Citation : 2017 Latest Caselaw 57 Del
Judgement Date : 4 January, 2017
$~28
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO(OS) (COMM) 2/2017
Date of Decision: 04th January 2017
TEYMA INDIA PRIVATE LIMITED ..... Appellant
Through Mr. Rakesh Sinha and Mr. Pawan Kr.
Bansal, Advocates.
versus
JITF WATER INFRASTRUCTURE PRIVATE LIMITED & ANR
..... Respondents
Through Mr. Manoj K. Singh and Ms. Nilam
Bandyopadhyay, Advocates for
respondent no. 1.
Ms. Jagriti Ahuja and Mr. Gowtham,
Advocates for respondent no. 2.
CORAM:
HON'BLE MS. JUSTICE INDIRA BANERJEE
HON'BLE MR. JUSTICE ANIL KUMAR CHAWLA
JUDGEMENT
INDIRA BANERJEE, J. (ORAL)
Caveat Pet. No. 4/2017
Since the caveator has put in appearance through counsel, the caveat
stands discharged.
CM No. 117/2017 Exemption allowed, subject to all just exceptions.
The application stands disposed of.
CM No. 115/2017 (delay) This is an application seeking condonation of delay of 7 days in filing
the appeal. For the reasons stated in the application, the delay of about 7
days in filing the appeal is condoned.
The application stands disposed of.
FAO(OS) (COMM) 2/2017 and CM Nos. 116/2017 (stay) and 118/2017 (for permission to file additional documents)
1. This appeal filed under Section 37(1) of the Arbitration and
Conciliation Act, 1996, is against a judgment and order dated 09.11.2016
passed by the learned Single Bench dismissing the application of the
appellant for interim relief.
2. By the judgment and order impugned, the learned Single Bench
rejected the prayer of the appellant for orders restraining the respondent
from encashing a bank guarantee furnished by the appellant in favour of the
respondent-JITF Water Infrastructure Private Limited.
3. On or about 10.12.2014, Uttrakhand Urban Sector Development
Agency ("UUSDA") entered into a contract with the respondent no.1, M/s
JITF Water Infrastructure Private Limited, for engineering, procurement,
construction, supplying, laying, testing and commissioning of water supply
distribution system for 19 geographic zones in Dehradun.
4. The contract, hereinafter referred to as the main contract, provided for
sub-contract of the contractual work. On or about 28.06.2015, the
respondent no.1 entered into a contract dated 28.06.2015 with the appellant
whereby the respondent no.1 sub-contracted the contract job to the appellant
on back to back basis.
5. In terms of the agreement between the respondent and the appellant,
the appellant was required to furnish a bank guarantee which the appellant
duly furnished for an amount of Rs.3,76,25,000/-. The bank guarantee is
referred to as the first bank guarantee. The appellant issued a second bank
guarantee for an amount of Rs.6,09,88,271.30 which is referred to as the
second bank guarantee, as required in terms of the sub-contract.
6. It appears that several disputes arose between the respondent no.1 and
the appellant with regard to the execution of the sub-contract, with which we
are not concerned at this stage.
7. It is well settled that the bank guarantee constitutes an independent
contract between the bank which issues the bank guarantee and the
beneficiary of the bank guarantee. A bank guarantee, and more particularly
an unconditional bank guarantee, is in no way concerned with the
underlying disputes between the party at whose instance the bank guarantee
has been furnished and the beneficiary of the bank guarantee.
8. It is well settled that an order restraining the invocation of a bank
guarantee can only be passed in rare cases of fraud in relation to the bank
guarantee, in cases of irretrievable injustice, or where special equity exists in
favour of the person at whose instance the bank guarantee has been
furnished. Fraud must be in connection with the invocation of the bank
guarantee.
9. If the invocation of a bank guarantee is not in terms of the bank
guarantee, invocation may be restrained. However, this is not a case where it
can be said that invocation is not in accordance with terms of the bank
guarantee. In fact, it is not even the case of the appellant, that the invocation
is not in accordance with the bank guarantee. Particulars of alleged fraud
allegedly committed by the respondent no. 1 have been pleaded in paragraph
7.1 of the petition filed before the learned Single Bench under Section 9 (1)
of the Arbitration and Conciliation Act, 1996. The pleadings in paragraph
7.1 do not disclose any act of fraud in the matter of invocation of the bank
guarantee.
10. It has strenuously been argued on behalf of the appellant that the
respondent no. 1 acted wrongfully in invoking the bank guarantees when the
Uttrakhand Urban Sector Development Agency had not invoked the bank
guarantees furnished by the respondent to Uttrakhand Urban Sector
Development Agency. Unfortunately, however, it was not a condition of the
bank guarantees that invocation thereof would be subject to invocation by
Uttrakhand Urban Sector Development Agency of the bank guarantees
furnished to them.
11. Principles of irretrievable injustice and special equity can be invoked
only in case of apparent illegality coupled with a situation where the party
furnishing a bank guarantee would never be able to recover the proceeds of
the bank guarantee. At least, there are no pleadings to the effect that in the
event the bank guarantee is invoked and if ultimately, the invocation is held
to be wrongful, the appellant would never be able to recover the proceeds
from the respondent.
12. The learned Single Bench has rightly held:
"The law relating to interdiction of bank guarantees is now well settled; the same cannot be interdicted unless the party seeking interdiction is able to establish a prima facie case of egregious fraud and irretrievable injustice. (See: Svenska Handelsbanken v. M/s. Indian Charge Chrome and Others: (1994) 1 SCC 502 and U.P. Cooperative Federation Limited v. Singh Consultants and Engineers Pvt. Ltd.: 1988 (1) SCC
174)."
13. It may also be pertinent to refer to the following observation of the
learned Single Bench.
"The reliance placed by the petitioner on the letter dated 30.06.2016 sent by respondent no. 1 to the principal employer is also not determinative of the dispute between the parties. It is relevant to note that the said response clearly stated that it was "without prejudice". Further, the said response was issued by the respondent no. 1 to dissuade the principal employer from taking action that the principal employer proposed to take against respondent no. 1. While respondent no. 1 was defending the issue regarding delays and poor work with the principal employer, it also informed the petitioner as to the said controversy, which directly related to the subject contract between respondent no. 1 and the petitioner.
It is also not in dispute that the principal employer has terminated the contract with respondent no. 1, inter alia, alleging poor performance."
14. The learned counsel appearing on behalf of the appellant submitted
that orders may be passed directing the respondent who has already invoked
the bank guarantee to deposit the proceeds in the registry of this Court. It is,
however, well settled that what cannot be done directly cannot be done
indirectly. If the Court cannot restrain the invocation of the bank guarantee,
the Court cannot indirectly restrain the beneficiary of the bank guarantee
from enjoying the proceeds of the bank guarantee. We find no grounds to
interfere with the order under appeal. The appeal is dismissed.
15. It is made clear that any observations in this order are prima facie
observations which will not sway the arbitration proceedings in any manner.
Since the appeal is dismissed, the applications mentioned herein have become infructuous, and shall stand disposed of.
16. Dasti.
INDIRA BANERJEE, J
ANIL KUMAR CHAWLA, J JANUARY 04, 2017 rs
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!