MOU.

The concomitant consequences of which were (and that is something which

is provided in Clause IV (1) itself) that both parties were prohibited from

conducting any business as was envisaged under the MOU.

49.7 The facts, as delineated above, would show that the respondent, in

fact, had made an application for registration with Trademark Authority,

albeit, in its sole name on 10.12.2012. This is a document which the

respondent has brought on record. The respondent, in terms of Clause IV

(1), could not have done so without the written consent of the petitioner.

The respondent was clearly in breach of its obligation. To get over this

impediment, it was sought to be argued on behalf of the respondent that the

OMP (I) (COMM) No.326/2018 Pg. 59 of 65 petitioner was aware of the registration. For this purpose, reliance was

placed by the respondent on the e-mail dated 14.01.2013. This document,

inter-alia, refers to payment of membership fee of INR 56,000 for

trademark registration. This document has also been brought on record by

the respondent. To my mind, the e-mail dated 23.01.2013 would not by

itself help the respondent in answering the charge made against it that it

could not have approached the Trademark Authority for registration of the

IPR depicting itself to be the sole proprietor without the explicit written

consent of the petitioner.

49.8 Knowledge about the payment of fees for filing the application, in

my opinion, is not the same thing as knowledge of the contents of the

application filed before the Trademark Authority by the respondent, with

respect to ownership of the IPR. There is no good reason why the petitioner

would give up its share in the IPR property without reasonable recompense.

No document has been filed by the respondent on record which would

show that for filing the application for registration of the trademark the

petitioner's written consent had been obtained.

OMP (I) (COMM) No.326/2018 Pg. 60 of 65 49.9 As indicated above, since the respondent was in breach with regard

to the fundamental term contained in the MOU, which is, that the IPR

would continue to remain the joint property of the parties, the MOU ceased

to have effect.

50 Resultantly, the respondent brought about a situation whereby it

could not have exploited the IPR. As a matter of fact, therefore, contrary to

the argument advanced by Mr. Dutt that the petitioner's termination notice

dated 24.08.2017 did not give an opportunity to cure the defect, in my

view, is an argument which is not sustainable. Clause VIII (3) of the MOU,

in my opinion, cannot whittle down the provisions of Clause IV (1) which

specifically provides that breach of the provisions contained in the said

clause would bring about the "immediate cessation" of the MOU.

Therefore, Clause VIII (3) of the MOU, in my view, would apply to

breaches other than those which fell within the ambit of Clause IV (1).

50.1 The other argument of Mr. Dutt that the respondent had invested

time and money in the 2018 IBW Event and, therefore, the injunction order

should be vacated and the respondent should be allowed to hold the Event

subject to the condition that it would maintain accounts, which would be

OMP (I) (COMM) No.326/2018 Pg. 61 of 65 produced before the Arbitrator cannot be accepted. The reason I say so is

that the respondent, as correctly argued by Mr. Krishnan, appears to present

the petitioner as well the Court with fait accompli for holding out that since

time and money has been invested, the annual Event should be allowed to

continue subject to the final adjudication of the disputes between the

parties. The 2017 IBW Event was allowed to be continued with the

understanding that the parties would have their disputes adjudicated before

the next annual event. Record shows that the respondent has not displayed

necessary alacrity in having the dispute adjudicated.

50.2 I am, therefore, not inclined to vacate the interim order on the ground

of balance of convenience. The petitioner, on the other hand, has been able

to demonstrate that it has a strong prima-facie case. The contention of the

petitioner that the IPR is a joint property and that it has a 40% share in the

same and with the breach, it has the right to claim full ownership has,

prima facie, a great amount of merit. The petitioner has also been able to

demonstrate, at this stage at least, that registration of IPR was sought to be

made by the respondent in its sole name, albeit, without the written consent

of the petitioner bringing about a breach of the fundamental term of the

MOU.

OMP (I) (COMM) No.326/2018 Pg. 62 of 65 50.3 Furthermore, in my view, the balance of convenience, if at all, is in

the favour of the petitioner since the petitioner cannot put in a situation

where its rights in the IPR get completely diluted with repeated infraction

of the understanding arrived at between the parties which stands

incorporated in the MOU. To my mind, if the respondent is allowed to

hold the Event this year as well on the terms that it will maintain accounts,

it would amount to rewarding a party which has embarked on a course that

is plainly in the teeth of the explicit provisions of the MOU.

50.4 Having regard to the aforesaid, this issue is also decided in favour of

the petitioner.

50.5 Before I conclude, there are two aspects which need to be addressed.

First, whether the petitioner delayed the institution of the present petition?

To my mind, the answer has to be in the negative. The reason being that

while it is true that the petitioner had issued a cease and desist notice in

February, 2018 for earlier breaches by the respondent, the immediate cause

of provocation was the uploading of information on the social media by the

respondent that the tickets for 2018 IBW Event would be available from

OMP (I) (COMM) No.326/2018 Pg. 63 of 65 15.08.2018. Therefore, in my view, the petitioner had approached the court

in time, contrary to what is suggested on behalf of the respondent.

50.6 As regards the argument that the 2018 Arbitration Agreement had

come to an end because the Arbitral Tribunal was not constituted within 30

days, to my mind, this is an argument which is thoroughly misconceived.

The petitioner had, as is evident from a narration of events set out above,

taken every possible step for appointment of an Arbitrator beginning with

placing its request with the DIAC qua the same on 06.04.2018, which was

a date that fell well before the expiry of 30 days from the date of execution

of the 2018 Arbitration Agreement.

Reliefs

51 Thus, having regard to the foregoing discussion, I am inclined to

grant interim reliefs to the petitioner in terms of prayer clause (a) & (b) as

set out in the instant petition, which would continue to obtain during the

pendency of the arbitration proceedings.

52 Needless to say, nothing stated by me hereinabove will come in the

way of the final adjudication of the disputes pending between the parties.

OMP (I) (COMM) No.326/2018                                        Pg. 64 of 65
 53    The petition is disposed of, accordingly, in the aforesaid terms.




                                              RAJIV SHAKDHER
                                                  (JUDGE)
SEPTEMBER 18, 2018
A




OMP (I) (COMM) No.326/2018                                       Pg. 65 of 65
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter