Citation : 2018 Latest Caselaw 1525 Del
Judgement Date : 7 March, 2018
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 7th March, 2018
+ CS(OS) No.96/2018
SANJIT CHATTERJEE ..... Plaintiff
Through: Ms. Ginny J. Rautray, Ms.
Anushka Ashok, Advs.
Versus
ALOK K. BAGCHI ..... Defendant
Through: None.
CORAM:
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
IA 3181/2018 (for exemption)
1.
Allowed, subject to just exceptions.
2. The application is disposed of.
CS(OS) 96/2018 & IA 3180/2018 (u/O XXXIX R -1 & 2 CPC)
3. The plaintiff has instituted the present suit: A] for permanent injunction to restrain the defendant from (i) constructing a lift blocking the plaintiffs‟ balcony and compromising the privacy of the first floor of property No. J-1908, Chittaranjan Park, New Delhi; (ii) undertaking construction of additional floors thereby seeking to usurp the 33% right of the plaintiffs in the land underneath the property; (iii) constructing additional floors without ascertaining whether 44 year old building can bear additional construction; (iv) undertaking further construction until and unless copies of appropriate applications and requisite permissions obtained for the said construction are brought on record; and,
B] for mandatory injunction directing the defendant to remove the illegal construction already made.
4. Needless to state that the suit is accompanied with an application under Order XXXIX Rules 1 and 2 to stop all construction activity.
5. The case of the plaintiff is:
(i) that the defendant as the sole owner of the property No. J-1908, Chittaranjan Park, New Delhi, then comprising only of ground floor, on 3rd June, 1993 entered into a Collaboration Agreement with a Builder for constructing a full first floor and a second floor (ad- measuring 650 sq. ft.) and a drawing room (ad-measuring 450 sq. ft) on the ground floor and in which Agreement the defendant was described as the „first party‟ and the Builder as the „second party‟ and the relevant clauses of which Collaboration Agreement, insofar as relevant for the present purposes, are as under:-
"4. That the constructed area shall be divided by the owner and the builder in the following manner:-
(a) The party of the first part i.e. owner shall get the following constructed areas.
(i) Complete Ground Floor with 33% undivided and unspecified share in the land measuring 233 sq. yds. in case of natural calamities or otherwise which has already made having three bedrooms, drawing dining, one kitchen and two bedrooms (approx. 1250 sq. ft.).
(ii) Complete second floor i.e. 650 sq. ft. approx.
with 33% undivided and unspecified share in the land measuring 233 sq. yds. in case of natural calamities or otherwise.
(iii) Front lawn and back courtyard
(iv) Terrace on the top floor with full sole occupancy
and including construction/demolition/any additional floor(s) and when Govt. Bye-laws permit. The party of the part i.e. Owner will have rights to use/sell or dispose off the terrace in any manner, they so desire. However, builder will construct common utilities like water storage tank, plus servant toilet on top beneath the water storage tanks or at other place with the consent of the owner for common use.
(v) Common passage and staircase in driveway without any hindrance.
(b) The following constructed area along with the undivided share as per details below shall go to the party of the second part i.e. builder as their share.
(i) Complete first floor with 33% undivided share in the land measuring 233 sq.yds. in case of natural calamities.
(ii) One servant toilet in top floor for common use and using rights of second floor terrace for T.V Antenna, water tank etc.
(iii) Common passage and staircase without any hindrance.
(iv) One scooter parking area in the driveway.
(v) One servant room in between first or second floor i.e. in annexe portion of second floor without blocking sencity of building.
10. That second party can extend the first floor according to his choice and can extend first floor from shaft front elevation in back whatever technically possible as per MCD Bye-laws at his own cost, risk and responsibilities and first party has no objection in it. Second party will entirely be responsible for any legal proceedings penalty or other expenses or liabilities paid to MCD or any other Department."
(ii) that an Agreement to Sell dated 15th June, 1994 was executed by the Builder of the portion of the property which had fallen to the share of the Builder and to which agreement to sell, the defendant was a confirming party and in which Agreement, the Builder was called the „first party‟, the defendant as the „confirming party‟ and the purchaser as the „second party‟ and the relevant clauses of which agreement to sell for the present purposes are as under:-
"And whereas the Confirming Party entered into a Collaboration Agreement on 03/06/1993 with M/s Dabcons Engineering Pvt. Ltd. of S-363, Greater Kailash-I, New Delhi-110048 acting through its Director Shri R. S. Verma, (First Party in this Agreement) and got erected the Upper Floors of the said property.
And whereas the First Party became the owner and in possession of entire First Floor of said property, along with 33% undivided and indivisible share in the land measuring 233 sq. yds. beneath the said property, one Servant Quarter in Annexe portion of Second Floor (Between First Floor and Second Floor), duly fitted with water, sewer and electric connections, along with rights of usage of easements attached thereto ie. Rights of using Booster, Water Motor, common passages for approach, staircases, Parking one scooter in driveway, Servant toilet on Roof/Terrace of Second Floor, Fixing and Repair/inspection of TV Antenna, Common water tank on Rooftop etc. (hereinafter collectively referred to as demised portion of said property) by virtue of aforesaid Collaboration Agreement.
And Whereas the First Party has agreed to sell, transfer and convey the rights, interests, liens and titles in demised portion of said property;
9. That the confirming party will have the sold right on the front lawn, back courtyard and the terrace on the top floors with full sole occupancy and including construction or / demolition / any additional floor(s) as and when Government by law permits. The confirmatory party will have rights to use / sell or dispose off the terrace in any manner."
(iii) that the first floor of the property so sold by the Agreement to Sell dated 15th June, 1994 aforesaid, from time to time changed hands and was ultimately in the year 2009 purchased by the plaintiff and his wife;
(iv) the plaintiff along with his wife is, however, not residing in the said first floor of the property and is residing at D-687, Second Floor, Chittaranjan Park, New Delhi.
(v) the defendant, in January, 2018, was found carrying on the work of construction of a) an elevator in the rear open setback on the ground floor of the property; b) on open terrace on the second floor; and, c) a third floor above the second floor; after obtaining sanction from the concerned municipality.
6. The counsel for the plaintiff has argued that though the plaintiff has no objection to the defendant raising construction over the open terrace on the second floor but has filed the present suit to restrain the defendant from constructing the elevator and from constructing a third
floor above the second floor. It is argued that the plaintiff is the owner of 33% share in the land underneath the property and the construction by the defendant of the elevator and the third floor will affect the share of 33% of the plaintiff in the land underneath the property. Another ground given for objecting to the construction of the third floor, is that the existing construction is 44 years old and would be unable to take the load of the proposed third floor of the property.
7. On enquiry, as to how the plaintiff is counting the said 44 years, it is stated that the same are counted from the date of construction of the ground floor in 1974.
8. The plaintiff however forgets that thereafter in the year 1993- 94, under the Collaboration Agreement aforesaid, an additional drawing room on the ground floor, first floor of which the plaintiff now claims to be the owner and part of the second floor was constructed. It is not the case of the plaintiff that the load of construction of the first and second floors above the ground floor constructed in 1974 could not be taken by the ground floor constructed in the year 1974. If the said ground floor constructed in 1974, could in the year 1993-94 take the load of additional two floors and the said construction has withstood the test of time, it cannot be presumed that the construction as existing cannot take the load of additional third floor. Moreover, the construction on the open terrace on the second floor would also be a load and the plaintiff is not objecting thereto. The plaintiff has not made any averments with particulars of the existing construction being unable to take the load of the proposed third floor and the counsel for the plaintiff on asking whether the
plaintiff has got any technical study done in this regard states that the plaintiff is in the process of doing so. It is quite obvious that the claim for restraining construction of the proposed third floor is only on the ground of the same affecting the 33% share of the plaintiff in the land underneath the property.
9. The said unfounded apprehensions of the plaintiff, qua the load of proposed third floor are also found to be contrary to the title which the plaintiff purchased and holds. The genesis of the said title, according to the plaintiff also, is the Collaboration Agreement dated 3rd June, 1993 and the Agreement to Sell dated 15th June, 1994, the relevant clauses whereof are set out hereinabove. Under Clause 4(a)(iv) of the Collaboration Agreement, the portion belonging to the defendant was inter alia described as "Terrace on the top floor with full sole occupancy and including construction / demolition / any additional floor(s) and when Government Bye-laws permit". The defendant under the Collaboration Agreement thus had right to the terrace above the second floor and to construct thereon as and when government bye-laws permit. The government bye-laws now permit the construction of the third floor and construction plans of which have been sanctioned by the concerned municipality. Under the same Collaboration Agreement, the share of the Builder, of whom the plaintiff is the assignee, comprised only of first floor and other portions as described in Clause 4(b) supra and which do not include the terrace above the second floor. Under the said Collaboration Agreement, no right was vested in the Builder or its assignee to restrain construction more than that existing on that date.
10. Similarly, Clause 9 reproduced hereinabove of the Agreement to Sell dated 15th June, 1994 also clarified that the defendant had sole right on the"terrace on the top floor with full sole occupancy and including construction / demolition / any additional floor(s) as and when Government Bye-laws permit" and to use the same in any manner whatsoever.
11. The plaintiff having purchased title to the property and under which title the defendant has a right to raise construction above the second floor, cannot today be heard to say that the same will affect the 33% right of the plaintiff in the land or will endanger the first floor of the plaintiff. If the plaintiff entertained any apprehensions at the time of purchase in the year 2009 that any such construction by the defendant in future may endanger the first floor being purchased by the plaintiff, the plaintiff ought not to have made the purchase. The plaintiff having purchased with his eyes open, cannot claim any rights in addition to the title purchased by him and of which rights the plaintiff has not even paid any consideration.
12. As far as the argument of the counsel for the plaintiff, of the proposed construction of the third floor prejudicing or diminishing the 33% right of the plaintiff in the land underneath the property is concerned, Clauses 4(a)(i) and 4(b)(i) supra of the Collaboration Agreement dated 3rd June, 1993 specified / clarified that the specified share in the land is "unspecified" and only for the eventuality of "natural calamity" or "in case of natural calamities" i.e. if owing to a natural calamity the structure constructed on the land were to fall or be demolished. The said 33% share was not in the constructed area and
to not extend to all further constructions on the property including on the portion which under the aforesaid documents is in the exclusive share of the defendant and on which the documents also entitle the defendant to make construction.
13. The Collaboration Agreement dated 3rd June, 1993 and the Agreement to Sell dated 15th June, 1994 have to be read and interpreted harmoniously and any one clause thereof cannot be read so as to be in negation of another clause. The plaintiff‟s interpretation of the Agreements aforesaid renders otiose the clauses therein which permit the defendant to raise construction on the terrace above the second floor as when the building bye-laws permit. The plaintiff is thus not found entitled to restrain the defendant from raising construction of the proposed third floor of the property.
14. However, as far as the claim of the plaintiff for restraining the defendant from constructing the elevator is concerned, though the defendant is admittedly the exclusive owner of the rear setback in which the elevator is being constructed but the right of the defendant to raise construction therein is only till the level of ceiling of the ground floor and the elevator shaft being constructed, for accessing the second and third floors would also pass through the space above the rear open setback at the level of the first floor belonging to the plaintiff and in which space the plaintiff under Clause 10 reproduced hereinabove of the Collaboration Agreement dated 3 rd June, 1993 has a right to extend the first floor. Though the counsel for the plaintiff has not argued so but it is deemed appropriate to issue summons of the
suit and notice of the application limited to the said aspect, to the defendant.
15. The plaintiff having waited for over two months since January, 2018 to file this suit, is however not found entitled to any ex parte relief.
16. Issue summons of the suit and notice of the application to the
defendant by all modes including dasti and electronic, returnable on
16th March, 2018.
RAJIV SAHAI ENDLAW, J.
MARCH 07, 2018 SRwt/gsr
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!