Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Oriental Foundry Pvt Ltd. vs Union Of India And Ors.
2018 Latest Caselaw 923 Del

Citation : 2018 Latest Caselaw 923 Del
Judgement Date : 7 February, 2018

Delhi High Court
Oriental Foundry Pvt Ltd. vs Union Of India And Ors. on 7 February, 2018
$~
*    IN THE HIGH COURT OF DELHI AT NEW DELHI

                                    Date of Decision: 07.02.2018

+    W.P.(C) 76/2018 & CM APPL. 338-339/2018

     ORIENTAL FOUNDRY PVT LTD.            ..... Petitioner
                  Through: Mr. Manoj K Singh with
                  Ms. Tanuka De, Advocate

                          versus

     UNION OF INDIA AND ORS.                     ..... Respondents
                   Through: Mr. Deepak Jain, Sr. Panel
                   Counsel, Ministry of Railways with
                   Ms. Prabhleen Kaur, Mr. Tanpreet Singh and
                   Ms. Parul Jagota, Advocates

     CORAM:
     HON'BLE MR. JUSTICE S. RAVINDRA BHAT
     HON'BLE MR. JUSTICE A. K. CHAWLA

     S. RAVINDRA BHAT, J.(ORAL)
     *

1. The petitioner's grievance is that it had applied for/furnished its bid pursuant to a tender floated by the respondent-Railways (hereinafter referred to as 'Railways'), inviting bids for the manufacture of Railway wagons. The notice inviting tender (NIT) has started operation of the procurement to be sourced on 'developmental orders'. These lots were 500 wagons, two out of 500 wagons - totalling 1000.

2. The petitioner claims that its facility was inspected by the Research Designs and Standard Organisation (RDSO) and that in

accordance with its guidelines, it had applied for audit of its facility, that request was pending. The petitioner's bid under the 'developmental orders' category was opened along with the orders dated 6.9.2017. However, they complain that nothing was heard thereafter. It was never heard from the respondent-Railways. In the meanwhile, on 17.11.2017 to 30.11.2017, the RDSO sent a team for inspection of the petitioner's facility and ultimately, in respect of the tender in question and on 14.12.2017 issued a detailed report in this regard.

3. It complains that the subsequent information is based on arbitrary directions of the tender condition. Subsequently, it is stated that the petitioners were never formerly informed about the rejection of the bid.

4. The Railways in its counter affidavit states that the petitioner's bid - as well as that of 5,000 tenderers who had claimed bid for 5-6 other tenderers bids for 'development orders' were rejected for on account of non-fulfilment with essential legibility character.

5. It is contended that the petitioners undoubtedly had a registration with the RDSO G-105 (2011). However, their audit had not been completed on the date the bid was made.

6. It is submitted that in these circumstances, the bid could not have been accepted. It was urged that the same interpretation was

adopted in the case of other developmental bidders for the development orders.

7. Learned counsel for the petitioner urges that the rejection of the bid in the present case is arbitrary. He places reliance on Clause 10.0 and eligibility in respect of powers for development orders, (later portion of Clause 1), the relevant conditions are as follows :-

"Tenderers who have registered for G-105 (2011) approval with RDSO and whose first Audit has been completed successfully shall be eligible for developmental orders. In this regard, assessment of Railways shall be final. The quantity of a developmental order on an eligible wagon builder would normally be around 500 wagons subject to their rates being lower than that of L-1 tenderer eligible for regular order.

The total cumulative quantity against all developmental orders in two procurement cycles on any wagon builder would be restricted to maximum 1,000 wagons. However, such tenderers will not be considered for wagon allocation formula till they attain the status of a regular source."

8. It is argued that in the case of regular orders, a valid G-105 Certificate issued by the RDSO should be provided.

9. However, the bidder provided a letter from RDSO stating that the concerned is entitled for revalidation of certification. It is urged that the conditions with respect to bidders for 'developmental orders' was received for interpretation.

10. In other words, counsel urges that the requirement of possessing an audit approval has to be seen at the time of the award of the contract rather than at the time of bidding in case of those who opted for 'development orders' too like in the case of G-105 certificate for regular orders.

11. Counsel for the Railway however, contested this position and states that the tender classifies bidders into two Clauses i.e. regular bidders and those proposing to supply under the 'development orders'. The eligible conditions are clearly defined; in the case of those wishing under the development orders category, the requirement of possessing an audit, the RDSO audit report is essential.

12. The requirement in the case of regular bidders for regular orders is entirely different.

13. If the conditions with respect to regular orders (condition (i) of Clause 1 is contrasted with the condition with respect to 'development orders' (i) in respect of development orders), it is clear that the registration for G-105 approval with RDSO is essential for the latter category. The second condition i.e. the bidder should have opted a certificate and whose audit has been completed successfully shall be eligible for 'development orders', is categorical.

14. In the case of those applying for tender/contract under the regular category, a separate treatment is mandated and in that even

an expired certificate of G-105 (2011) is deemed sufficient as long as an application for validation or audit is made.

15. The rationale for these distinctions is apparent; it is that the those supplying under the regular order category are known and it is a matter which falls within the 'tried and tested category'. In the case of those applying under the development orders category, however, the nature of the facility might be known but the audit of all its machinery is not yet undertaken.

16. In these circumstances, the interpretation given by the Railways cannot be characterised as unreasonable giving the extremely circumscribed parameters under Article 226 of the Constitution.

For these reasons, the petition has to fail. Accordingly, the same is dismissed.

S. RAVINDRA BHAT, J

A. K. CHAWLA, J FEBRUARY 07, 2018/P

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter