Citation : 2018 Latest Caselaw 4560 Del
Judgement Date : 6 August, 2018
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision : August 06, 2018
+ FAO (OS) 337/2007
HINDUSTAN VIDYUT PRODUCTS LTD. ..... Appellant
Through Mr. B. Mohan and Mr. Siddharth
Aggarwal, Advs.
versus
DELHI POWER COMPANY LTD. & ANR. ..... Respondents
Through Mrs. Avnish Ahlawat and
Ms.Palak Rohmetra, Advs. with
Mr.Gaurav Gupta, GM (Legal)
for R-1.
FAO (OS) 338/2007
HINDUSTAN VIDYUT PRODUCTS LTD. ..... Appellant
Through Mr. B. Mohan and Mr. Siddharth
Aggarwal, Advs.
versus
DELHI TRANSCO LTD. & ANR. ..... Respondents
Through Mrs. Avnish Ahlawat and
Ms.Palak Rohmetra, Advs. with
Mr.Gaurav Gupta, GM (Legal)
for R-1.
CORAM:
HON'BLE MR. JUSTICE S. RAVINDRA BHAT
HON'BLE MR. JUSTICE A. K. CHAWLA
JUDGMENT
A.K. CHAWLA, J.
Both the appeals in hand, preferred under Section 37 of the Arbitration and Conciliation Act, 1996 (hereafter 'the Act'),
extend challenge to the judgment dated 25.07.2007 passed by the learned Single Judge allowing the two petitions being OMP No.114/2006 (Delhi Power Company Limited vs. Hindustan Vidyut Products Ltd. and Anr.) and OMP No.115/2006 (Delhi Transco Limited vs. Hindustan Vidyut Products Ltd. and Anr.) under Section 34 of the Act, where-under, an award dated 22.12.2005 passed by the learned Arbitrator in favour of the appellant and against the respondents; BSES Rajdhani Power Ltd.; Delhi Power Co. Ltd. (D.P.C.L.); North Delhi Power Ltd. (N.D.P.L.); and, BSES Yamuna Power Ltd., was set aside. Objections against the award came to be filed by the respondents only, claiming to be two independent entities other than as one, as find mention in the award. Instant appeals are so preferred against the order passed by the learned Single Judge on the objections filed by them.
2. Concisely, the facts relevant for the disposal of the appeals are that the appellant had entered into a contract for supply of goods with DESU-the predecessor-in-interest of Delhi Vidyut Board and the three DISCOMS i.e. Rajdhani Power Ltd., Yamuna Power Ltd. and North Delhi Power Ltd. in the year 1992. For the goods supplied by the appellant between 8th October, 1992 and 18th February, 1993, the challans/bills no. 201 dated 08.12.1992; 202 dated 08.10.1992; 270 dated 10.12.1992; 307 dated 17.01.1993; 320 dated 05.02.1993 and 334 dated 18.02.1993 were raised upon DESU. Goods so supplied were
received by DESU without any objection. As per the terms of payment, the appellant was to receive 100% payment with tax through bank or direct cash, within three days from the date of the receipt of the challan. At the time of release of the payment against such bills, a sum of `10 lakh was withheld on the premise that the appellant had supplied defective goods against contract no. TE 1949 and a penalty in that regard was contemplated. On the appellant making a representation dated 11.05.93, DESU vide its letter dated 24.05.1993 informed the appellant that the amount of `10 lakh was being withheld and rest of the amount was being released, on account of an earlier contract, where-under, allegedly, defective goods were received by it. Later, on the representations made by the appellant, vide its letter dated 19/21.06.2001, DVB, since successor-in-interest of DESU, informed the appellant that a penalty of `24,23,659.80 had been levied upon the appellant and the withheld amount of `10 lakh stood already adjusted. For the balance payment towards the penalty, demand was also raised. On this, the appellant sent notice dated 08.03.2002 demanding payment of the withheld amount of `10 lakh alongwith interest. It was not responded and the appellant proceeded to invoke the arbitration clause sending notice dated 08.03.2002. Arbitral proceedings so ensued amongst the parties.
3. The pertinent question agitated in the appeals is with regard to the question of limitation in invoking the arbitration
clause. According to the respondent, the arbitration clause was invoked much beyond the prescribed time and the claim made was therefore, time barred.
4. Undisputedly, the goods were delivered to and received by DESU during the period from 8.10.1992 to 18.2.1993. All such goods were supplied under one contract no. TE-45. It is also not in dispute that as per the terms of payment under the subject contract no.TE-45, 100% payment was payable within three days from the date of the receipt of challan. There is also no dispute to the fact that there was neither any defect in the goods nor in the documents furnished alongwith the bill/challan at the time of the delivery of the goods under contract no. TE-45. Whether the respective payments against the different supplies made under the subject contract no. TE-45 had come to be made by DESU within three days of the receipt of the bills/challans or not, equally has not been the question for consideration in the claim made by the appellant. The claim made by the appellant was solely founded on the premise that a sum total of `10 lakhs had come to be withheld by DESU/DVB for the supply of goods made by it under contract no. TE-45, the last of which supply was made vide bill/challan dated 18.2.1993. Arbitration came to be invoked by the appellant vide notice dated 8.3.2002 and it was so invoked pertaining to subject contract no.TE-45 only. Appellant asserts to have invoked the arbitration clause within prescription on the premise that the withholding of the payment
and the release thereof has always been under consideration by DVB without any denial/repudiation of the liability, till at least 19.6.2001, when DVB communicated adjustment of the said amount by it against the liability arising out of the contract no. TE-1949. Thus, according to the appellant, the invocation of the arbitration clause vide notice dated 8.3.2002 was within time. In support of such plea, the appellant placed reliance upon the letters dated 24.5.1993, 24.11.1999 and 19.6.2001 written by DESU/DVB to the appellant in response to the diverse representations made by the appellant for the release of the payment of `10 Lakh under contract no. TE-45.
5. Learned Arbitrator rejected the plea of prescription holding that in the given facts and circumstances, the case of the appellant was governed by Article 113 and not Article 14 of the Limitation Act, 1963. The reasons given to conclude so, are as follows :
"36. Arguments of the Counsel for claimant is that limitation in respect of any 'with-held or retained amount' does not start running till adjustment or appropriation of the same amount is made finally towards any dues of the party making adjustment. It is urged that the Claimant never agreed for adjustment of the amount of Rs.10 lacs. (It only suggested to retain some amount as an interim measure so that rest of huge dues of Claimant towards this and other supplies are released by Respondent Otherwise it was causing financial jeopardy to the business of the Claimant). It is urged that the 'retained amount', retained that character so long as it is not appropriated (even if
illegally) against any penalty imposed in future. Further arguments of the claimant is that, in the alternative the letters dated 19th/21st June, 1993 read with letter dated 24.11.1999, are promise to pay the retained amount within the meaning of Section 25 of Contract Act.
............................................................................................... .............................................................................................
38. The just interference from reading of these judgments is that when an amount due and payable to the Contractor on a supply order is with-held by purchaser because he claims that certain damages would be due to him in respect of an earlier supply order, although those damages have not been adjudicated in appropriate Forum nor admitted by Contractor and the amount is 'with-held', as interim measure till the final decision is taken about levy of damages, then so long as purchaser does not take such a final decision whether to levy a penalty or not and if yes, how much, the status of 'with-held amount' due to the Contractor on a letter supply order in the hands of the purchaser, would be 'holding it on account of the Contractor' till final decision on the levy of penalty is taken in respect of the earlier supply order. 'With- holding', is not an appropriation towards damages which might be payable when assessed, by the purchaser about the earlier supply order. The Purchaser, in such case, at best, is asserting his lien and no more. There is an implied promise or undertaking in such 'with-holding' and 'retaining' money of the contractor that it will be returned to the contractor, if finally no damages or less damages are payable. It is only when the final decision is taken by the purchaser, whether to levy penalty or not and if yes how much, (which in the present case is indicated by the fact that penalty to the extent of 50% of the purchase price was levied by the respondent in respect of earlier supply order no. TE-1949, as informed vide letter dated 19/21.6.2001, (CW-1/7), that cause of action can arise to the contractor to claim his amount finally arrived at and
limitation would start to run from that date because it is only by such act of appropriation by the purchaser that the contractor is told that money will not be paid to him. Before such an event, he can keep on waiting for the purchaser to release his money without risk of losing on limitation. Limitation does not start running against him before such an act of appropriation. Limitation will be governed by Article 113 and not by Article 14 of the Schedule to the Limitation Act. Cause of action arises when appropriation of payable dues is made, after levy of penalty.
............................................................................................... .............................................................................................
40. In the present case there was no term of supply order TE-45 that the price of goods supplied under this order can be adjusted or with-held for money claimed by purchaser as penalty which may be levied in respect of any earlier supply. When the Respondent (DESU), at that time, wrote to petitioner on 24.5.1993 that exact quantum of penalty will be worked out and intimated, the respondent was not sure about the penalty that would be worked out and imposed in future or if at all any penalty would be levied. It was at the best ' retaining' the amount of the claimant. Even in letter dated 19th/21st June, 2001, DESU was still writing with respect to that amount against order TE-1949. It was by this letter that they intimated about penalty of Rs.24,23,659.80 Ps. and claimant was asked to deposit it within 7 days. So that is the time when the recoverable amount was ascertained. It was then, at best, that Respondent treated the 'with-held amount' of Rs.10 lacs as appropriated to the penalty levied for earlier supply order. Respondent invoked arbitration process by letter dated 8th March, 2002 i.e. within 9 months of this appropriation. In express terms this appropriation has been pleaded by Respondent for the first time in the written reply to the Petitioner's claim petition. Assuming that
appropriation was made on 19th June, 2001, invoking of arbitration was within 3 years and so within limitation. ............................................................................................... ............................................................................................
43........................................................................................... ............................................................................................... Even if it is taken that there was no implied from promise to pay the money at the time when the decision whether to levy penalty in respect of the supply order No.TE-1949 or not, was taken by the Respondent, still the limitation in this case would not be covered by the Article 14 of the Schedule to the Limitation Act but by residuary Article 113 of that schedule, and limitation would start running when right to sue accrues. In such a case when the money is retained till a decision on penalty is taken, the right to sue will arise when that decision is conveyed. In a case like the present one, limitation would start running when the appropriation towards penalty on earlier supply order is made or is made by a particular letter. (In this case such letter is exhibit CW-1/7 dated 19/21.6.2001). So the limitation would start running at best from 21.6.2001 against the claimant. The arbitration in the present case was invoked vide notice dated 8.3.2002. So the arbitration proceedings were started within the period of three years prescribed under Article 113 to the Schedule of the Limitation Act. So the claim is within limitation.
6. Learned Single Judge of this Court did not find favour with the conclusions arrived at by the learned Arbitrator and took the view that the case in hand was not covered under Article 113 of the Limitation Act. The observations of the learned Single Judge in this regard are, as follows :
"10. It is settled law that question of limitation is mixed- question of law and facts. The facts in this case are not in
dispute. It is to be seen whether the limitation in this case would start running from 1993 or from 2001 as observed by the learned Arbitrator.
11. It is undisputed that amount of Rs.10 lakh was withheld by DESU in 1993. Despite protest of the respondent, the amount was not paid to the respondent. Rather vide its letter dated 24.5.1993 DESU confirmed withholding of Rs.10 lakh against defective supplies made by the respondent in contract no. TE 1949. There is no letter written by the respondent protesting against initiation of penalty proceedings in respect of supply order no. TE 1949 under which the respondent had supplied defective goods. At no stage, respondent wrote to the petitioner that no penalty proceedings could be initiated or the goods supplied were not defective and the amount could not be withheld. This assumes importance for the question of limitation. If the claimant had a grievance that no amount could be withheld out of the bills of 17.1.1993 & 5.2.1993 or if he had any grievance that no penalty could be imposed in respect of previous contract or no amount could be recovered regarding previous contract he was supposed to make a grievance of this and raise a dispute in 1993 itself. The claimant did not raise a dispute from May 1993 onward against wrongful withholding of Rs.10 lakh. I consider that the period of limitation, in a case where amount is payable against a specific contract and is not paid, starts from the date when payment of the amount is refused and no assurance is given that this amount would be paid at any time in future. In the present case, no assurance was given by DESU that this amount would be paid to him. The learned Arbitrator came to the conclusion that there was no consent of the respondent for withholding this amount. In view of this finding Learned Arbitrator's conclusion that limitation will start from 19.6.2001 is contrary to law. In either case whether there was consent of the respondent to withhold the amount or there was no consent, the limitation cannot be held to have started from 19.6.2001. The limitation would start running
from the day amount is wrongfully withheld and not paid. If the respondent had the stand that this amount could not be withheld and could not be adjusted against any contract, this stand need to have been taken immediately and dispute need to have been raised in May 1993 itself or within 3 years of it. The limitation would start running when the amount was "wrongly" withheld. If, withholding was bad, it was bad in 1993 it did not become bad in 2001. The limitation would therefore start in 1993 and not in 2001. The judgment cited by the respondent is not applicable to the facts of this case. In the cited case, the dispute was between family members and the family members had been corresponding with each other. It is only when the dispute crystallized that it could be referred to the arbitration. In the present case, the dispute is not between family members and the dispute was purely of commercial nature and parties were being governed by commercial interest. The amount was withheld because of defective supplies of material by the respondent and the respondent was informed of this. If the claimant had wanted to challenge the withholding as a wrongful withholding, he need to have taken action within three years of May 1993. I find that the decision of the Arbitrator is contrary to the law and Public Policy that state claims are required to be rested. The award is liable to set aside on this ground.
12. The Arbitrator had not held how petitioner became successor of Delhi Vidyut Board in respect of the claim. The Arbitrator ought to have fixed the responsibility of each of the respondent and could not have held that it had no jurisdiction to decide the issue. The Arbitrator had jurisdiction to fix the responsibility as to who was liable to pay the amount. Since the award has been given by the Learned Arbitrator in respect of time barred claim, it is a patent illegality and the award is liable to be set aside in view of the judgment of Supreme Court in Oil & Natural Gas Corporation v. Saw Pipes Limited (2003) 5 SCC 705 and McDermott International Inc. v. Burn Standard Co.
Ltd. & Ors (2006) 11 SCC 181. The award is hereby set aside. The petition is allowed."
The conclusions so arrived at by the learned Single Judge are premised on the applicability of Article 14 or 15. The learned Single Judge took the view that the withholding of the amount took place in May, 1993, which according to the appellant was unlawful and therefore, the action there-against was required to be taken within three years of such withholding.
7. In the submissions of the learned counsel for the appellant, no dispute could have been raised by the appellant on an earlier point of time as there was a "live issue" and the dispute in that context, for the first time, arose only on 19/21.6.2001, when the claim was sought to be repudiated. In his submissions, the conclusions arrived at by the learned Single Judge for the amount having been wrongly withheld in the year 1993 was based on surmises and the conjectures inasmuch as the material on record would show that such an issue was always alive and that, the amount was withheld by the respondent with the consent of the appellant. Assailing the impugned judgment, it is also contended that the learned Arbitrator had interpreted the letter dated 11.5.1993 as not an admission of liability for `10 lakh towards the alleged defective supplies under some other contract. In support of its submissions, reliance is placed upon Hari Shankar Singhania & Ors. vs. Gaur Hari Singhania, 2006 (4) SCALE 74; Shree Ram Mills vs. Utility Premises (P) Ltd.,
2007 (4) SCALE 571; Associate Builders vs. Delhi Development Authority, 2014 (13) SCALE 226; and, National Highways Authority of India vs. M/s ITD Cementation India Ltd., 2015 (5) SCALE 554.
8. In the submissions of the learned counsel for the respondents, the claim made by the appellant was hopelessly barred by time and the learned Arbitrator misconducted himself by holding that the respondents were jointly and severally liable to pay `20,26,000/- being successors-in-interest of Delhi Vidyut Board for the purposes of claim as provided under Delhi Electricity Reforms (Transfer Scheme) Rules, 2001. It is also the plea of the respondents that the limitation for commencement of arbitration runs from the date, when the cause for arbitration arose and that, in the present case, it is to be reckoned from date of expiry of the period of credit. In support of such plea, reliance is placed upon 2006 (1) SCC 164, 1993(1) SCC 572, 1996 (2) SCC 216, 2003 (5) SCC 705, 1999 (8) SCC 122, 2006 (11) SCC 181. It was also contended that in the case in hand, there were three distribution companies who were the successors of DVB having utilized the cables in the distribution lines.
9. Article 113 is to be construed as an omnibus Article. This Article can be invoked only if by a reasonable consideration no other Article for the institution of suits is attracted. Be that as it may, in our considered opinion, neither Article 113 nor Article 14 or 15 is attracted to the case in hand. These Articles apply to
suits. The case before us is however of making an application to the Court for appointment of an Arbitrator and it is now well settled that for making such applications, Article 137 is attracted. Article 137 reads as follows :
"Any other application for Three years When the which no period of limitation right to is provided elsewhere in this apply division. accrues."
This Article on its plain reading shows that it speaks of a right accruing to a party to apply for, or, in other words, make an application. When does such right to apply arise to a party under a contract prescribing resolution of the disputes amongst them through arbitration, would necessarily depend upon the facts and circumstances of each case. It would be a mixed question of fact and law. In the case in hand, the last supply of the goods under the subject contract TE-45 was made vide challan/bill dated 18.02.1993 and the payment there-under was to be made by DESU within three days of the receipt of the challan/bill. Can then it be said that immediately on the expiry of the period of credit, a right had accrued to the appellant to apply for appointment of an Arbitrator? Answer thereto has to be in the Negative, for the simple reason that the parties had agreed to resolve the matter amicably through arbitration and as on that day, no dispute or difference had arisen amongst the parties which would have prompted the appellant to apply for making
an application to the Court for appointment of an Arbitrator. Can then it be said that it arose on 24.05.1993, when the respondent conveyed to the appellant that it was advising its accounts department to release all its payments except `10 lakhs against the defective supply against TE-1949 as the exact quantum of penalty was being worked out to be intimated in due course? This communication dated 24.05.1993, in our considered view, by no means suggests that the instructions so issued by it and communicated to the appellant were determinative of the contract and/or determinative of full and final satisfaction of all claims amongst the parties under the subject contract TE-45. On a plain reading, this letter only suggests that the instructions contained therein, were of temporary nature and the final outcome, was to depend upon the outcome of the contemplated action of imposition of penalty in relation to another contract i.e. TE-1949. Seen from another perspective, the said letter/communication does not suggest that the said instructions were determinative even of the quantum of the amount(s) against the contemplated action. When the contemplated action had not yet concluded, at this stage, it could not be said that the amount to be adjusted would be either `10 lakhs or beyond or it could be a meagre sum of `50,000/- or `5,000/- or at all. This leads to irresistible conclusion that the account in that regard was kept open to be settled at a later stage. At the most, it can therefore be said that on the appellant's accepting the stance of DESU to withhold/retain the sum of `10 lakhs under the subject
contract, a consensus was arrived amongst the parties to settle such accounts at a later stage, when the event of adjustments on the imposition of the contemplated penalty comes to be imposed and is sought to be recovered from the dues payable under the subject contract TE-45. Right to apply for appointment of an Arbitrator therefore cannot be said to have accrued to the appellant on the issuance or the receipt of the letter dated 24.05.1993 as well. The acceptance of the terms contained in the letter dated 24.05.1993 by the appellant is only suggestive of the fact that there was a consensus amongst the parties to keep any of their disputes and the differences in abeyance, till the time, the contemplated action in relation to another contract fructifies. It is matter of record that the parties from this time onwards continued to represent each other on the similar lines till the time the respondent vide its communication dated 19/21.6.2001 conveyed that it had adjusted the entire sum of `10 lakhs towards its claim against another contract. The material on record also leaves no doubt that the claim of the appellant was all along kept alive. In other words, the parties had not concluded their claims at least till around 19/21.6.2001. In somewhat similar circumstances adverting to considerations before the Chief Justice or the Court, when an application under Section 11(6) for appointment of an Arbitrator is made, Supreme Court in SBP & Co. v. Patel Engg. Ltd., (2005) 8 SCC 618 observed as under:
"39. It is necessary to define what exactly the Chief Justice, approached with an application under Section 11 of the Act, is to decide at that stage. Obviously, he has to decide his own jurisdiction in the sense whether the party making the motion has approached the right High Court. He has to decide whether there is an arbitration agreement, as defined in the Act and whether the person who has made the request before him, is a party to such an agreement. It is necessary to indicate that he can also decide the question whether the claim was a dead one; or a long-barred claim that was sought to be resurrected and whether the parties have concluded the transaction by recording satisfaction of their mutual rights and obligations or by receiving the final payment without objection. It may not be possible at that stage, to decide whether a live claim made, is one which comes within the purview of the arbitration clause. It will be appropriate to leave that question to be decided by the Arbitral Tribunal on taking evidence, along with the merits of the claims involved in the arbitration. The Chief Justice has to decide whether the applicant has satisfied the conditions for appointing an arbitrator under Section 11(6) of the Act. For the purpose of taking a decision on these aspects, the Chief Justice can either proceed on the basis of affidavits and the documents produced or take such evidence or get such evidence recorded, as may be necessary. We think that adoption of this procedure in the context of the Act would best serve the purpose sought to be achieved by the Act of expediting the process of arbitration, without too many approaches to the court at various stages of the proceedings before the Arbitral Tribunal."
The above-said observations were re-iterated in the subsequent judgment 2007 (4) SCALE 571, Shree Ram Mills Ltd. vs. Utility Premises (P) Ltd. relied upon by the learned counsel for the appellant. In Shree Ram Mills' case (supra), the Supreme
Court reiterated the ratio of the judgment delivered by it in Hari Shankar Singhania & Ors. vs. Gaur Hari Singhania & Ors. 2006 (4) SCALE 74, with the observations, as follows :
"30. Once we have come to the conclusion that the learned designated Judge was right in holding that there was a live issue, the question of limitation automatically gets resolved. This Court in Hari Shanker Singhania case [(2006) 4 SCC 658] held that till such time as the settlement talks are going on directly or by way of correspondence no issue arises and with the result the clock of limitation does not start ticking. This Court observed:
"24. Where a settlement with or without conciliation is not possible, then comes the stage of adjudication by way of arbitration. Article 137, as construed in this sense, then as long as parties are in dialogue and even the differences would have surfaced it cannot be asserted that a limitation under Article 137 has commenced. Such an interpretation will compel the parties to resort to litigation/arbitration even where there is serious hope of the parties themselves resolving the issues ........................................................"
These observations would clearly suggest that where the negotiations were still on, there would be no question of starting of the limitation period."
10. In view of the afore-going, none of the judgments relied upon by the learned counsel for the respondent are of any avail to it. The State of Orissa's (supra) case, on a careful reading, would show that it lays down that the cause of arbitration arises when disputes or differences arise on the unequivocal denial of
the claim of one party by the other. In the case in hand however, there was no unequivocal denial of the claim of the appellant by the respondent till around 19/21.6.2001. HUDA's case (supra) relates to a case where a claim for compensation had come to be granted by the NCDRC in a complaint for deficiency of service much beyond the period of limitation provided under the Act. No parity with the provisions of Consumer Protection Act can be drawn with the case in hand. Said case is outrightly distinguishable on facts. ONGC's and Mcdermott International's cases (supra) are the cases, which relate to a petition filed under Section 34 of the Act and have equally no bearing to the case in hand. SAIL's case (supra) interprets the misconduct attributable to the Arbitrator, when he exceeds his jurisdiction or goes beyond his jurisdiction. This case is also not applicable to the case in hand.
11. Keeping in view the totality of the facts and circumstances and the position of law enunciated in the judgments referred to in para 9, we are of the considered view that the conclusions arrived at by the learned Arbitrator that the claim of the appellant was not hit by the limitation of time, cannot be said to be either unfair or opposed to public policy. It was certainly logical as well, in the given factual conspectus.
12. Besides the question of limitation, another question attracting consideration is with respect to the liabilities of the respondents under the award. The respondents-Delhi Transco
Ltd. and Delhi Power Company Ltd. are two separate companies. These two companies came into existence in pursuance of Delhi Electricity Reforms Act, 2000 in short "DERA" and the Delhi Electricity Reforms Transfer Schemes Rules, 2001 in short "the Rules". DERA had come to be enacted for the constitution of an Electricity Commission, restructuring of the electricity industry by rationalization of generation, transmission, distribution and supply of electricity, increasing avenues for participation for private sector in the electricity industry and for taking measures conducive to development and management of the electricity industry in an efficient, commercial, economic and competitive manner in the National Capital Territory of Delhi. To achieve this end, the Act and the Scheme adopted a three step procedure whereby the Government of NCT, after enforcement of DERA, in exercise of its obligation and power under Section 14, incorporated separate companies, segregating the different functions of electricity generation, transmission and distribution. By operation of Section 15, the Government was empowered to transfer rights and liabilities immediately before the effective date of itself. DERA came into force w.e.f. 03.11.2000 and in pursuance of the objects thereof, the Govt. of NCT notified binding policy directions, enabling restructuring of DVB and in relation to the liabilities of the DISCOMS, provided for as under :
"8. Pending suits, proceedings--(1) All proceedings of whatever nature by or against the Board pending on the
date of the transfer shall not abate or discontinue or otherwise in any way prejudicially be affected and the proceedings may be continued, prosecuted and enforced, by or against the transferee to whom the same are assigned in accordance with these rules.
............................................................................................... ............................................................................................... (3) Notwithstanding anything contained in these rules including the schedules, the liabilities arising out of litigation, suits, claims, etc. pending on the date of the transfer and/or arising due to events prior to the date of the transfer shall be borne by the relevant distribution company viz. DISCOM 1, DISCOM 2 and DISCOM 3 respectively, subject to a maximum of Rs. 1 crore per annum. Any amount above this shall be to the account of the Holding Company in the event for any reason the Commission does not allow the amount to be included in the revenue Requirement of the DISCOM."
It would thus be seen that the afore-going Rules, which have the statutory force, fix the liabilities upon the DISCOMS inter alia in relation to the subject matter of the award. Here, it would suffice to say, while Delhi Transco Ltd. was incorporated for procurement, transmission and supply of electricity to the subsidiary companies i.e. the DISCOMS, Delhi Power Company Ltd. was incorporated as a holding company of the shares in the distributing companies i.e. the DISCOMS and Indraprastha Power Generation Co. Ltd. Liability to make any payment in relation to the subject award therefore, is not attracted as against the instant respondents i.e. Delhi Transco Ltd. and Delhi Power Ltd. Impugned award to that extent is therefore, not sustainable.
13. Since none of the DISCOMS have chosen to extend challenge to the impugned award, it is not necessary to get into their individual liabilities under such award.
14. In view of the foregoing, the impugned judgment of the learned Single Judge dated 25.07.2007 is set aside and the award dated 22.12.2005 is set aside as against the instant respondents i.e. Delhi Transco Ltd. and Delhi Power Supply Co. Ltd. and is consequently modified to that effect. Appeals stand disposed of accordingly. No order as to costs.
A. K. CHAWLA, J
S. RAVINDRA BHAT, J AUGUST 06, 2018 rc
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!