Wednesday, 29, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Nhpc Limited (Formerly Known As ... vs M/S Continental Construction & ...
2018 Latest Caselaw 7194 Del

Citation : 2018 Latest Caselaw 7194 Del
Judgement Date : 6 December, 2018

Delhi High Court
Nhpc Limited (Formerly Known As ... vs M/S Continental Construction & ... on 6 December, 2018
$~49
*      IN THE HIGH COURT OF DELHI AT NEW DELHI
                                      Date of Decision: 6th December, 2018
+                               O.M.P. 141/2010
       NHPC LIMITED (FORMERLY KNOWN AS NATIONAL HYDRO
       ELECTRIC POWER CORPORATION LTD.             ..... Petitioner
                     Through: Mr. B. P. Singh and Dr. S. K. Khatri,
                              Advocate.
                     versus
       M/S CONTINENTAL CONSTRUCTION & ANR. ..... Respondents
                    Through: Mr. Satpal Singh, Advocate with Mr.
                              V. K. Sharma, Arbitration consultant.
                              (M:9810780218)
       CORAM:
       JUSTICE PRATHIBA M. SINGH
Prathiba M. Singh, J. (Oral)

I.A. 16198/2018 in OMP 141/2010

1. The application has been moved for replacing the special conditions of contract of which the wrong version was placed on record inadvertently. Fresh documents of special conditions of contract is taken on record.

2. I.A. is disposed of.

O.M.P. 141/2010

3. The present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter „the Act‟) has been preferred by the National Hydro-Electric Power Corporation (hereinafter „NHPC‟) against the impugned award dated 9th December, 2009 passed by the learned Sole Arbitrator. M/s. Continental Construction Limited - Respondent No.1 (hereinafter „Contractor‟) entered into a contract with the NHPC on 28th May, 1986 in respect of works for the "Construction of Tailrace Tunnel -

Civil Works" at Chamera HE Project (hereinafter, „project‟). The date of commencement was 1st April, 1986 and stipulated date of completion was 31st July, 1989, however, the actual work was completed on 22nd February, 1994. There is no dispute in respect of these dates. The original contract was awarded for a total value of Rs.13,95,24,220.00/-. Various extra works were also given to the Contractor. The final bill was submitted by the Contractor for a sum of Rs.53,75,21,440.04/-. The Contractor raised various claims including non-payment of the final bill. Since NHPC did not take any action, the petition under Section 11 (6) of the Act was moved in the Delhi High Court. The matter finally culminated in a Special Leave Petition before the Supreme Court, and vide the order dated 11th May, 1999, Shri Abdul Hamid Raina, the retired engineer of the NHPC was appointed as the Sole Arbitrator.

4. Before the learned Arbitrator, the following claims were raised by the Contractor:

S. Brief Description of Claims Amount Claimed No. (Rs.) 1 Payment due on BOQ items, 50,000.00 executed within (+/-) 30% variation of quantities 2 Payment due on variations in 68,88,420.88 quantities beyond (+) 30% of individual items and revision of rate of deviated item at par with other contracts at Chamera 3 Payment due on variation in 1,45,68,737.97 quantities beyond (-) 30% deviation on individual items 4 Payment due on revision of rates of 3,77,36,432.17 individual items executed beyond (+) 20% overall deviation of

contract sum 5 i) Payment on account of 16,90,805.00 withheld/balance amount due from the Respondent in respect of execution of extra items of work. 58,08,499.39

ii) Payment due for extra items of work done but not paid so far 6 Payment due on account of excess 1,52,14,096.70 and unaccepted recoveries 7 Payment due on account of actual 1,81,49,616.39 escalation 8 Payment due on account of unpaid 12,58,48,839.70 claims Total Rs. 22,57,35,448.00 9 Interest @ 24 per annum w.e.f. 18- 20,96,63,084.10 10-94 to 31-08-98 10 Interest @ 24 per annum w.e.f. 01- A matter of 09-98 to date of actual payment Calculation Grand total Rs. (Excluding Sr. No.10) 43,53,98,532.40

5. The total claims awarded by the Arbitrator are as under:

            S. No.   Description of Claims           Amount in Rs.
            1      Amount of Award in             1,54,40,606.67
                   favour of the Claimant
            2      Less recoveries awarded        25,44,717.99
                   against counter claims of
                   Respondent
            3      Net amount of Award in         1,28,95,888.68
                   favour of the Claimant
            4      Pre reference Interest         66,20,491.33
                   awarded @ 14% p.a.
                   w.e.f.     18.10.98       to
                   31.08.98
            5      Interest @ 12% p.a. from       1,74,09,449.72
                   1.9.98 to date of award i.e.
                   05.06.09
            6      Total amount of Award as       9,66,72,394.84

                       on 09.12.09, the date of
                      Award

6. Before this Court, the only objections raised by the NHPC are in respect of claim no.8.1 in respect to which Rs.1,10,20,000/- was awarded by the learned Arbitrator, as also the interest.

7. Claim no.8.1, which relates to claim for in-fructuous expenditure on supervision, overheads etc. together with pre-reference, pendente-lite and future interest on the final amount due to failure of NHPC to meet the contractual obligations as also change in the geographical conditions and other unforeseen circumstances, is set out herein below:

"

       Sl. Description of the Claim              Amount    Amount
       No.                                       Claimed (Rs.)
                                                           Awarded
                                                           (Rs.)

2. Claim No.8.1 for infructuous 98,705,430.00 11020000.00 expenditure on supervision, overheads etc. due to failure of Respondent to meet their contractual obligation "

8. Reasons for raising this claim is the huge overheads, which were claimed to have been incurred by the Contractor due to delays. The delays highlighted by the Contractor are -

a) Delay in handing over Land for Setting up Construction Facilities;

b) Delay on part of NHPC in handing over Site of Works to the Contractor;

c) Delay due to late supply of power;

d) Delay due to late supply of portal drawings to Adit;

e) Delay due to change in main channel drawings by the Respondent;

f) Delay due to change in alignment of Adit by the Respondent;

g) Delay in first full blast of the tunnel of Adit due to adverse geology met;

h) Delay due to unexpected geology at outlet site;

i) Delay due to defective ventilation system provided by the Respondent;

j) Delay due to change in supports specified in the contract drawings for all classes of tunnel supports on account of wrong identification of geology.

k) Delay due to slow progress of the project construction works with equipment supplied by the Respondents.

9. Reasons for claiming these overheads was in respect of continuing wages of staff, maintenance of camps, ventilation, dewatering, lighting, compressed air, running vehicles, telephone, telex, postage, financing expenses, etc. Learned Arbitrator after considering the submissions of the Contractor and submissions of the NHPC held that the period of 20 months out of delay of 30 months is the period for which the Contractor would be entitled for overhead and financing costs. Accordingly, the Ld. Arbitrator awarded a sum of Rs.1,10,20,000.00/-, as compensation for overheads. The split-up of the amount was calculated as below:

OVERHEADS

1. Date of commencement of main 01.04.1986 works (as per the agreement)

2. Stipulated date of completion 31.12.1988

3. Period for completion of works 33 months

4. Contract Value Rs.1395.24 lacs

5. Monthly turn over (1395.24/33) Rs.42.28 lacs

6. Time related cost per month (i.e. Rs.5.51 lacs overheads @ 15%) = 0.15 x 42.281/1.5

7. Actual date of completion 22.02.1994

8. Extended period for completion 61.6 months

9. Total Value of work done Rs.2732.75 lacs

10. Value of extra work done after the Rs.1336.45 lacs Contractual date of completion (9-

4)

11. Corresponding time for which time 31.6 months related cost already recovered from extra works = (10x¾)

12. Number of months of un-recovered 30 months overheads payable to the Contractor (8-11)

13. Compensation decided by the Rs.110.20 lacs Tribunal for 20 months (20x5.51)

10. The main objections raised by learned counsel for the NHPC is that the learned Arbitrator has failed to consider the bar against award of overheads, as contained in clauses 21.1 and 21.2 of the Special Conditions of the Contract. It is submitted that the entire award has been made by the learned Arbitrator without considering the fact that for all the additional work and escalation, which was granted, the Contractor was not entitled to anything in addition. The work undertaken by the Contractor was duly paid for and hence during the 30 months' period, no additional overheads ought to have been awarded. Further submission of learned counsel for the NHPC is that there was no evidence led before the learned Arbitrator to actually show and establish that no additional overhead expenses were incurred by the Contractor. Even basic material was not placed on record. Learned counsel for the NHPC relies upon the judgment of the Delhi High Court in

National Highways Authority of India v. Bumi Hiway (M) SDN BHD, in OMP 249/2013 decided on 25th March, 2015 (hereinafter, „Bumi Hiway‟).

11. The Contractor, on the other hand, submits that it had also filed a Section 34 petition being OMP 206/2010, as even though the Ld. Arbitrator held all delays were attributable to NHPC, and that the Contractor was entitled for compensation for delay in 30 months @25%, he awarded compensation for only 20 months @15% for overheads and profit to the Contractor. The Contractor states that no reasons were given by the Ld. Arbitrator for restricting the award to 20 months, despite giving a finding that the delays were attributable to NHPC. However, in response to the contentions raised by NHPC in the present petition, the Contractor submitted that clauses 5, 15, 18, 39, 46 of the General Conditions of Contract and Clauses 21.1 and 21.2 of the Special Conditions of Contract have no application to the claim. The Ld. Arbitrator had considered the rival submissions of the parties in detail, and come to a conclusion that all delays in respect of the project is attributable to NHPC, which finding has not been challenged. The only argument advanced by NHPC is application of clause 21.1 of the Special Conditions of Contract, which they failed to establish before the Arbitrator. Thus, NHPC failed to establish the reasons for interference in the impugned award. However, without prejudice to the above, the Contractor prayed for setting aside of the impugned award on the grounds as stated in OMP 206/2010.

12. The Court has heard the submissions of the parties in respect of this claim. First, it needs to be noticed that the Ld. Arbitrator has awarded an amount which is higher than the claimed amount. The contractor had claimed a sum of Rs. 98,705,430.00/- under this claim, whereas the Ld.

Arbitrator has awarded a sum of Rs.1,10,20,000/-. The Ld. Arbitrator ought to have considered as to whether the amount awarded in this claim is barred under special conditions of clause 21 of the Contract. Clause 21 of the Contract is set out herein below:

"21. FACILITIES BY CORPORATION 21.1 Where any facility/material or anything is agreed to be provided by Corporation to Contractor and if it is not provided or if there is any delay in providing the same, Contractor shall not be entitled to any claim or damage from or against Corporation. Contractor may, however, ask for a suitable extension of time which may be granted by Engineer-in-Charge, at his sole discretion as provided in clause 39 of the General Conditions of the Contract. 21.2 In the Contract, unless it is specifically provided that a particular facility, material or any other thing is to be provided by Corporation at its own cost, it is agreed by the parties that the same shall be provided by Contractor at its own cost."

13. A perusal of this clause shows that if there is any delay by the Corporation i.e. the NHPC in providing any facility, any material, or anything as agreed, the Contractor would not be entitled to any claim or damages against the Corporation. The clause provides that the Contractor is entitled to seek extension, which would be granted by the Engineer-in- Charge. Learned counsel for the Contractor argues that the interpretation, which resulted in the delay do not constitute a facility or material. A perusal of the reasons for delays, as enumerated by the learned Arbitrator, shows that firstly the delay was in respect of handing over of the land for putting up the construction facilities, as also delay in handing over of the site and secondly, due to change in portal location, delays in supply of equipment

and delay to change in supports of all classes of tunnel supports due to wrong identification of geology etc., All these would constitute facility provided by the NHPC. The Ld. Arbitrator, held NHPC solely responsible for the delay in the execution of the work, and gave the following finding:

"i) I have gone through the submissions made by the parties, orally as well as in writing and after careful study of the case, it is my considered opinion that during the stipulated contract period, due to various reasons, including adverse geological conditions encountered at sit and consequent increase in the number of steel supports, in major lengths of the tunnel, the claimant could not execute the work at required rate of progress which resulted in delay in the completion of the work. The reasons for delay were beyond the control of the claimant and solely due to Respondent‟s inability to fulfil his contractual commitments. The Project was delayed by a period of 6 months, which includes the rime required for the extra quantum of work.

ii) So far as overheads are concerned, it is an established fact that the delay in the completion of the work results in loss to the contractor, owing to off-site overheads which are independent of the actual site expenditure such as expenses on account of rent, taxes, insurance, bank guarantee charges, postage, telex, telephone, printing & stationery, travelling, conveyance charges, general office expenses etc., and also on sit overheads i.e., those elements of cost which are government by time, such as supervisory costs, costs of site colonies etc. .........

vi) The Claimant had submitted the claim for in- fructuous expenditure on supervision, overheads, profit, etc., including financing cost amount to Rs.9,87,05,430.00 in the SOC.

vii) As the Claimant was required to remain mobilized

and therefore, invested in overhead and financing costs beyond the Contractual period for no fault of his, the Tribunal decides to award the claim for overhead and financing costs be beyond the Contractual period for no fault of his, the Tribunal decides to award the claim for overhead and financing costs for a period of 20 months out of the delay of 30 months. The amount of compensation works out to Rs.110.20 lacs as per details given in Annexure - 8A."

14. This interpretation of the learned Arbitrator is clearly contrary to the plain reading of the petition itself, inasmuch as it is the admitted position that extension has been granted to the Contractor without levy of any liquidated charges or compensation, in terms of clause 21.1. The question is whether the Contractor can claim anything over and above the same under the claim of overhead expenditure. During the 30 months, which the learned Arbitrator holds to be the delayed period, there is no doubt that the work was being executed by the Contractor and for the said work, the payment has been made by the NHPC. When there is a clear bar under the contract, the learned Arbitrator could not have simply rejected this plea of NHPC by holding that the Contractor had to continue to be mobilized and had therefore invested in overhead and financing costs beyond the contractual period for no fault of his. Moreover, the manner in which the Ld. Arbitrator holds that the Contractor is entitled to damages for a period of 20 months instead of claimed 30 months, is whimsical. There is no basis for the said finding. Firstly, there was a bar in the contract from awarding such damages and secondly, even on merits there was no ground to award for 20 months and no evidence was also led in this regard to prove that the overheads had been actually incurred by the Contractor. The reasons cited by the

Contractor itself for the delays, resulting in the claim being raised, clearly show that they are covered by this clause 21.1.

15. Further the learned Arbitrator has also not considered any specific evidence, which has been led but simply applied 15% overhead component. In the absence of any material i.e. evidence in terms of payment of wages, actual office expenses incurred during this period etc., by applying the judgment of Bumi Hiway (supra), this Court is of the opinion that without proving actual damage or loss, the Contractor could not have claimed any amount under this head. Relevant portion of the said judgment is set out herein below:

"13. The principal question that arises therefore is whether in the absence of BHSB placing any material before the AT to prove any loss of profit or damages having been incurred, the AT was justified in proceeding to award BHSB any amount in respect of the said two claims.

14. The Court is conscious of the scope of the interference with an Award in terms of Section 34 of the Act. In Associate Builders v. Delhi Development Authority 215 (2014) DLT 204, after referring to the decision in ONGC Limited v. Western Geco International Limited 2014 (9) SCC 263 the Supreme Court held that where a finding is based on no evidence or the AT takes into account something irrelevant to the decision which it arrives at, such decision would necessarily be perverse. The AT was expected not to give an Award which was contrary to the settled legal position.

15. In McDermott International Inc. v. Burn Standard Co. Ltd. (supra), the Court specifically dealt with the method for computation of damages. The Court prefaced its discussion with the remarks that "In the assessment of damages, the Court must consider only

strict legal obligations, and not the expectations, however reasonable, of one contractor that the other will do something that he has assumed no legal obligation to do." The Court then explained each of the formulae commonly adopted. The Court noted the criticisms of the Hudson‟s formula observing that "it adopts the head office overhead percentage from the contract as the factor for calculating the costs and this may bear little or no relation to the actual head office costs of the contractor." The Emden formula which has received judicial support in a number of cases has the advantage of using the "contractor‟s actual head office and profit percentage rather than those contained in the contract." The Eichleay formula is used "where it is not possible to prove loss of opportunity and the claim is based on actual cost." The Court did not endorse any one particular formula since "it is an accepted position that different formulas can be applied in different circumstances and the question as to whether damages should be computed by taking recourse to one or the other formula, having regard to the facts and circumstances of a particular case, would eminently fall within the domain of the arbitrator." What is significant as far as the above discussion is concerned is that it is only concerned with the application of formulae and not whether the formulae would apply notwithstanding there is no proof of the contractor having suffered overhead charges or loss of profit.

16..........

17. The net result of the discussion is that nowhere in the decision in McDermott International Inc (supra) did the Supreme Court hold that even without producing any material to show loss of overheads or profit, the Arbitrator could apply one of the formulae to award the claims.

18. On the other hand, the Court finds that it has been repeatedly stressed in the decisions of the Court that

some basic material has to be placed on record by the contractor to demonstrate loss of profits. It is one thing to say that on account of the premature termination of a contract, losses would be suffered and such in such instances it will be possible to demonstrate loss of profit. However, that is not the case here. Extension of time was given by NHAI up to 30th September 2004 without levy of LD. As the AT itself noted, BHSB did earn profits but over an extended period of time. Secondly, as the AT itself noted, BHSB did not produce any material to show that it had suffered any overhead costs or loss of profit. Therefore, the question of the AT simply applying the formulae did not arise. The Award appears to have proceeded on guess work.

19....22.......

23. For the aforementioned reasons, the Court is unable to sustain the impugned Award of the Arbitrator as it has proceeded merely on surmises and conjectures in awarding BHSB's claim for overheads and loss of profits without there being any evidence whatsoever produced to even prima facie show that it had suffered overhead charges and incurred losses. This is not a case of inadequacy of evidence but there being no evidence whatsoever to justify the impugned Award. In such circumstances, merely applying formulae to the total cost of the project to calculate the compensation was impermissible in law. The award of the amount under Claim No.7 is therefore set aside. Consequently, the question of awarding any interest on the said amount also does not arise."

16. For the above reasons, the claim under 8.1 is not liable to be sustained and the same is, accordingly, set aside.

Objection in respect of the amount of interest awarded

17. The next objection is in respect of the interest, which has been awarded by the learned Arbitrator. The learned Arbitrator has considered

one year period as a grace period for the payment of final bill. Post the one year period, the learned Arbitrator has awarded 14% interest from 1st January, 1995 till 31st August, 1998 and interest @ 12% per annum from 1st September, 1998 till 9th December, 2009, which is the date of award.

18. The submission of learned counsel for the NHPC is that no interest is payable in respect of any delayed period in respect of payment of final bill in view of clause 49. Learned counsel also relies on the judgment of the this Court in Union of India v. Pradeep Vinod Construction Co., in OMP 296/2005 decided on 30th July, 2018.

19. On the other hand, learned counsel for the Contractor relies upon clause 48 of the Special conditions of Contract to argue that a maximum of six months is the period in which the withholding of the final bill amount can be done. Admittedly, the learned Arbitrator has granted interest after a period of one year from the raising of the final bill. This, according to the learned counsel for the Contactor, cannot be held to be barred under clause

49. Relevant clause 48 and 49 are extracted herein below:

"CLAUSE 48 : PAYMENT OF FINAL BILL:

The final bill shall be submitted by the contractor within one month of the date fixed for completion of the work or of the date the certificate of completion furnished by the Engineer-in-Charge. No further claim in this regard unless as specified herein under shall be entertained. Payment shall be made within three months if the amount of the contract plus that of the additional items is upto Rs.2 lakhs and in 6 months, if the same exceeds Rs. 2 lakhs of the submission of such bill. If there shall be any dispute about any item or items of the work then the undisputed item or items only shall be paid within the said period of three months or six months, as the case may be. The

contractor shall submit a list of the disputed items within thirty days from the disallowance thereof and if he fails to do so, his claim shall be deemed to have been fully waived and absolutely extinguished. CLAUSE 49: OVER PAYMENTS AND UNDER PAYMENTS:

49.1 Whenever any claim whatsoever for the payment of a sum of money to the Corporation arises out of or under this contract against the Contractor, the same may be deducted by the Corporation from any sum then due or which at any time thereafter may become due to the contractor under this contract and failing that under any other contract with the Corporation or from any other sum whatsoever due to the contractor from the Corporation or from his security deposit, or he shall pay the claim on demand.

49.2 The Corporation reserve the right to carry out post-payment audit and technical examination of the final bill including all supporting vouchers, abstracts, etc. The Corporation further reserves the right to enforce recovery of any overpayment when detected, notwithstanding the fact that the amount of the final bill may be included y one of the parties as an item of dispute before an arbitrator appointed under Clause 55 of this contract and notwithstanding the fact that the amount of the final bill figures in the arbitration award.

49.3 If as a result of such audit and technical examination any overpayment is discovered in respect of any work done by the Contractor or alleged to have been done by him under the contract, it shall be recovered by the Corporation from the Contractor by any or all of the methods prescribed above, and if any under-payment is discovered, the amount shall be duly paid to the contractor by the Corporation. 49.4 Provided that the aforesaid right of the Corporation to adjust overpayments against amounts due to the contractor under any other contract with the

Corporation shall not extend beyond the period of two years from the date of payment of the final bill or in case the final bill is a MINUS bill, from the date the amount payable by the Contractor under the MINUS final bill is communicated to the Contractor. 49.5 Any sum of money due and payable to the contractor (including the security deposit returnable to him) under the contract may be withheld or retained by way of lien by the Engineer-in-Charge or Corporation against any claim of the Corporation or such other person or persons in respect of payment of a sum of money arising out of or under any other contract made by the contractor with the Engineer-in-Charge or Corporation or with such other person or persons. 49.6 The sum of money so withheld or retained under this clause by the Engineer-in-Charge or Corporation will be kept withheld or retained as such by the Engineer-in-Charge or Corporation or till his claim arising out of in the same contract or any other contract is either mutually settled or determined by the arbitrator, if the contract is governed by the arbitration clause under the clause 55 or by the competent court hereinafter provided, as the case may be, and the contractor shall have no claim for interest or damages whatsoever on this account or any other ground in respect of any sum of money withheld or retained under this clause. "

20. A perusal of the above two clauses shows that under clause 48, if the final bill is less than Rs.2 lakhs, the amount would have to be paid within a period of three months and if the amount of the final bill exceeds Rs.2 lakhs, the Engineer-in-Charge has the discretion to pay within a period of six months. Under clause 49, the claim of interest is barred only when the money is withheld or retained by the Engineer-in-Charge of the Corporation. The said two clauses have to be read conjointly and it cannot be argued that

the interest is not payable in perpetuity if Engineer-in-Charge of the Corporation does not authorise the payment of the bill. Such an interpretation would be contrary to public policy. The admitted position is that a substantial amount was due to the Contractor under the final bill, which the learned Arbitrator has awarded. The computation of the outstanding amount under the final bill is not in dispute but the only issue being disputed is in respect of the interest component. A reading of clauses 48 & 49 distinguishes the present case from the judgment in the Pradeep Vinod Construction (supra). Learned counsel for the Contractor has placed reliance on H. P. Housing & Urban Devt. Auth. & Anr. v. Ranjit Singh Rana, AIR 2012 SC 1337 to submit that even in the said case, interest @ 18% was upheld by the Supreme Court. The award of interest is in accordance with law and is not barred under the contract.

21. Under these circumstances, it is held that the interest awarded by the learned Arbitrator of 14% and 12% per annum cannot be said to be unreasonable or perverse. Interest at 12% p.a. would be payable from the date of the award till date of this order. The payments be now made by NHPC of the awarded amounts, as per the present order, within 3 months. If payment is not made within 3 months, interest at the rate of 18% p.a. shall be payable on the total awarded amount.

22. The O.M.P is disposed of in the above terms.

PRATHIBA M. SINGH JUDGE DECEMBER 06, 2018/dk

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter