Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

A.R. Construction vs C.C.C. Infrasys Private Limited
2017 Latest Caselaw 3523 Del

Citation : 2017 Latest Caselaw 3523 Del
Judgement Date : 24 July, 2017

Delhi High Court
A.R. Construction vs C.C.C. Infrasys Private Limited on 24 July, 2017
$~
*     IN THE HIGH COURT OF DELHI AT NEW DELHI
%                                      Reserved on: 11th July, 2017
                                       Pronounced on: 24th July, 2017

+     CO.PET. 548/2015

      A.R. CONSTRUCTION                                   ..... Petitioner
                   Through :          Mr.L.B.Rai,     Mr.Mohit Kumar
                                      Sharma and      Mr.Sumit Nagpal,
                                      Advocates.
                             versus

    C.C.C. INFRASYS PRIVATE LIMITED           ..... Respondent
                   Through : Mr.Dalip Mehra, Advocate.
CORAM:
HON'BLE MR.JUSTICE YOGESH KHANNA

YOGESH KHANNA, J.

1. Petitioner has filed this petition under Section 433 and 434 of the Companies Act, 1956 on the basis of a work order dated 29.09.2014 given by respondent for doing the M.S. Structural work. The rate agreed between the petitioner and respondent was ₹74 per kg for the said work.

2. After getting the work order dated 29.09.2014, the petitioner executed the work successfully at site and raised various invoices for the same. The said invoices are of dated 27.10.2014, 01.12.2014 and 27.12.2014 for total sum of ₹49,54,382/-. The respondent paid an amount of ₹23,26,500/- on account thus leaving a balance of ₹26,27,444/- . Some extra work worth ₹3.00 Lac was directed to be done which also was completed successfully. Hence, the respondent issued four cheques towards balance payment of the invoices raised by the petitioner, of dated

16.01.2015 for ₹9,90,000/-; of dated 01.05.2015 for ₹7,46,444/-; of dated 15.05.2015 for ₹3,00,000/-; and of dated 19.05.2015 for ₹8,91,000/-. All these cheques were dishonoured on the ground 'INSTR STALE (instrument stale) / payment stopped by the drawer. A statutory notice though issued on 03.06.2015, was ignored despite being served upon the respondent company on 10.06.2015. Hence this petition was filed on 04.08.2015.

3. It is the petitioner's case that there was never any complaint received from the respondent company qua the execution of the work but that now in its reply to this petition, the respondent has raised concerns about the quality of the work and also qua certain formalities left to be completed -viz. (a) failure to submit measurements duly certified by M/s Regant Garages Private Limited; (b) failure to furnish the check list certified by M/s Regant Garages Private Limited; (c) submission of no claim undertaking; submission of unconditional acceptance of final bill; submissions of clearance certificate by M/s Regant Garages Private Limited; (d) certain discrepancy in the bills raised by the petitioner and

(e) that such cheques were given only as a security.

4. These objections are raised by the respondent for the first time in its reply to the petition for winding up before this court despite having failed to even respond to the statutory notice and more so when the work has long being executed. Taking such technical objections after many a months of demands raised and after admitting its liability by handing over four cheques for amount totaling to ₹29,27,444/- do show such pleas are afterthought. Now, if the bills were not verified as alleged, then why the cheques for balance amount of ₹29,27,444/- were given at the first

instance. The fact that the cheques were for the balance amount belies the argument that these were for security. Now, if such cheques were given in blank as alleged, then why the respondent did not took prior action to inform the petitioner of not using such cheques or why it did not challenge this fact by replying to the statutory notice of demand.

5. It is necessary to note that the petitioner had filed two criminal complaints against the respondent company, under Section 138 of the Negotiable Instruments Act, 1881, being CC No.393/2015 and CC No.395/2015 for the first two dishonoured cheques; which complaints were rather settled on 29.05.2015 wherein the respondent company undertook to repay an amount of ₹12,50,000/- in installments in lieu of such two dishonoured cheques. However after making payment of the first two installments, the respondent company failed to pay further amount on a plea that compromise was effected for all the four cheques and not for the two cheques which were subject matter of the said complaints.

6. Even while making statement in CC Nos. 393 & 395 (supra) the respondent company did not allege that such cheques were given as security or the petitioner did not complete the work or the formalities as alleged in its reply to this petition. It shows the respondent yet again neglected to pay the debt of the petitioner company by raising frivolous issues. Rather the conduct of respondent in not paying the amount, so settled in complaints aforesaid, without any cogent reasons do show its inability to pay. The respondent cannot allege that it is though solvent but would not pay admitted debt.

7. In IBA Health (I) Pvt. Ltd vs. Info-Drive Systems Sdn. Bhd 2010 (10) SCALE 151 where the Apex Court observed:-

"21. If the company refuses to pay on no genuine and substantial grounds, it should not be able to avoid the statutory demand. The law should be allowed to proceed and if demand is not met and an application for liquidation is filed under Section 439 in reliance of the presumption under Section 434(1)(a) that the company is unable to pay it debts, the law should take its own course and the company of course will have an opportunity on the liquidation application to rebut that presumption.

22. ... If the debt is an undisputedly owing, then it should be paid. If the company refuses to pay, without good reason, it should not be able to avoid the statutory demand by proving, at the statutory demand stage, that it is solvent. In other words, commercial solvency can be seen as relevant as to whether there was a dispute as to the debt, not as a ground in itself, that means it cannot be characterized as a stand alone ground."

8. The contention qua inferior quality of goods, as alleged by the respondent in its reply, can be answered by referring to Lohmann Rausher Gmbh v. Medisphere Marketing Pvt. Ltd. 117(2004) DLT 95 wherein the Court observed :-

"22. Undisputably, goods under first invoice were received in the month of May, 2000 and under the second invoice in the month of September, 2000. Defendant, on receipt of the goods, did not indicate to the plaintiff that the goods were defective till as late as 31.12.2001. This was when the plaintiff had served upon the defendant a legal notice in the month of October, 2001.

xxx xxx

29. The long gap after which goods were ostensibly rejected on the premise that they were defective/sub-standard is clearly fatal to the projected defense in the context of statutory law being Section 41 and 42 of the Sale of Goods Act."

9. As the genuine/admitted demand of the petitioner was neglected by the respondent company without any cogent, substantial or genuine ground, the facts call for an appointment of the Provisional Liquidator.

10. In view of the above, the petition is admitted.

11. Citation be published in the "Statesman" (English edition) and "Jansatta" (Hindi edition) in accordance with Company (Court) Rules, 1959.

12. However, publication of the citation and appointment of the provisional liquidator is deferred and one opportunity is given to the respondent company to pay the amount found already due and payable to the petitioner with interest at the rate of 8% per annum with effect from 03.06.2015 when the statutory notice was served on the respondent company. The amount be paid within one month failing which the petitioner shall be entitled to publish the citation and apply for appointment of the Provisional Liquidator.

13. List for further directions on 26th September, 2017.

YOGESH KHANNA, J JULY 24, 2017 M/DU

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter