Citation : 2018 Latest Caselaw 7165 Del
Judgement Date : 5 December, 2018
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ RFA No. 818/2006
% 5th December, 2018
TRADE FAIR AUTHORITY OF HARYANA AND ORS.
..... Appellants
Through: Ms. Noopur Singhal, Advocate
for Mr. Anil Grover, Advocate
(M. No.9312765888).
versus
AJAY JAIN
..... Respondent
Through: Mr. Sunil Dutt, Advocate (M.
No.9811168148).
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
To be referred to the Reporter or not?
VALMIKI J. MEHTA, J (ORAL)
1. This Regular First Appeal under Section 96 of the Code
of Civil Procedure, 1908(CPC) is filed by defendants in the suit
impugning the Judgment of the trial court dated 08.09.2006 by which
the trial court has decreed three claims to the respondent/plaintiff as
under:-
1. Payment for scaffolding for year 1999 Rs. 47,500
2 Balance payment as per letter dated Rs. 1,21,600 05.01.2001 being 10% of security deducted
3 Earnest money deposited at the time of tender Rs. 30,000
2. At the outset I may note that counsel for the
respondent/plaintiff very fairly does not seek the amount of
Rs.47,500/- under claim no.1 and therefore impugned judgment and
decree will stand modified accordingly by reducing this amount of
Rs.47,500/- from the judgment and decree passed for a sum of
Rs.1,99,100/- alongwith interest @ 12% per annum.
3. The only aspect and issue to be addressed by this Court is
whether the respondent/plaintiff is guilty of delay in the work awarded
to the appellants/defendants under Award no.1017 dated 21.09.2000
pertaining to design of exterior and related work for the Haryana
Pavilion at I.I.T.F., Pragati Maidan, New Delhi. Admittedly the work
was to commence on 05.10.2000 and was to be completed by
05.11.2000. The issue is whether the respondent/plaintiff has
completed the work by 05.11.2000 or the work got delayed thereafter
and was completed after 05.11.2000.
4. The counsel for the appellants/defendants has argued that
the appellants/defendants were entitled to deduct the penalty for the
delayed work in terms of Clause 8 of the Award Letter dated
21.09.2000, and this para 8 reads as under:-
"8. In case the work is not completed within the time period up to 5.11.2000 the agency will be penalized at the rate of Rs.25,000/- per day upto 13.11.2000 and the work will be completed at his risk and cost."
5. No doubt there is a clause which entitles the
appellants/defendants to deduct the penalty for delayed work beyond
05.11.2000 and upto 13.11.2000 at the rate of Rs.25,000/- per day, but
the factual issue is that whether or not the respondent/plaintiff had
completed the work by 05.11.2000. In this regard, there can be no
doubt that the respondent/plaintiff completed the work by 05.11.2000
inasmuch as the respondent/plaintiff had written its Letter dated
06.11.2000 attaching therewith the final Running Bill/Ex.PW1/17
dated 04.11.2000, and the letter dated 06.11.2000 shows that the entire
work was complete except laying of the carpet on the floor and which
was agreed, that the same would be laid on 12.11.2000. The counsel
for the respondent/plaintiff is right in contending that the carpet was to
be laid within the next few days after 05.11.2000 because otherwise
the carpet would have been spoiled even before the trade fair would
have commenced on 14.11.2000. This letter dated 06.11.2000 reads
as under:-
" 6th Nov.
The Administrator
Trade Fair Authority of Haryana
Haryana Bhawan
Copernicus Marg
New Delhi-1
Ref:-Renovation of HARYANA PAVILLION IITF-2000 Sub:- Submission of Third Running Bill
Madam, With reference to ongoing renovation work of Haryana Pavilion IITF-2000 at Paragati Maidan, New Delhi, please find herewith enclosed our third running bill for payment.
We also wish to inform you that we have completed all the works expect laying of carpet on the floor, as it was agreed to lay this on 12th Nov.2000.
Thanking you,
Your's Sincerely, For Options Unlimited,
RAJEEV SEHGAL, DIRECTOR
Encal a.a."
6. There is no doubt that the appellants/defendants have not
in any manner disputed the contents of the Letter dated 06.11.2000
written by the respondent/plaintiff to the appellants/defendants, and
even if the work was not completed then surely the
appellants/defendants would have contradicted the contents of the
Letter dated 06.11.2000. I may note that with respect to the same
work order, there were various other disputes and these have been
decided by the impugned Judgment dated 08.09.2006. As per the
impugned judgment various letters which are Ex.PW1/D2 to
Ex.PW1/D5 and Ex.PW1/16were written by the appellants/defendants
to the respondent/plaintiff which were not found to be responded to by
the respondent/plaintiff, and thus the contents of those letters were
used against the respondent/plaintiff. Therefore by the very same
logic the appellants/defendants are deemed to have accepted the
contents of the Letter dated 06.11.2000 which is reproduced above.
Once the work was completed by 05.11.2000 and Running bill
alongwith the Letter dated 06.11.2000 is given by the
respondent/plaintiff to the appellants/defendants, it cannot be held that
the respondent/plaintiff was guilty of delay in work beyond
05.11.2000.
7. Ld. counsel for the appellants/defendants have sought to
place reliance upon the Letter dated 10.10.2000 / Ex.PW1/8 issued by
the appellants/defendants to the respondent/plaintiff on the aspect of
respondent/plaintiff being guilty of delay beyond 05.11.2000, but
surely this letter has no bearing on whether the work was completed
by 05.11.2000 as this letter is dated 10.10.2000 and was written just
about four days after the commencement of work. It's pertinent to note
there could have been some delay but the issue is not about any delay
for the period from 05.10.2000 to 10.10.2000 but of a delay and non-
completion beyond 05.11.2000. I therefore reject the argument urged
on behalf of the appellants/defendants by placing reliance upon the
Letter dated 10.10.2000/Ex.PW1/8.
8. Ld. counsel for the appellants/defendants then sought to
place reliance upon Ex.PW1/D12 to show that certain items of work as
per the contract were not done, however, it is noted that the
appellants/defendants have already reduced payment made to the
respondent/plaintiff for certain works not done, and therefore, such
works stand deducted from the said work order. The document
Ex.PW1/D12 is pursuant to a Report prepared by the officials of the
appellants/defendants dated 30.12.2000 pointing to both the delay and
the defective nature of work and the deduction was only made for the
defective nature of work.
9. Ld. counsel for the respondent/plaintiff is also justified in
placing reliance upon Letter dated 05.01.2001/Ex.PW1/18 written by
the appellants/defendants to the respondent/plaintiff, and the para 6 of
this letter states that a penalty of Rs.1.93 lakhs was imposed upon the
respondent/plaintiff both for delay and unsatisfactory completion of
work. Therefore if the appellants/defendants have once deducted an
amount of Rs.1.93 lakhs out of the total payment made to the
respondent/plaintiff as penalty towards unsatisfactory completion of
work and an assumed delay, the appellants/defendants have thus
already deducted the penalty with respect to any assumed delayed
work, and thus no further deduction can be allowed to the
appellants/defendants from the final bill.
10. Ld. counsel for the appellants/defendants very vainly
canvassed that the trial court ought not to have granted interest and in
any case not at 12% per annum, however considering that we are
talking of payments due in the year 2000, and in the year 2000 if loan
was taken by the respondent/plaintiff from any bank, surely at that
time, the respondent/plaintiff would have to pay interest @ 12% per
annum simple, and therefore there is no illegality in the trial court
awarding interest @ 12% per annum simple.
11. In view of the aforesaid discussion, this appeal is partially
allowed and the impugned judgment and decree in favour of the
respondent/plaintiff is reduced by a sum of Rs.47,500/- from the
decretal amount of Rs.1,99,100/- i.e now the money decree against the
appellants/defendants in favour of the respondent/plaintiff will be
Rs.1,51,600/-. The rest of the judgment with respect to interest and
costs will remain as it is. The Parties are left to bear their own costs
so far as this appeal is concerned.
12. The decretal amount has been deposited by the
appellants/defendants in this Court. Out of the aforesaid amount, the
respondent/plaintiff is entitled to withdraw a sum of Rs.1,51,600/-
alongwith interest till the date of deposit in this Court as a principal
amount, and since this amount deposited in this Court is lying in a
fixed deposit, on this amount payable to the respondent/plaintiff of
Rs.1,51,600/- alongwith interest @ 12% per annum till the date of
deposit in this Court interest has accrued in favour of
respondent/plaintiff and this amount which is payable to the
respondent/plaintiff will be the amount of Rs.1,51,600/- with interest
@ 12% per annum till the deposit in this Court and future interest
accrued thereon as per the fixed deposit made. The balance amount
alongwith interest accrued thereon be refunded back to the
appellants/defendants.
DECEMBER 05, 2018 VALMIKI J. MEHTA, J Ne
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!