Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Union Of India (Sr. Divisional ... vs M/S Samrat Construction Co.
2018 Latest Caselaw 6450 Del

Citation : 2018 Latest Caselaw 6450 Del
Judgement Date : 25 October, 2018

Delhi High Court
Union Of India (Sr. Divisional ... vs M/S Samrat Construction Co. on 25 October, 2018
$~1
*        IN THE HIGH COURT OF DELHI AT NEW DELHI
                                          Date of decision: 25th October, 2018
+                           O.M.P. 668/2007
         UNION OF INDIA (SR. DIVISIONAL ENGINEER-V, DRM
         OFFICE)                                               ..... Petitioner
                            Through:    Mr. Anand, Proxy for Mr. S.R.
                                        Narayan, Advocate (M-9718447715).

                            versus

         M/S SAMRAT CONSTRUCTION CO.                         ..... Respondent
                      Through: None.
                      AND

         CORAM:
         JUSTICE PRATHIBA M. SINGH
Prathiba M. Singh, J. (Oral)

1. The proxy counsel for the Petitioner seeks an adjournment. It is noticed that even on the last date, none appeared for the Petitioner and Court notice was issued. There is no reason for adjournment in the matter. None appears even for the Respondent.

2. The brief background is that the present petition has been filed under Section 34 of the Arbitration and Conciliation Act, 1996 challenging the award dated 14th June, 2007. Vide the said award, the Respondent/Claimant has been awarded a sum of Rs.7,48,966/- towards the various claims made by it.

3. The brief background is that the Claimant was awarded a contract for provision of fencing in connection with high speed high speed in the section

of Assistant Divisional Engineer/Tughlakabad (Junction cabin Palwal) Section from Km. 1515 to 1511 (Zone-I). The work was awarded on 2nd April, 2004 and was to be completed within a period of three months i.e. by 1st July, 2004. The date of completion was extended up to 15th January, 2005 with a penalty of Rs.2,000/- per week. The contract was finally rescinded on 28th April, 2005.

4. The initial value of the contract was Rs.76,65,500/- which was thereafter increased to Rs.95,04,912/- and approved on 19th October, 2004. A total payment of Rs.85,49,919/- was released to the Claimant.

5. It is not disputed that the work was completed and 12 running bills were paid by the Government. All the bills were duly certified by the Engineer-in-charge.

6. According to the Claimant, a sum of Rs.11,77,727/- was outstanding towards various heads of work executed by the Claimant. The Arbitral Tribunal has, under Claim 1, gone into detailed calculations of the amount of work which was actually executed and as against a sum of Rs.11,77,727/- which was claimed, Rs.4,78,107/- has been awarded. The admitted position on record is that the entire work was completed and no agency was engaged at the risk and cost of the Claimant to execute any balance work or defective/damaged work.

7. Insofar as Claims No.2, 3, 4, 5, 6 and 7 are concerned, the Arbitral Tribunal has passed a nil award.

8. Claim No.8 relates to refund of security deposit including the earnest money. The claim was for Rs.3 lakhs and the Arbitral Tribunal awarded a sum of Rs.2,70,859/- including the refund of the earnest money of Rs.50,000/-.

9. Claims No.9, 10 and 11 have been rejected.

10. The Government's Counter Claim No. A is related to excess payment received by the contractor in connivance with the field staff. According to the Government, the various measurements and defective work was not pointed out during the completion of the work. The persons who had issued the said certificates in terms of quality of work were the Government's own employees. Further, the Arbitrator also notes that no details in respect of alleged connivance have been proved on record. Accordingly, this Claim was rejected.

11. Counter Claim No. B relates to penalty which was also rejected.

12. The main objection raised by the Petitioner/Government in the objection petition is extremely factual. The grounds raised in the petition primarily relate to the fact that the contractor was given excess payment. The said ground having not been made out before the Tribunal and the remaining award having been decided on the basis of the work executed by the contractor, no interference is called for in the present petition.

13. Under these circumstances, the OMP is dismissed.

PRATHIBA M. SINGH JUDGE

OCTOBER 25, 2018 Rahul

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter