Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Brij Lal & Sons vs Union Of India & Anr.
2017 Latest Caselaw 3397 Del

Citation : 2017 Latest Caselaw 3397 Del
Judgement Date : 18 July, 2017

Delhi High Court
M/S Brij Lal & Sons vs Union Of India & Anr. on 18 July, 2017
*            IN THE HIGH COURT OF DELHI AT NEW DELHI

+                         FAO No. 304/2007

%                                                      18th July, 2017

M/S BRIJ LAL & SONS                                      ..... Appellant
                          Through:       Appellant in person.
                          versus

UNION OF INDIA & ANR.                                ..... Respondents

CORAM:

HON'BLE MR. JUSTICE VALMIKI J.MEHTA

To be referred to the Reporter or not?

VALMIKI J. MEHTA, J (ORAL)

1. This first appeal under Section 37 of the Arbitration and

Conciliation Act, 1996 (hereinafter referred to as „the Act‟) impugns

the judgment of the court below dated 13.4.2007 by which the

objections filed by the appellant under Section 34 of the Act have been

dismissed against the Award of the arbitrator dated 10.8.2006. The

only dispute raised before this Court with respect to the objections

under Section 34 of the Act is with respect to item no.4 of the extra

work done. It may be noted that appellant was awarded the work of

doing cross drainage at Road No.57 near subway in East Delhi.

2. After completion of work appellant/contractor claimed

payment for extra items of work done, and one such payment claimed

is with respect to item no.4. This item no.4 has been decided by the

Arbitrator against the appellant by holding that the work done of

Cement Concrete (C.C) in the ratio of 1:5:10 is not of 94.23 cum as

was the case of the appellant/contractor, but the work of Cement

Concrete of 1:5:10 was only of 2.15 cum. The relevant portion of the

Award with respect to item no.4 reads as under:-

"Item 4: Against 52.92 cum of C.C. 1:3:6 paid by Department, contractor has claimed Nil. Against 2.15 cum of C.C. 1:5:10 paid by Department, contractor has claimed 94.23.cum. Respondent pointed out that contractor has quoted Rs.1,400/- per cum for C.C. 1:5:10 but Rs.900/- per cum for C.C. 1:3:6 and there is no reason for Department to go in for C.C. 1:5:10. However, the calculations of cross-sectional area in MB do not appear to be in order since Respondent agreed that C.C. work was projecting above pipe surface. Approximate calculation for sectional area of C.C. around pipe is as follows:

Base: 2.1x 0.3=0.63 sqm Overall up to center of pipe: 2.1 x 0.75 = 1.575 Above center of pipe: 22/7 x 1.05 x 1.05/2= 1.732 Deduct for pipe 22/7 x 0.75 = (-) 1.768 Net area= 2.169 sqm Quantity for pipe length = 45.11 x 2.169 = 97.84 cum Add for manhole 2.60 x 1.5 x 0.3 = 1.17 cum Total quantity = 99.01 cum.

As such, total quantity of 94.23 cum claimed by contractor is accepted. Amount of C.C 1:5:10 = 2.15 x 1400= 3,010 Amount of C.C. 1:3:6=92.08 x 900== 82,872 Total amount= Rs.85,882/-

Payment already made = Rs.50,638/-

Additional payment worked out= Rs.35,244/-."

3. Arbitrator is a technical person as admittedly he was an

engineer. The Arbitrator has held that though there is no dispute that

total quantity of work done under item no.4 was of 94.23 cum but the

work done of the Cement Concrete of 1:5:10 was only 2.15 cum and

not 94.23 cum inasmuch as the balance work of 92.08 cum out of the

total of 94.23 cum was done in the ratio of 1:3:6. This Court cannot sit

as an appellate court over the findings and conclusions of the

Arbitrator and it is not even pointed out to this Court that there is any

measurement book of the work showing that work done of 94.23 cum

is done in the ratio of 1:5:10 instead of only 2.15 cum work done at

1:5:10 as recorded in the Award. I therefore do not find any error in

the Award which makes the Award illegal or perverse or in violation

of the ingredients of Section 34 of the Act.

4. The court below has also held that the Arbitrator after

considering respective cases, when he takes a view, a civil court

hearing objections under Section 34 of the Act is not to sit as an

appellate court to re-apprise the findings of facts and conclusions of

the Arbitrator. I agree.

5. Though appellant relies upon a theoretical statement,

however, a theoretical statement prepared and submitted during the

course of work done by Union of India cannot change the fact that the

final measurements recorded for the work show the work of Cement

Concrete work done in the ratio of 1:5:10 only of 2.15 cum.

6. There is no merit in the appeal and the same is therefore

dismissed.

JULY 18, 2017/ib                           VALMIKI J. MEHTA, J





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter