Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Inflow Technologies Pvt Ltd vs Gramtech(India) Pvt Ltd
2018 Latest Caselaw 2155 Del

Citation : 2018 Latest Caselaw 2155 Del
Judgement Date : 6 April, 2018

Delhi High Court
Inflow Technologies Pvt Ltd vs Gramtech(India) Pvt Ltd on 6 April, 2018
$~CP-19
*    IN THE HIGH COURT OF DELHI AT NEW DELHI
%                                            Date of decision: 06.04.2018
+      CO.PET. 534/2013 and Co. Appl. 1842/2013, 197/2017
       INFLOW TECHNOLOGIES PVT LTD          ..... Petitioner
                   Through  Mr. Gaurav Kejriwal and Mr.Sujit
                            Kuma Keshri, Advs.

                          versus

       GRAMTECH(INDIA) PVT LTD                ..... Respondent

Through Mr.Rohit Singh, Adv.

CORAM:

HON'BLE MR. JUSTICE JAYANT NATH

JAYANT NATH, J.(ORAL)

1. This petition is filed under Sections 433 and 434 of the Companies Act, 1956 seeking winding up of the respondent Company. It is contended by the petitioner that the respondent Company had from time to time placed purchase orders on the petitioner for purchase of software and for services related to the software. On 18.06.2010 through two letters, the respondent placed purchase orders on the petitioner for purchase of the software with standard support for one year and also for installation and implementation of the same.

2. The first order dated 18.06.2010 was regarding purchase of software (SQL anywhere advance edition 25 user) and standard support service for a period of one year and the total amount of consideration was Rs.6,87,013/-.

3. The second order was regarding installation and implementation of the software at the respondent's client's site and the total cost for that was

Rs.9,45,226/-.

4. There is no dispute regarding the first purchase order for which the petitioner has received payments. The dispute centres around the second purchase order.

5. It is the case of the petitioner that after installation and implementation, the petitioner procured the required Implementation Completion Certificate dated 24.08.2010 from the client of the respondent. It may be noted that the respondent was doing the work on behalf of the Indian Navy. It is pleaded that the said Certificate was duly signed by the official of the Indian Navy. Thereafter, it is stated that the petitioner raised an invoice dated 23.09.2010 for an amount of Rs.9,45,227/-. However, the respondent failed to honour the said amount. In these circumstances, the petitioner issued a legal notice on 10.09.2010. A reply was received from the respondent on 01.10.2012 denying its liability. Hence, the present winding up petition.

6. The respondent have filed their reply. In the reply, various defences are taken, namely, that the claim of the petitioner is barred by limitation, the petitioner failed to get the Implementation Completion Certificate from the client of the respondent, namely, the Indian Navy and the petitioner failed to complete the work.

7. I have heard learned counsel for the parties.

8. Learned counsel for the respondent has vehemently submitted as follows:-

(i) He submits that as per the purchase order which was placed on the petitioner, the payment was payable 50% on installation and balance 50% on completion of scope of work. He submits that the cause of action arose when

as per the petitioner the work was completed. He points out that as per the petitioner, the work was completed on 24.08.2010 whereas the present winding up petition has been filed on 21.09.2013. It is hence pleaded that the present debt had become barred by limitation when the present winding up petition was filed. Reliance is placed on Article 18 of the Schedule to the Limitation Act.

(ii) He further submits that despite placing the purchase order, the petitioner failed to complete any work. Hence, it was the respondent Company which carried out the work and had got the necessary payment from the client, namely, the Indian Navy. Hence, no amount is due to the petitioner.

(iii) He further submits that the petitioner is wrongly relying upon the Implementation Completion Certificate dated 24.08.2010. This, he submits, has been issued to one M/s. Sybase Professional Services which is an unknown entity and not known to the respondent. Further, the certificate is not in the prescribed format of the Implementation Completion Certificate. Hence, no amount is due to the petitioner.

9. I may point out that this court on 26.02.2018 had noted the submissions of the respondent and had issued a direction to the respondent to file an affidavit as to whether the respondent received any payment from the end user, namely, the Indian Navy. This court had directed as follows:-

"Learned counsel for the respondent has made two broad submissions. He firstly, submits that the work that was assigned to the petitioner has not been installed and that the completion certificate relied upon by the petitioner is not in the correct format and cannot be called a completion certificate. He in fact submits that the so called completion certificate relied upon by the petitioner is a time sheet. He further submits that this

document relied upon by the petitioner was never provided to the respondent earlier. He secondly submits that the claim is barred by limitation.

Before I hear the matter further, in my opinion, it would be appropriate that the respondent files an affidavit of the Managing Director of the respondent Company who will confirm as to whether the respondent received any payment from the end user, namely, the Indian Navy for the above noted equipment, namely, (SQL anywhere Advanced Edition 25 User). The affidavit will be filed within three weeks from today with advance copy to the learned counsel for the petitioner. I t is made clear that if there is any default in filing of the affidavit, the matter will be disposed of on the next date of hearing."

10. Pursuant to the said order dated 26.02.2018, the respondent has filed an affidavit of Mr.Rakesh Gupta, Director of the respondent Company. In the affidavit it is stated that the petitioner did not perform their work as per the scope of work of the client and hence, the respondent was compelled to complete the project. It is also stated that after issuing of Implementation Completion Certificate on completion of the project, the Navy released the payment in favour of the respondent Company.

11. I may first deal with the contention of the respondent that the work was never completed and the Implementation Completion Certificate is not in the prescribed format. The petitioner has filed the Implementation Completion Certificate dated 24.08.2010 which appears on a letter head of M/s. Sybase Professional Services. The said certificate provides details of various functions and the dates when the functions were completed. At the end of the Certificate a stamp has been put by the Indian Navy which is signed by Cdr.Vikrant Jairath showing that the work was completed and the Certificate is dated 24.08.2010. The correct format in which the said

Implementation Completion Certificate was to be issued has not been placed on record by the respondent. There may perhaps not be a strict technical compliance of the requirement. However, a perusal of this document would show that the work in question was completed by the petitioner/Sybase Professional Services, a sub-contractor of the petitioner. From the above, it becomes quite clear that the work that was entrusted to the petitioner by the second purchase order was completed as per Indian Navy.

12. The question that now arises is that was the work completed by the petitioner or as claimed by the respondent, by the respondent.

13. After perusing the facts, in my opinion, it is quite manifest from the record that the work was completed by the petitioner and the plea raised by the respondent that the work was completed by the respondent is a bogus plea. Reasons for the above conclusions are noted herein below. 13.1 In the affidavit filed pursuant to the last order of this court by the respondent and now, while hearing submissions, what has been vehemently argued is that the petitioner never completed the work that was assigned to it by the purchase order and that it is the respondent who has completed the work and has thereafter obtained the said completion certificate and also received the money from the client, namely, the Indian Navy. However, it is interesting to note that a perusal of the reply dated 01.10.2012 sent by the respondent to the legal notice issued by the petitioner on 10.09.2012 or the reply to the present petition would show that there is no averment anywhere made that the work has been completed by the respondent company. A perusal of the reply to the present petition shows that essentially what has been pleaded is that the completion certificate filed by the petitioner is a time sheet and fabricated document. It is also pleaded that the petitioner did

not perform his work. There is no averment that the work was ever completed and the respondent received the money from the Indian Navy. It is now at the time of arguments, the respondent have chosen to come up with this plea that it was the respondent who performed the work which plea had never been taken earlier. This is clearly an afterthought which is now sought to be introduced after pleadings have been completed in the course of arguments. Clearly, the version now being sought to be introduced by the respondent cannot be believed.

13.2 Another interesting fact is that the respondent did not even mention in their reply that they received the consideration from Indian Navy. It is only pursuant to the order of this court dated 28.02.2018 that in the affidavit filed it has been revealed that the respondent has received the payment from the Indian Navy. This act/conduct of the respondent is quite surprising. It is obvious that the work was completed and the respondent have received money. They owed a duty to reveal the full facts to the court and inform the court that they have received the money for the work done. Their failure to intimate to the court the full facts throws a grave doubt on pleas made today before this court.

It is clear that the said amount was due and payable to the petitioner and the respondent are only finding pretexts not to make the payment.

14. As far as the issue of limitation is concerned, learned counsel for the respondent has relied upon Article 18 of the Schedule to the Limitation Act, 1963. The same reads as follows:-

       18.           For the price of Three years            When     the
                     work done by the                        work       is
                     plaintiff for the                       done.
                     defendant at his




                     request, where no
                    time has been
                    fixed         for
                    payment



15. Relevant portion of the second purchase order dated 18.06.2010 reads as follows:-

"2) Payment: For Implementation: 50% on installation as balance 50% on completion of scope of work.( Customer PO and Scope of work is attached)

(We need the implementation completion certificate from the User)"

16. The case of the petitioner is that after the work was completed, the petitioner has raised the invoice dated 23.09.2010. I may note that raising an invoice pursuant to completion of the work is a standard procedure inasmuch as it is the invoice that brings out the details of service tax and other statutory requirements. In the absence of any invoice it is not clear how the respondent would make the payment. Even otherwise, the completion certificate which has been produced by the petitioner has been issued by the Indian Navy. It is not addressed to the respondent. The respondent will receive knowledge of completion of the work only when he receives this completion certificate. It is only when the respondent receives the invoices alongwith the completion certificate that he would have a liability to pay in terms of the contract. Hence, the limitation has to start from the date of receipt of the invoice along with the completion certificate and not otherwise. In fact for the first purchase order also the petitioner had raised an invoice dated 18.06.2010. A perusal of the first purchase order

would show that again there is no requirement stated of raising an invoice inasmuch as payment was payable within 45 days of delivery of the software yet an invoice was raised and payment has been effected. In the present case as the invoice for the second purchase order was raised on 23.09.2010, the present winding up petition that has now been filed on 21.09.2013 cannot be said to be barred by limitation.

17. Reference may also be had to the judgment of the Division Bench of the Allahabad High Court in Devender Kumar v. Nagar Palika Parishad Shamli & Anr., 2015 SCC OnLine All 5976. The Division Bench while referring to Article 18 to the Schedule of the Limitation Act, 1963 held as follows:

"20. A bare reading of aforesaid provision shows, where no time for payment has been prescribed or fixed in the agreement between parties or otherwise, limitation would be three years from the date work has been done by plaintiff. This Article applies where plaintiff has performed some work at the request of defendant.

21. All these conditions are satisfied in the present case. The dispute is confined as to the meaning of the term "work done". Whether literally it would mean that work is completed or done when claimed by plaintiff on his own or when it is measured and found satisfactory by defendants, at whose request work has been done by plaintiff.

22. In our view work done can only be said when defendant, who has to make payment and at whose request the work is done by plaintiff, is satisfied that work has been done. This satisfaction that work has been done on the part of defendant would come only when work done by plaintiff is measured by competent authority of defendant and entered in the measurement book.

23. If intention of legislature would have been only to commence limitation as soon as plaintiff has completed some work according to his own understanding or claim, rest of the part would not have been necessary to be mentioned in aforesaid provision. However, when legislature has added words for the defendant at his request' it means that whatever work is done by plaintiff, it must be such which has been requested by defendant and is performed for defendant. Therefore, ultimate decision to evident that work has been done, would be that of defendant.

24. In the present case it is not in dispute that work was done by plaintiff in his own way in 1992. The defendants, however, got his satisfaction after measurement thereof in 1996. Thus it can be said that work has been done only in 1996 when Assistant Engineer submitted his report on 17.6.1996 or when Additional Chief Officer, Nagar Palika Parishad made recommendation for payment seeking approval of higher authority vide report dated 26.6.196.

25. Words 'when the work is done' in clause 3 of Article 18, therefore, will have to be read in consonance with column 1 and we are of the view that to attract Article 18, limitation would commence when work done by plaintiff is measured by defendant and he finds satisfaction that work as requested has been done by plaintiff for defendant."

18. Similarly, a Bench of the Punjab & Harayana High Court in Jullundur Improvement Trust, Jullundur v. Kuldip Singh, AIR 1984 P&H 185/(MANU/PH/0159/1984) held that Article 18 of the Limitation Act, 1963 would be attracted in the facts of those case when the work was dully entered in the measurement book and on the basis of which the final bill was prepared. Clearly, settled legal position is that it is only when as per the defendant the work is done that the limitation starts running under Article 18

of the Schedule to the Limitation and not when the plaintiff claims that the work is completed. In these circumstances, even otherwise it cannot be said as claimed by the respondent that the limitation will commence from the date of completion certificate per se.

19. In my opinion, the defence raised by the respondent is not bona fide or valid. The respondent is liable to pay the petitioner and is refusing to pay. Accordingly, I admit the present petition

20. The Official Liquidator attached to this court is appointed as the Provisional Liquidator. He is directed to take over all the assets, books of accounts and records of the respondent-company forthwith. The citations be published in the Delhi editions of the newspapers 'Statesman' (English) and 'Veer Arjun' (Hindi), as well as in the Delhi Gazette, at least 14 days prior to the next date of hearing. The cost of publication is to be borne by the petitioner who shall deposit a sum Rs75,000/- with the Official Liquidator within 2 weeks, subject to any further amounts that may be called for by the liquidator for this purpose, if required. The Official Liquidator shall also endeavour to prepare a complete inventory of all the assets of the respondent-company when the same are taken over; and the premises in which they are kept shall be sealed by him. At the same time, he may also seek the assistance of a valuer to value all assets to facilitate the process of winding up. It will also be open to the Official Liquidator to seek police help in the discharge of his duties, if he considers it appropriate to do so. The Official Liquidator to take all further steps that may be necessary in this regard to protect the premises and assets of the respondent-company.

21. In the interest of justice, I suspend this order for a period of one month only. In case the respondent makes the necessary payment of

Rs.9,45,226/- to the petitioner within one month from today, the aforesaid order shall stand recalled.

22. List on 08.08.2018.

JAYANT NATH, J APRIL 06, 2018/rb

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter