Citation : 2017 Latest Caselaw 5443 Del
Judgement Date : 26 September, 2017
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on : 20.9.2017
Judgment delivered on : 26.9.2017
+ W.P.(C) 9213/2016
DR. RISHI KANT SIDDHARTH MAHAVIDYALAYA SEVA
SANSTHAN ..... Petitioner
Through: Mr Mayank Manish, Adv
versus
NATIONAL COUNCIL FOR TEACHER EDUCATION & ANR
..... Respondents
Through Ms. Sonali Malhotra and Mr. Amit
Sanduja, Advs
CORAM:
HON'BLE MS. JUSTICE INDERMEET KAUR
INDERMEET KAUR, J.
1 Petitioner is aggrieved by the order dated 11.9.2015 passed by the
Northern Regional Committee (respondent no.2) which was affirmed on
09.06.2016 by its Appellate Authority, National Council for Teacher
Education (respondent no.1).
2 Record shows that on 29.12.2012 the petitioner institute had applied to
respondent no.2 seeking recognition for its course of Bachelor of Education
(B.Ed. course) for intake of 100 seats. All relevant documents were
submitted to respondent no.2. The Building Completiton Certificate (BCC)
issued by its architect was obtained by the petitioner and on 08.01.2015 this
BCC document (duly certified by the Village Panchayat) had been handed
over to respondent no.2. Respondent no.2 failed to process the application of
the petitioner for some time. Thereafter in its 238th Meeting (between
20.5.2015 to 31.5.2015) it decided to issue a show cause notice to the
petitioner. Petitioner responded to this show cause notice on 19.6.2015.
Vide this communication dated 19.6.2015 he dispatched the BCC related
documents to the office of respondent no.2. Respondent no.2, however,
refused to grant recognition to the petitioner and dismissed his prayer; this
was endorsed by respondent no.1. This exercise by the respondents is
arbitrary. The order is liable to be set aside.
3 Counter affidavit has been filed. Stand of the respondents is that BCC
related documents had never been filed before respondent no.2. There is a
time schedule laid down by the respondents during which the documents
have to be submitted. It is pointed out that on 16.6.2015 a show cause notice
was issued to the petitioner informing the petitioner that the BCC related
document certified by the competent Government Authority in the prescribed
format has not been submitted. Submission is that the fact of the issuance of
the show cause notice on 16.6.2015 asking the petitioner to file the BCC
document (duly certified by the competent Government Authority in the
prescribed format) is not in dispute. Further submission is that neither any
reply to the aforenoted show cause notice was filed by the petitioner and nor
was the said document submitted to respondent no.2. Petitioner's
submission that he submitted its BCC document on 19.6.2015 is palpably
false; he has nothing on record to substantiate this submission. In the
absence of the BCC document being before the competent authority,
respondent no.2 had no other option but to reject the case of the petitioner.
The appeal order passed by respondent no.1 endorsing this fact thus suffers
from no infirmity.
4 Rejoinder has been filed affirming the averments made in the petition.
It is not disputed that a notice dated 16.6.2015 sent by respondent no.2 had
been duly received by the peititioner. This averment of the respondents find
mentions in para 8 of the counter affidavit. Corresponding para in the
rejoinder admits that this is a matter of record. This being the factual
position and the petitioner having failed to substantiate his case that he had
filed his BCC document on 19.6.2015 nothing really remains to be answered.
This is also for the reason that even as per the petitioner in his purpoted reply
of 19.06.2016 he did not state that he had already filed the BCC document
on 08.01.2015; he merely responded by filing the BCC document again.
Before respondent no.1 (Appellate Authority) on 09.06.2016 respondent no.1
had recorded that during the course of hearing before it, a copy of the letter
dated 19.6.2015 along with the BCC related document had been placed by
the petitoner. It had also been noted that this document was not in the records
of the Regional Committee. Petitioner had also failed to show any proof of
either a dispatch or receipt of this letter by respondent no.2. Moreover, this
BCC related document was issued by a private architect; date of the
inspection of the building or the date of the issuance of the certificate as also
the date of its approval by Pradhan of Gram Panchayat was not known.
5 Arguments have been heard. Record perused. 6 On the perusal of the record, the Scrutiny of this BCC related
document (Annexure P-2) (which has been filed along with this petition)
reveals that this document has no date of the issuance of the certificate;
there is also no date indicating as to when the building of the petitioner was
inspected pursuant to which the building certificate had been granted.
Moreover, this document has been prepared by one Saurabh Saxena i.e. a
private architect.
7 Regulation 8 (7) of the Regulations of the National Counsel for
Teacher Education (made pursuant to a statutory legislation i.e. the National
Council for Teacher Education Act, 1993) are relevant. Regulation 8 deals
with the conditions for grant of recognition. Regulation 8 (7) reads as under:
"8. Conditions for grant of recognition- (1)......
(2)................
...................
(7) At the time of inspection, the building of the institution shall be completed in the form of a permanent structure on the land possessed by the institution, equipped with all necessary amenities and fulfilling all such requirements as prescribed in the norms and standards. The applicant institution shall produce the original completiton certificate issued by the competent Authority, approved building plan in proof of the completiton of building and built up area and other documents to the visiting team for verification. No temporary strucutre or asbestos roofing shall be allowed in the institution, even if it is in addition to the prescribed built up area." 8 This regulation mandates that at the time of inspection the building of
the institute should be complete as per the requirement, norms and standards;
the institute should produce his original completion certificate issued by a
competent authority along with the approved building plan for the purposes
of verification.
9 The petitioner institute had been inspected on 14.5.2015. It is not the
case of the petitioner that the BCC related document was not available at that
time; his case all along being that he had given this document firstly on
08.01.2015 and thereafter again alongwith his reply dated 19.06.2015 to the
show cause notice (issued by respondent no.2) the petitioner had submitted
the building completition certificate to respondent no.2. He admittedly has
no proof of substantiating this submission. This was in spite of opportunity
afforded to him both by respondent no.2 and respondent no.1. Respondent
no.1 in the course of hearing had noted that a letter dated 19.6.2015 has been
shown to respondent no. 2 (alongwith the BCC document) but this letter of
the BCC document were not a part of the file of the respondent no.2 (NRC).
It was correctly held that this document had not been filed before the
Regional Committee.
10 That apart the lacunae in the document were many. There was
admittedly no date mentioned in the document. It bore a stamp of
08.01.2015 which was a stamp of Uttar Pradesh (first page of the document)
and as rightly pointed out by the learned counsel for respondents this
document becomes suspect for the reason that if this document was stamped
on 08.01.2015 in the State of Uttar Pradesh, then how the petitioner had
submitted this document on the same day i.e. 08.01.2015 to the Regional
Committee (respondent no.2) at Rajasthan is not explained. This query has
been put to the learned counsel for petitioner for which he has no answer. It
is also strange that a private architect (Saurabh Saxena) having prepared this
certificate had not thought it fit to give the date under his signatures. In the
first part of the document the architect had certified that he had personally
visited the land and building as mentioned in the statement below; he again
failed to mention the date. The stamp of the purported Gram Panchayat on
the last page of the document is that of a Pradhan of Kashiram Nagar, which
place does not appear to be either the Tehsil/Taluka or the City of the
petitoner's institute and this appears to be clear from the order dated
11.9.2015 wherein the details of this institute have been mentioned.
11 In the context of the defence of the time schedule, the Apex Court had an occasion to consider this issue in the case of Maa Vaishno Devi Mahila Mahavidyala Vs. State of Uttar Pradesh and Ors. reported as (2013) 2 SCC 617 and the observation of the Apex Court in this regard would be relevant; the same reads as under:
81. Lastly, the question which is required to be discussed in light of the facts of the present cases is adherence to the Schedule. Once the relevant Schedules have been prescribed under the Regulations or under the Judge made law, none, whosoever it be, is entitled to carve out exceptions to the prescribed Schedule. Adherence to the Schedule is the essence of granting admission in a fair and transparent manner as well as to maintain the
standards of education. The purpose of providing a time schedule is to ensure that all concerned authorities act within the stipulated time. Where, on the one hand, it places an obligation upon the authorities to act according to the Schedule, there it also provides complete clarity to other stakeholders as to when their application would either be accepted and/or rejected and what will be the time duration for it to be processed at different quarters. It also gives clear understanding to the students for whose benefit the entire process is set up as to when their examinations would be held, when results would be declared and when they are expected to take admission to different colleges in order of merit obtained by them in the entrance examinations or other processes for the purposes of subject and college preference.
82. We are constrained to reiterate with emphasis at our command that the prescribed schedules under the Regulations and the judgments must be strictly adhered to without exceptions. None in the hierarchy of the State Government, University, NCTE or any other authority or body involved in this process can breach the Schedule for any direct or indirect reason. Anybody who is found to be defaulting in this behalf is bound to render himself or herself liable for initiation of proceedings under the provisions of the Contempt of Courts Act, 1971 as well as for a disciplinary action in accordance with the orders of the Court."
12 The building completion certificate not having seen the light of the
day before the respondent no.2 or respondent no.1, which even otherwise (on
its scrutiny) suffers from various defects; the impugned orders do not suffer
from any infirmity.
13 Petition dismissed.
INDERMEET KAUR, J
SEPTEMBER 26, 2017
ndn
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!