Citation : 2018 Latest Caselaw 6441 Del
Judgement Date : 25 October, 2018
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ O.M.P. (COMM) No. 443/2018
% 25th October, 2018
NATIONAL HIGHWAY AUTHORITY OF INDIA
..... Petitioner
Through: Mr. Manish Kumar Bishnoi,
Ms. Tanvi Sapra and Mr.
Sarthak Ahuja, Advocates
(Mobile No. 9811548007).
versus
M/S ORIENTAL STRUCTURAL ENGINEERS PVT. LTD.
..... Respondent
Through: Mr. Anil Airi, Sr. Advocate
with Mr. Ravi Chandna, Ms.
Bindiya Logawney and Ms.
Sukanya Lal, Advocates
(Mobile No. 9711752002).
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
To be referred to the Reporter or not?
VALMIKI J. MEHTA, J (ORAL)
I.A. No. 14634/2018 (for exemption)
1. Exemption allowed, subject to all just exceptions.
I.A. stands disposed of.
I.A. No. 14635/2018 (for delay)
2. For the reasons stated in the application the delay of 5 days in
re-filing the petition stands condoned, subject to all just exceptions.
I.A. stands disposed of.
O.M.P. (COMM) No. 443/2018
3. The present petition under Section 34 of the Arbitration
and Conciliation Act, 1996 (hereinafter 'the Act') is filed by the
petitioner/employer impugning the Award passed by the Arbitration
Tribunal (hereinafter 'AT') on 21.04.2018 by which the AT has
awarded Claim no. 2 to the respondent/contractor. Claim no. 2 of the
respondent/contractor was the claim made for the expenses incurred in
the period for which the Performance Bank Guarantees (hereinafter
'PBGs') and Retention Bank Guarantees (hereinafter 'RBGs') were
illegally directed to be continued by the petitioner/employer beyond
the requisite dates provided by the contract, and thus causing incurring
of expenses towards the continuation of the bank guarantees. The
PBGs or RBGs had to be returned, by a particular date of taking over
of the project by the petitioner/employer, so far as the RBGs are
concerned these were to be returned on completion of the Defect
Liability Period. The petitioner/employer also impugns the Additional
Award dated 07.06.2018 by which the AT under Section 33 of the Act
has amended the Award dated 21.04.2018 and has directed that the
charges payable by the respondent/contractor to the banks for
continuing the validity of these RBGs, will continue to be payable to
the respondent/contractor till the RBGs are returned by the
petitioner/employer to the respondent/contractor.
4. The facts of the case are that the petitioner/employer
awarded to the respondent/contractor a contract/project pertaining to
'Allahabad Bypass Project-Construction from Km 198 to Km 242.708
of NH-2 Construction: Contract Package ABP-3'. The date of issuing
of the letter of acceptance of the contract by the petitioner/employer
was 06.09.2004, with commencement date being 04.11.2004. The
time for completion of the contract originally was thirty months i.e. by
04.05.2007, with the actual date of completion being 15.10.2009.
Since the respondent/contractor had to remove certain defects in the
work, the handing over of the project to the petitioner/employer by the
respondent/contractor took place subsequently on 11.12.2009. The
Defect Liability Period was of 365 days and this period of 365 days
would commence from 11.12.2009 when the project was handed over
to the petitioner/employer. Disputes between the parties arose because
the respondent/contractor claimed that it had to incur unnecessary
charges for keeping alive the PBGs upto a date beyond the stipulated
date as provided in the contract. The respondent/contractor also had to
keep alive the RBGs till date, being well beyond the stipulated date as
provided in the contract.
5(i). As per Clause 10.2 of Conditions of Particular
Application, the PBGs were to be valid until a period of twenty eight
days from the date of issue of the Taking Over Certificate and that
these PBGs were to be returned to the respondent/contractor within
fourteen days after this aforesaid twenty eight day period. Since the
PBGs had to be returned within twenty eight days plus fourteen days
from 11.12.2009, the last date for returning the PBGs would be
22.01.2010. The PBGs were however returned by the
petitioner/employer to the respondent/contractor only subsequently on
08.05.2010. The respondent/contractor, therefore, claimed charges for
keeping the PBGs alive from 22.01.2010 to 08.05.2010.
5(ii). The second part of the claim of the respondent/contractor
was for the charges incurred for the period for keeping the RBGs alive
beyond the stipulated date as required under the contract. The
stipulated date for keeping the RBGs alive was a period of 365 days
after the completion of the project. This period of 365 days is
mentioned in Clause 49 of the General Conditions of Contract read
with Clause 49.1 of the Appendix to the Bid Documents. Since the
contract was completed on 11.12.2009, therefore the Defect Liability
Period came to an end on 11.12.2010. Since, the
petitioner's/employer's Engineer had during the Defect Liability
Period pointed out various defects in the project work undertaken by
the respondent/contractor for the petitioner/employer, such defective
works were rectified by the respondent/contractor even beyond
11.12.2010, and the defects were ultimately removed by 12.01.2012,
and on this date of 12.01.2012, the Engineer issued the unqualified
Defect Liability Certificate (hereinafter 'DLC') i.e. the Engineer
certified that no defects remained in the project/contract performed by
the respondent/contractor.
6. As per the contract, from every Interim Payment
Certificate, the petitioner/employer could retain certain amounts, but
these retained amounts could be received by the respondent/contractor
on furnishing bank guarantees for such amounts. The total defective
work, as pointed out by the engineer appointed by the parties, was of
the value of Rs. 6.50 crores whereas the RBGs which were available
to the petitioner/employer were of a larger amount of Rs. 12.63 crores.
The difference of the RBGs beyond Rs. 6.50 crores was hence
released by the petitioner/employer to the respondent/contractor, but
the balance amount of the bank guarantees of Rs. 6.50 crores were
retained by the petitioner/employer on the ground that there existed
defects in the works executed by the respondent/contractor and that
the respondent/contractor is liable to remove the defects in the work.
This retention was done although the Engineer designated by the
parties had issued an unconditional DLC that no defects remained
which were required to be rectified.
7. Therefore, it is seen that there were two disputes which
arose before the AT, and which are the subject matter of the present
petition under Section 34 of the Act as under:-
(i) Claim of the respondent/contractor for charges for
keeping the PBGs alive from 22.01.2010 till 8.05.2010, and
(ii) Keeping the RBGs alive till date and from the date
beyond the fourteen day period of issuing of the DLC dated
12.01.2012 by the Engineer appointed by the parties under the
contract.
8. It is not disputed before this Court that as per the
contractual provisions, the PBGs were to be released by the employer
on 22.01.2010, but were actually released only later on 08.05.2010.
Therefore, since the respondent/contractor has incurred charges to
keep the PBGs alive, beyond the date from 22.01.2010 and till
08.05.2010, the AT in my opinion has committed no illegality or
perversity or in any manner acted beyond the contract by holding that
the charges incurred by the respondent/contractor for keeping the
PBGs alive from 22.01.2010 to 08.05.2010 have to be awarded to the
respondent/contractor.
9. On the second dispute between the parties, it is seen that
it is an undisputed position in terms of the contract that the RBGs
were to be returned immediately after completion of the one year of
the Defect Liability Period. This is clearly provided in Sub Clause
62.1 of the General Conditions of Contract, and this clause makes it
further clear that this liability of the petitioner/employer to return the
RBGs is even independent of the Engineer failing to issue the DLC.
The DLC is dated 12.01.2012, and therefore within 14 days of this
date i.e. by 26.01.2012, the RBGs had to be released to the
respondent/contractor. Admittedly, the RBGs for the disputed
amounts have not been released till date, and consequently by the
impugned awards, the respondent/contractor has been rightly awarded
charges to keep these RBGs alive from 26.01.2012 till the RBGs are
returned by the petitioner/employer to the respondent/contractor.
10(i). Learned counsel for the petitioner/employer very
vehemently argued that the claim petition with respect to PBGs
charges was filed by the respondent/contractor in the year 2017,
although the cause of action had arisen to claim these PBGs charges
on 08.05.2010 when the PBGs were admittedly released back to the
respondent/contractor, and hence it is argued that the AT has
committed an illegality in awarding time barred claims.
10(ii). The learned senior counsel for the respondent/contractor
argues that no doubt the issue of limitation is an issue of law, however
an issue of limitation can always be waived by a person in whose
favour the right to plead the bar of limitation arises. It is argued on
behalf of the respondent/contractor that admittedly at no stage in the
arbitration proceedings, i.e. either in the pleadings of the
petitioner/employer, or during the course of evidence, or even during
the course of final arguments, the petitioner/employer ever urged
before the AT this ground of limitation, and the same is now urged for
the first time in this petition under Section 34 of the Act.
11. In my opinion, the argument urged on behalf of the
respondent/contractor is justified that the plea of limitation if not
raised, is deemed to be waived. In my opinion, an issue of limitation
cannot be raised for the first time in a petition under Section 34 of the
Act because a petition under Section 34 of the Act has to challenge the
Award on the ground that what the award decides is violative of the
provisions and ingredients of Section 34 of the Act. Once there is
nothing decided in the Award with respect to the issue of limitation, then
how can the petitioner/employer argue that Award is wrong on the
ground of awarding time barred claims. The Award has not decided this
issue of limitation as this issue was admittedly never raised by the
petitioner/employer in the arbitration proceedings. An issue before being
argued as wrongly decided, has to first be decided on raising of such a
defence, and once there is no decision on the issue of limitation, as it was
not raised by the petitioner/employer, then how can the
petitioner/employer urge that the issue of limitation is wrongly decided.
This argument of the petitioner/employer is wholly misconceived and is
therefore rejected.
12. In view of the aforesaid facts, I do not find that the
impugned Awards in any manner violate any provisions of law or the
contract between the parties, or that the Awards can be said to be in any
manner wholly perverse, for this Court to interfere under Section 34 of
the Act.
13. The petition is therefore dismissed.
OCTOBER 25, 2018/AK VALMIKI J. MEHTA, J
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!