Citation : 2018 Latest Caselaw 7232 Del
Judgement Date : 7 December, 2018
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ RFA No. 992/2018
% 7th December, 2018
M/S. SCOPIC INTERNATIONAL
..... Appellant
Through: Mr. Harsh Vardhan Sharma,
Advocate (M. No.9999897692).
versus
SURENDER RASTOGI
..... Respondent
Through:
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
To be referred to the Reporter or not?
VALMIKI J. MEHTA, J (ORAL)
C.M. No. 51417/2018(exemption)
1. Exemption allowed subject to just exceptions.
C.M. stands disposed of.
C.M. No. 51418/2018(for condonation of delay of 383 days)
2. Though there is no valid reason for condonation of delay
of 383 days in filing of the appeal, but since I have heard the counsel
for the appellant/defendant on merits of the appeal, therefore only for
this reason this application is allowed.
C.M. stands disposed of.
RFA No. 992/2018 and C.M. No. 51416/2018(stay)
3. This Regular First Appeal under Section 96 of the Code
of Civil Procedure, 1908(CPC) is filed by the defendant in the suit
impugning the Judgment of the trial court dated 11.08.2017 by which
the trial court has decreed the suit filed by the respondent/plaintiff for
a sum of Rs.3,52,097/- alongwith interest @ 12% per annum. The
amount which has been decreed is towards electrical work done by the
respondent/plaintiff for a project of the appellant/defendant.
4(i) The facts of the case are that a Letter of Intent dated
26.06.2006 was issued by the appellant/defendant to the
respondent/plaintiff for doing electrical works at site SV-40 and IP-IV
in Rajasthan, inasmuch as the appellant/defendant was awarded a
contract for doing work at various sites of M/s Kalaptaru Power
Transmission Limited in Rajasthan. The approved rate list formed part
of the Letter of Intent dated 26.06.2006. The respondent/plaintiff was
doing the work at site when on 10.11.2006 the contract was abruptly
cancelled. The appellant/defendant told the respondent/plaintiff to get
the measurement of the actual work done and get payment thereof.
Accordingly, respondent/plaintiff stopped the work and got the
measurements done and subsequently raised the following bills:-
S. No. Site Name Date Amount(Rs.)
1. SV-39 24.10.2006 83,412.50
2. SV-40 24.10.2006 38,603.00
3. IP-4 24.10.2006 57,553.50
4. IP-4(Ex. Work) 24.10.2006 80,162.50
5. IP-4 10.11.2006 12,713.00
Total Amount 2,72,444.50
4(ii) Under Clause 13 of the contract, the appellant/defendant
was entitled to 15% of the amount of the bills which was to be
released after three months of completion of work, and therefore, this
15% amounting to Rs. 79,651/- was also claimed by the
respondent/plaintiff. Thus the total amount of Rs. 3,52,097/- was
claimed by the respondent/plaintiff from the appellant/defendant.
5. The appellant/defendant contested the suit by filing the
written statement. The receipt of the bills was not denied. It was also
not denied by the appellant/defendant that the respondent/plaintiff did
the work. The defence of the appellant/defendant was that the bills
were highly inflated and were not in terms of the approved rate list. It
was also pleaded that the bills were not approved by the duly
authorized person at site, namely Mr. Vijay Tyagi.
6. After the pleadings were complete, the trial court framed
the following issues:-
"(i) Whether the plaintiff is entitled for a decree of recovery of Rs.4,50,847/- against the defendant? OPP.
(ii) Whether the plaintiff is entitled for interest, if so, at what rate and for which period? OPP.
(iii) Whether there is any cause of action to file the present suit against the defendant? OPD.
(iv) Relief."
7. The relevant issues were issue nos.1 and 2, and while
dealing with these issues, the trial court has crystallized the four
defences of the appellant/defendant as under:-
"(a) That alongwith the bills, the plaintiff had not filed proof of deposit of provident fund of its employees, as contemplated under clause 6.6 of the contract;
(b) That the plaintiff had not taken the approval from EIL (Engineers India Limited) before quoting the rates mentioned in the bills;
(c) That the measurement sheets and bills were not certified by the duly authorized official of the defendant, i.e Shri Vijay Tyagi;
(d) That the plaintiff instead of charging the agreed rates had submitted bills on the basis of highly inflated rates."
8. The trial court has held the first defence against the
appellant/defendant by noting that during the course of the suit, the
respondent/plaintiff had filed the necessary proof of deposit of
provident fund of its employees. As regards the second defence that
approval was not taken from Engineers India Limited (EIL), the trial
court has rightly rejected this defence by holding that there is no
requirement in the contract for bills of the respondent/plaintiff to be
approved by the EIL. So far as bills being submitted by the
respondent/plaintiff of not being in accordance with the approved rates
is concerned, the trial court has in para 22 of this impugned judgment
referred to the admissions made by the DW-1 in cross-examination
that the bill Ex.PW1/18 being a previous bill for which there is no
dispute was as per the settled rate and subject bills which were under
question in the suit are those where DW-1 could not tell as to which
bill was inflated. The trial court in para 11 of the impugned judgment
has observed that with respect to the work already done, for which the
bills were proved as Ex. PW- 1/30 to 1/39, were as per the approved
rates and contract, and were cleared by the appellant/defendant
without any demur, and therefore the trial court has held that it cannot
be validly argued by the appellant/defendant that the bills were raised
at inflated rates.
9. So far as the main defence of the appellant/defendant that
the bills Ex.PW-1/10 to Ex.PW-1/14 were not certified by the duly
authorized person, namely Mr. Vijay Tyagi, the trial court has referred
to the fact that the bills were duly received by the persons who are the
Site In-Charge of the appellant/defendant, and who have duly verified
the measurements in the bill and certified them for payment. The trial
court has also held that the contention of the appellant/defendant that
Mr. Vijay Tyagi was the only authorized person is not established
because nowhere in Ex.PW-1/6 it is stated that Mr. Vijay Tyagi was
the only authorized person. The relevant findings of the trial court in
this regard are contained in para 24 of the impugned judgment and this
para 24 reads as under:-
"24. Further, on the point that the disputed bills were not certified or measured by the authorized person namely Shri Vikas Tyagi, it is noted that:
(a) It is not mentioned in the agreement Ex.PW1/6 that it was only Vikas Tyagi who had to certify or measure the work mentioned in the bill;
(b) All the disputed bills were handed over to the officers of the defendant, i.e Shri Deepak Kumar, Shri Vijay, Mr. Mehra @ Mr. Mourya and Shri Vikas Tyagi, whosever was available at the site or office, the bills were handed over to him. It is absolutely wrong that Vikas Tyagi was the only person to receive the bills. As mentioned above, it is not mentioned in the contract or in any letter and the said fact was never notified to the plaintiff.
(c) That the defendant never produced their employees' register to show that Shri Deepak Kumar, Mr. Mehra @ Mr. Mourya were not the officers of defendant."
10. In my opinion, no fault whatsoever can be found with the
thorough and exhaustive reasoning and discussion given by the trial
court for decreeing the suit and which are contained in paras 14 to 26
of the impugned judgment. Since para 24 is already reproduced
above, paras 14 to 23, 25 and 26 are reproduced as under:-
"14. It is clearly evident that the defendant has not specified the articles/work done by the plaintiff for which he had filed inflated bill. The documents filed on record by plaintiff with regard to payment of provident fund to his employees by the plaintiff have been admitted by the defendant. The approval of EIL was nowhere required under the contract. The issue now remains with regard to the fact as to whether the bills Ex.PW1/10 to Ex.PW1/14 were certified by the duly authorized officer(s) of the defendant or not. In this regard, clause 13, 15 and 18 of the contract are relevant, which are reproduced as under: xxxxx
13. Payment Terms:
13.1 85% of approved unit rates on pro-rata basis against running bills shall be paid after certification by Engineer-In-Charge of SI/Kalpataru and against submission of certificate by contractor that all statutory payment/compliance in respect of labour wage payment, PF payments etc., till then have been met and nothing is outstanding. You can submit maximum two RA bills per month. The bills should be raised on 5th and 50th of every month.
13.2 10% payment shall be released against completion of entire job of erection, testing, commissioning work and balance 5% after 3 months from the date of completion handing over to SI/Kapataru. Balance 5% after three months from the date of completion and handing over.
xxxxx xxxxx
15. RA Bill and Final Bill:
15.1 Documents required with every RA Bill
15.1.1 RA bill - 3 copies
15.1.2 Joint measurement sheet - 3 copies
16.1.3 Proof of PF deposit
15.1.3 Approval of EIL
15.2 Documents required with final bill:
15.2.1 Final joint measurement sheet - 3 copies
15.2.2 Final reconciliation statement for all the materials (free
issue items) issued by SI/Kalpataru & EIL
15.2.3 Documents as a proof of fulfillments of statutory
requirement
15.2.4 Store clearance certificate from SI/Kalpataru
15.2.5 As built drawings -1 set
xxxxx
xxxxx
18. Inspection:
All the relevant IS, technical specifications and FQP shall be carried out by you in the presence of Engineer-In-Charge and 05 sets of inspection report to be submitted to SI/Kalpataru immediately. No extra charges shall be paid to you by SI/Kalpataru for arranging inspection at site.
xxxxx
15. Now, let us analyse the bills Ex.PW1/10 to Ex.PW1/14.
16. Ex.PW1/10 was submitted by the plaintiff on 10.11.2006 to the Incharge of the site namely Mr. Mehra @ Mr. Maurya, whose signatures appear on the Work Measurement Sheet as well as the invoice. The defendant has disowned said Mr. Mehra @ Mr. Maurya to be the authorized person to certify the work measurement sheets.
17. Ex.PW1/11 was submitted by the plaintiff on 24.10.2006, the same was received by the Site Incharge on 27.10.2006, whereupon the site supervisor asked one Shri Raghvinder to verify the measurements on 10.11.2006 and after verification of the measurement, the bill was submitted to Shri Vijay Tyagi on 21.11.2006.
18. Ex.PW1/12 was submitted by the plaintiff on 24.10.2006, the same was received by the Site Incharge, whereupon the site supervisor asked one Shri Raghvinder to verify the measurements on 10.11.2006 and after verification of the measurement, the bill was submitted to Shri Vijay Tyagi on 21.11.2006.
19. Ex.PW1/13 was submitted by the plaintiff on 24.10.2006, the same was received by the Site Incharge on 27.10.2006. Shri Mehra @ Maurya duly verified the measurement of work, as his signature appear on all the pages thereof.
20. Ex.PW1/14 was submitted by the plaintiff on 24.10.2006, the same was received by the Site Incharge on 27.10.2006. This bill was in respect of extra work done by the plaintiff.
21. Defendant has miserably failed in establishing as to in respect of which article mentioned in the aforesaid bills, the inflated rates have been quoted by the plaintiff. A comparison of the articles in the bills with the approved rate list does not justify the objection of the defendant. In his evidence, the DW-1 has disowned Mr. Mehra @ Mr. Maurya and Shri Deepak Kumar as authorized persons of defendant to certify the measurement of the work at the site. The defendant has,
however, not disowned the other two persons, one of whom is Shri Raghvinder, who was directed to verify the measurements. By merely denying the authority of aforesaid persons will not justify the stand of defendant.
22. The defendant has duly admitted that there was a contract Ex.PW1/6 between the parties. The approved rate list was also part of contract. Some of the articles with regard to which the approved rate list had not provision were mutually agreed vide subsequent letter Ex.PW1/8. In this regard, the relevant part of the cross-examination of DW-1 is as under:
xxxxx "(a) It is correct that agreed rates are at page 137 to 140."
xxxxx xxxxxx "(b) It is correct that Ex.PW1/18 are the rates settled."
xxxxx xxxx "(c) I have seen the bills and I cannot tell which one is inflated."
xxxxx xxxxx "(d) It is correct that on the basis of Ex.PW1/6, the bills were produced by the plaintiff and he had made part payment."
xxxxx xxxxx "(e) Admitted that all disputed bills were received by him.
xxxxx"
23. On the point of deposit of provident fund of the employees of plaintiff and approval of EIL (Engineers India Limited) of the work done, it is noted:
(a) That no cross-examination on the point of provident fund and EIL was made by the defendant of the plaintiff PW-1;
(b) EIL has nothing to do with the present contract nor EIL is a party in the present contract, ie. Ex.PW1/6;
(c) The defendant had never issued any notice or complaint to the plaintiff regarding deposit of provident fund or regarding the approval of EIL;
(d) In the previous bills which are Ex.PW1/30 to Ex.PW1/39 and which have been paid by the defendant to the plaintiff, no approval of EIL or any objection of provident fund was taken or raised by the defendant;
(e) The EIL has already made all the payments of the defendant and has never raised any objections to the defendant in this aspect. The defendant has admitted the said fact in his cross-examination.
(f) Even otherwise, the plaintiff has filed the receipt of provident fudn of his employees on the judicial file.
xxxxx
25. If we go to the admitted documents which are the payment certificate Ex.PW1/15 and Ex.PW1/16, it is absolutely clear that the defendant is liable to pay the retention amount of Rs.79,651/-.
26. On the point of inflated bills, the defendant no.1 in his cross- examination has stated:
xxxx "I have seen the bills but I cannot tell which one is inflated."
xxxxx"
(Underlining Added)
11. In view of the aforesaid discussion, it is seen that the
respondent/plaintiff did the work for the appellant/defendant, and also
raised bills which were proved as Ex.PW1/10 to Ex.PW1/14 and these
bills were duly verified by the officers of the appellant/defendant and
no evidence was led by the appellant/defendant that the persons who
verified the bills were not their employees or how they were not
justified in verifying the bills. The bills were not inflated because bills
were given at the same rates as per the earlier paid bills proved as
Ex.PW1/30 to Ex.PW1/39 and these bills were for the same work
order. Also, the EIL was never required as per the contract to certify
the bills. The respondent/plaintiff had filed documents to prove the
deposit of provident fund of its employees. The trial court was hence
completely justified in decreeing the suit for the bills Ex.PW1/10 to
Ex.PW1/14 alongwith interest thereon.
12. There is no merit in the appeal. Dismissed.
DECEMBER 07, 2018 VALMIKI J. MEHTA, J Ne
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!